Time Management Flashcards
What are the four types of logical relationships between activities in the precedence diagramming method?
Finish-to-Start (FS): An activity must finish before the successor can start
Start to Start (SS): An activity must start before the successor can start
Finish to Finish (FF): An activity must finish before the successor can finish
Start to Finish (SF): An activity must start before the successor can finish
What are the key outputs of the Control Schedule process?
Work performance information
Schedule forecasts
Change requests
What are mandatory dependencies?
What are discretionary dependencies?
Mandatory: the order in which the activities MUST be done, due to the inherent nature of the work; also called “hard logic”
Disretionary: the order in which the organization has CHOSEN that activities be performed; also called preferred, preferential, or soft logic
What are external dependencies?
What are internal dependencies?
External: dependencies based on the need of a party OUTSIDE the project
Internal: dependencies based on the needs of the project; may be under the control of the project team
What is lag?
What is lead?
Lag: waiting time inserted between activities
Lead: how soon an activity can start before its predecessor activity is completed
What is a resource breakdown structure?
An organizational chart or table showing identified resources, organized by category and type
How does a schedule model differ from a schedule?
The schedule model consists of all the project data that will be used to calculate the schedule, such as the activities, dependencies, leads and lags, etc.
The project schedule is the output of the schedule model - this refers to the final printed dates that make up the schedule that becomes the baseline and part of the project management plan
What is the critical path?
What is the near-critical path?
Critical: the longest path through the network diagram
Near-critical: the path closest in length to the critical path
How does the critical path help us manage the project?
It shows the project manager the shortest time in which the project can be completed
It shows the project manager where to focus his/her time
It is used in compressing or adjusting the schedule
Define total float, free float, and project float
Total float: the amount of time an activity can be delayed without delaying the project end date or an intermediary milestone
Free float: the amount of time an activity can be delayed without delaying the early start date of its successor(s)
Project float: the amount of time the project can be delayed without affecting the projects required end date
What are the two formulas for calculating float?
Late start - early start
OR
Late finish - early finish
What are the methods that can be used to compress a schedule?
Crashing
Fast Tracking
What is crashing?
Adding or adjusting resources in order to compress the schedule while maintaining the original project scope
What is fast tracking?
Compressing the schedule by doing more critical path activities in parallel
What is the critical chain method?
A schedule network analysis tool that builds in buffers at critical milestones