Time Management Flashcards
What is the process of time management?
Plan schedule management, define activities, sequence activities, estimate activity resources, estimate activity durations, develop schedule, control schedule
What is the key output of the Plan Schedule Management process?
Schedule management plan
What are the key outputs of the Define Activities process?
Activity listActivity attributesMilestone list
What are the key outputs of the Sequence Activities process
Network diagramsUpdates to the project documents
What are some of the key outputs of the Estimate Activity Resources process?
Activity resource requirementsResource breakdown structure
What are the key outputs of the Estimate Activity Durations process?
Activity duration estimatesUpdates to the project documents
What does the Develop Schedule process involve?What are some key outputs?
Creating a project schedule that is bought into, aproved, realistic, and formalProject scheduleSchedule baselineUpdates to the project management plan and project documents
What are the key outputs of the Control Schedule process?
Work performance informationSchedule forecastsChange requests
What are the four types of logical relationships between activities in the precedence diagramming method?
Finish-to-Start (FS): An activity must finish before the successor can startStart to Start (SS): An activity must start before the successor can startFinish to Finish (FF): An activity must finish before the successor can finishStart to Finish (SF): An activity must start before the successor can finish
What are mandatory dependencies?What are discretionary dependencies?
Mandatory: the order in which the activities MUST be done, due to the inherent nature of the work; also called “hard logic”Disretionary: the order in which the organization has CHOSEN that activities be performed; also called preferred, preferential, or soft logic
What are external dependencies?What are internal dependencies?
External: dependencies based on the need of a party OUTSIDE the projectInternal: dependencies based on the needs of the project; may be under the control of the project team
What is lag?What is lead?
Lag: waiting time inserted between activitiesLead: how soon an activity can start before its predecessor activity is completed
What is a resource breakdown structure?
An organizational chart or table showing identified resources, organized by category and type
How does a schedule model differ from a schedule?
The schedule model consists of all the project data that will be used to calculate the schedule, such as the activities, dependencies, leads and lags, etc.The project schedule is the output of the schedule model - this refers to the final printed dates that make up the schedule that becomes the baseline and part of the project management plan
What is the critical path?What is the near-critical path?
Critical: the longest path through the network diagramNear-critical: the path closest in length to the critical path