Procurement Mgmt Input/Output Definitions Flashcards

1
Q

Activity Cost Estimates

A

These are quantitative assessments of the probably costs required to complete project work. Can be presented in detailed or summary form and will usually contain:

  • Direct Labor
  • Materials
  • Equipment
  • Services
  • IT, etc.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Activity Resource Requirements

A

This is an output of the process 6.3 Estimate Activity Resources. This contains the preliminary requirements for the people needed on the project. This is elaborated as part of this process.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Approved Change Requests

A

Perform Integrated Change Control (process 4.5) is where requests for changes are approved or rejected. Approved change requests are scheduled for implementation by the project team. Approved change requests are changes to expand/reduce project scope or a modification of policies.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Change Requests

A

If during the course of executing the project, issues develop that require a change to the scope, budget, or schedule, or quality, then change requests are developed. Note that the change requests are made in the Executing Progress Group, but are evaluated and either accepted or rejected as part of the Monitoring & Controlling Progress Group. If they are accepted, these changes get fed into the Executing Progress Group once again.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Closed Procurements

A

The buyer provides the seller with formal written notice that the deliverables have been received and approved, and that the contract has been completed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Contract

A

A contract is a mutually binding agreement that obligates the seller to provide the specified product or service or result and obligates the buyer to pay for it.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Cost Performance Baseline

A

A specific version of the time-phased budget used to compare actual expenditures to planned expenditures to determine if preventive or corrective action is needed to meet the project objectives.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

EEF

A

This is the “company culture”, or factors that are external to the project but which influence the project’s success. These can include the company databases and, in particular, the project management software used by the company. Think of them as “soft copy” (software and the company culture or “unwritten rules” that govern how work is done).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Make-or-buy Decisions

A

This documents the conclusion of the decision regarding which products, services, or results of the product will be acquired from outside the project organization as opposed to being performed internally by the project team. This includes not just issues of cost, but issues of risk as well.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

OPA

A

Written procedures, policies, and guidelines that are used by the company to guide all operations, including projects. Lessons learned would be an important part of OPA. Think of the operational process assets as the “hard copy” (written procedures)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Performance Reports

A

Performance reports communicate project performance and status information with regard to scope, schedule, cost, quality, resources and risks to various stakeholders as per the Communication Management Plan. They provide summarized project status, forecasts, EV information, variance analysis, seller performance reports, significant achievements, status of risks, and project issues.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Procurement Contract Award

A

A procurement contract is awarded to each selected seller.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Procurement Documentation

A

This includes the procurement contract, technical documentation, and other work performance information.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Procurement Documents

A

These are the documents used to solicit proposals from prospective sellers. These may include a Request for Information (RFI), Invitation for Bid (IFB), Request for Proposal (RFP), and/or Request for Quotation (RFQ).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Procurement Management Plan

A

The document that describes how procurement processes from developing procurement documentation through contract closure will be managed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Procurement Statements of Work

A

The Statement of Work or SOW defines only that portion of the project scope which is to be included within the related contract. It describes the item to be procured in sufficient detail to allow prospective sellers to determine if they are capable of providing it. The SOW is included in the procurement documents

17
Q

Project Documents

A
  • Project documents that are considered include:
    o Risk register
    o Risk-related contract decisions
18
Q

Project Management Plan

A

A formal, approved document that defines how the project is executed, monitored, and controlled. It will be composed of one or more subsidiary management plans and other planning documents.

19
Q

Project Management Plan Updates

A

If the project management plan is changed or the performance baseline is changed, then updates to these are made.

20
Q

Project Schedule

A

The project schedule contains information on required timelines or mandated deliverable dates. This can be in the form of a bar chart, project schedule network diagram, and/or a milestone chart.

21
Q

Qualified Seller List

A

This is a list of sellers who have been qualified as sellers on previous projects with the company.

22
Q

Requirements Documentation

A

The whole purpose of this process is to take high-level requirements and make them more detailed.
The requirements document describes how individual requirements meet the business need for the project. The document lists all the requirements categorized by stakeholder and priority.

23
Q

Resource Calendars

A

A calendar of working days and nonworking days that determines those dates on which each specific resource is idle or can be active. Typically defines resource specific holidays and resource availability periods.

24
Q

Risk Register

A

The risk register identifies each risk, indicates the chances and what impact it would have on the project if the risk were to occur, and identifies potential responses to that risk.

25
Q

Risk-Related Contract Decisions

A

Decisions to transfer risk, such as agreements for insurance, services, etc. are selected in this process. This may happen as a result of mitigating or transferring part or all of the risk involved in part of the project. The contract type selected also provides a mechanism for sharing risks.

26
Q

Scope Baseline

A

The scope baseline is a component of the PM Plan. Components of the scope baseline include:

  • Project Scope Statement: this includes the product scope description, the project deliverables, and defines the product user acceptance criteria.
  • WBS: this defines each deliverable and the decomposition of the deliverables into work packages.
  • WBS Dictionary: this has a detailed description of work and technical documentation for each WBS element.
27
Q

Selected Sellers

A

The sellers are those selected based on the evaluation of their proposal or bid.

28
Q

Seller Proposals

A

The proposals by the sellers form the basic information used to select one or more successful bidders.

29
Q

Source Selection Criteria

A

These criteria include such things as the risk involved, the overall cost, the financial capacity of the seller, intellectual property issues, etc.

30
Q

Teaming Agreements

A

Teaming agreements are legal contractual agreements between the parties to form a partnership or joint-venture. The agreement defines the roles for both parties. Whenever the new business venture ends, the teaming agreement ends. This will affect the planning process heavily in scope of work, competition requirements, and other critical issues by predefining the work to be done.

31
Q

Work Performance Information

A

Information and data, on the status of the project schedule activities being performed to accomplish the project work. Information includes:

  • Status of deliverables
  • Implementation of change requests
  • Corrective & Preventive actions/ Defect Repair
  • Status of work completed
  • Achieved value of technical performance measures