Cost Mgmt Input/Output Definitions Flashcards

1
Q

Activity Cost Estimates

A

These are quantitative assessments of the probably costs required to complete project work. Can be presented in detailed or summary form and will usually contain:

  • Direct Labor
  • Materials
  • Equipment
  • Services
  • IT, etc.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Basis of Estimates

A

Documentation of assumptions made, known constraints, range of estimates, and confidence level of estimate.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Budget Forecasts

A

Either a calculated EAC value or a bottom-up EAC value is documented and communicated to stakeholders. EAC or the estimate to completion is calculated using one of the formulas
EAC = AC + (BAC – EV)
EAC = AC + (BAC – EV)/CPI
EAC = AC + (BAC – EV)/CPI*SPI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Change Requests

A

If during the course of executing the project, issues develop that require a change to the scope, budget, or schedule, or quality, then change requests are developed. Note that the change requests are made in the Executing Progress Group, but are evaluated and either accepted or rejected as part of the Monitoring & Controlling Progress Group. If they are accepted, these changes get fed into the Executing Progress Group once again.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Contract

A

A contract is a mutually binding agreement that obligates the seller to provide the specified product or service or result and obligates the buyer to pay for it.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Cost Performance Baseline

A

A specific version of the time-phased budget used to compare actual expenditures to planned expenditures to determine if preventive or corrective action is needed to meet the project objectives.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

EEF

A

This is the “company culture”, or factors that are external to the project but which influence the project’s success. These can include the company databases and, in particular, the project management software used by the company. Think of them as “soft copy” (software and the company culture or “unwritten rules” that govern how work is done).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Human Resource Plan

A

The human resource plan contains the following elements
• Roles and responsibilities for the project
• Project organizational charts
• Staffing management plan (resource calendars, training needs, criteria for recognition and rewards)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

OPA

A

Written procedures, policies, and guidelines that are used by the company to guide all operations, including projects. Lessons learned would be an important part of OPA. Think of the operational process assets as the “hard copy” (written procedures)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Project Document Updates

A

Any time there has been a change that will impact the project it must be documented and the stakeholder’s must be informed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Project Funding Requirements

A

Funding requirements for each period (quarter or year) are derived from the cost baseline.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Project Management Plan

A

The document that describes how procurement processes from developing procurement documentation through contract closure will be managed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Project Management Plan Updates

A

If the project management plan is changed or the performance baseline is changed, then updates to these are made.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Project Schedule

A

The project schedule contains information on required timelines or mandated deliverable dates. This can be in the form of a bar chart, project schedule network diagram, and/or a milestone chart.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Resource Calendars

A

A calendar of working days and nonworking days that determines those dates on which each specific resource is idle or can be active. Typically defines resource specific holidays and resource availability periods.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Risk Register

A

The risk register is an output of the 11.2 Identify Risks process, and is updated as part of the 11.3 Perform Qualitative Risk Analysis process. It is further updated as part of this process by additional of the following categories of information: probabilistic analysis of the project, probability of achieving cost and time objectives, prioritized list of quantified risks, and trends in quantitative risk analysis results.

17
Q

Scope Baseline

A

The scope baseline is a component of the PM Plan. Components of the scope baseline include:

  • Project Scope Statement: this includes the product scope description, the project deliverables, and defines the product user acceptance criteria.
  • WBS: this defines each deliverable and the decomposition of the deliverables into work packages.
  • WBS Dictionary: this has a detailed description of work and technical documentation for each WBS element.
18
Q

Work Performance Information

A

Information and data, on the status of the project schedule activities being performed to accomplish the project work. Information includes:

  • Status of deliverables
  • Implementation of change requests
  • Corrective & Preventive actions/ Defect Repair
  • Status of work completed
  • Achieved value of technical performance measures
19
Q

Work Performance Measurements

A
Work performance measurements are used to produce project activity metrics to evaluate actual progress as compared to planned progress. These metrics include:
-	Planned vs. Actual
o	Technical Performance
o	Schedule Performance
o	Cost Performance