Time Management Flashcards

1
Q

What is the process of time management?

A

Plan schedule management, define activities, sequence activities, estimate activity resources, estimate activity durations, develop schedule, control schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the key output of the Plan Schedule Management process?

A

Schedule management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the key outputs of the Define Activities process?

A

Activity listActivity attributesMilestone list

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the key outputs of the Sequence Activities process

A

Network diagramsUpdates to the project documents

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are some of the key outputs of the Estimate Activity Resources process?

A

Activity resource requirementsResource breakdown structure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the key outputs of the Estimate Activity Durations process?

A

Activity duration estimatesUpdates to the project documents

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What does the Develop Schedule process involve?What are some key outputs?

A

Creating a project schedule that is bought into, aproved, realistic, and formalProject scheduleSchedule baselineUpdates to the project management plan and project documents

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the key outputs of the Control Schedule process?

A

Work performance informationSchedule forecastsChange requests

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the four types of logical relationships between activities in the precedence diagramming method?

A

Finish-to-Start (FS): An activity must finish before the successor can startStart to Start (SS): An activity must start before the successor can startFinish to Finish (FF): An activity must finish before the successor can finishStart to Finish (SF): An activity must start before the successor can finish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are mandatory dependencies?What are discretionary dependencies?

A

Mandatory: the order in which the activities MUST be done, due to the inherent nature of the work; also called “hard logic”Disretionary: the order in which the organization has CHOSEN that activities be performed; also called preferred, preferential, or soft logic

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are external dependencies?What are internal dependencies?

A

External: dependencies based on the need of a party OUTSIDE the projectInternal: dependencies based on the needs of the project; may be under the control of the project team

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is lag?What is lead?

A

Lag: waiting time inserted between activitiesLead: how soon an activity can start before its predecessor activity is completed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is a resource breakdown structure?

A

An organizational chart or table showing identified resources, organized by category and type

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How does a schedule model differ from a schedule?

A

The schedule model consists of all the project data that will be used to calculate the schedule, such as the activities, dependencies, leads and lags, etc.The project schedule is the output of the schedule model - this refers to the final printed dates that make up the schedule that becomes the baseline and part of the project management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the critical path?What is the near-critical path?

A

Critical: the longest path through the network diagramNear-critical: the path closest in length to the critical path

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How does the critical path help us manage the project?

A

It shows the project manager the shortest time in which the project can be completedIt shows the project manager where to focus his/her timeIt is used in compressing or adjusting the schedule

17
Q

Define total float, free float, and project float

A

Total float: the amount of time an activity can be delayed without delaying the project end date or an intermediary milestoneFree float: the amount of time an activity can be delayed without delaying the early start date of its successor(s)Project float: the amount of time the project can be delayed without affecting the projects required end date

18
Q

What are the two formulas for calculating float?

A

Late start - early startORLate finish - early finish

19
Q

What are the methods that can be used to compress a schedule?

A

CrashingFast Tracking

20
Q

What is crashing?

A

Adding or adjusting resources in order to compress the schedule while maintaining the original project scope

21
Q

What is fast tracking?

A

Compressing the schedule by doing more critical path activities in parallel

22
Q

What is the critical chain method?

A

A schedule network analysis tool that builds in buffers at critical milestones

23
Q

What is reestimating?

A

Estimating the project again after planning to make sure you can still meet the end date, budget, or other objectives, and adjusting the project if you cannot

24
Q

What is resource optimization?

A

Finding ways to adjust the use of resources

25
Q

What is resource leveling?

A

A resource optimization technique that keeps the amount of resources used for each time period constant, resulting in a more stable level of resources and a longer project duration

26
Q

What is resource smoothing?

A

A modified form of resource leveling where resources are leveled only within the limits of the float of their activities, so the completion dates of activities are not delayed

27
Q

What is the schedule baseline?

A

The approved version of the schedule model, along with any approved changes, used to measure the project schedule performance

28
Q

What are the main presentation formats for a schedule?

A

Network diagramBar chartsMilestone charts

29
Q

What do network diagrams show?

A

Dependencies (logical relationships) between activitiesHow project activities will flow from beginning to endMay also be used to determine the critical path

30
Q

What do simple bar charts show?

A

Project schedule or project status

31
Q

What do milestone charts show?

A

High-level project status

32
Q

What is Monte Carlo analysis?

A

A schedule network analysis technique used to simulate the project to determine the likelihood that the project will be completed by a specific date or for a specific costAlso used in Perform Quantitative Risk Analysis to determine the overall level of risk on the project