Quality Mgmt Input/Output Definitions Flashcards
Approved Change Requests
Perform Integrated Change Control (process 4.5) is where requests for changes are approved or rejected. Approved change requests are scheduled for implementation by the project team. Approved change requests are changes to expand/reduce project scope or a modification of policies.
Change Requests
If during the course of executing the project, issues develop that require a change to the scope, budget, or schedule, or quality, then change requests are developed. Note that the change requests are made in the Executing Progress Group, but are evaluated and either accepted or rejected as part of the Monitoring & Controlling Progress Group. If they are accepted, these changes get fed into the Executing Progress Group once again.
Cost Performance Baseline
A specific version of the time-phased budget used to compare actual expenditures to planned expenditures to determine if preventive or corrective action is needed to meet the project objectives.
Deliverables
Deliverables that meet the acceptance criteria are formally signed off and approved by the customer and sponsor.
EEF
This is the “company culture”, or factors that are external to the project but which influence the project’s success. These can include the company databases and, in particular, the project management software used by the company. Think of them as “soft copy” (software and the company culture or “unwritten rules” that govern how work is done).
OPA
Written procedures, policies, and guidelines that are used by the company to guide all operations, including projects. Lessons learned would be an important part of OPA. Think of the operational process assets as the “hard copy” (written procedures)
Process Improvement Plan
- Process boundaries (their purpose, start and end, inputs/outputs, data required, stakeholders involved)
- Process configuration (graphical depiction of processes used to facilitate analysis)
- Process metrics (with control limits)
- Targets for performance improvement
Project Document Updates
Any time there has been a change that will impact the project it must be documented and the stakeholder’s must be informed.
Project Management Plan
A formal, approved document that defines how the project is executed, monitored, and controlled. It will be composed of one or more subsidiary management plans and other planning documents.
Project Management Plan Updates
If the project management plan is changed or the performance baseline is changed, then updates to these are made.
Quality Checklists
Component-specific checklist used to verify that required steps have been performed. This is done to ensure consistency in frequently performed tasks.
Quality Control Measurements
Quality control measurements are the results of quality control activities. They are used to analyze and evaluate the quality standards and processes of the performing organization.
Quality Management Plan
This plan documents how the requirements will be analyzed, documented, and managed throughout the project.
Quality Metrics
This describes a project or product attribute and how the quality control process will measure it. The tolerance defines the allowable variations on the metrics. Quality metrics are used in the quality assurance and quality control processes.
- On-time performance
- Budget control
- Defect frequency
- Failure rate
- Test coverage
Risk Register
The risk register identifies each risk, indicates the chances and what impact it would have on the project if the risk were to occur, and identifies potential responses to that risk.