Time Management Flashcards

0
Q

What are the four types of logical relationships between activities in the precedence diagramming method?

A

Finish-to-Start (FS): An activity must finish before the successor can start
Start to Start (SS): An activity must start before the successor can start
Finish to Finish (FF): An activity must finish before the successor can finish
Start to Finish (SF): An activity must start before the successor can finish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
1
Q

What are the key outputs of the Control Schedule process?

A

Work performance information
Schedule forecasts
Change requests

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are mandatory dependencies?

What are discretionary dependencies?

A

Mandatory: the order in which the activities MUST be done, due to the inherent nature of the work; also called “hard logic”
Disretionary: the order in which the organization has CHOSEN that activities be performed; also called preferred, preferential, or soft logic

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are external dependencies?

What are internal dependencies?

A

External: dependencies based on the need of a party OUTSIDE the project
Internal: dependencies based on the needs of the project; may be under the control of the project team

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is lag?

What is lead?

A

Lag: waiting time inserted between activities
Lead: how soon an activity can start before its predecessor activity is completed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is a resource breakdown structure?

A

An organizational chart or table showing identified resources, organized by category and type

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How does a schedule model differ from a schedule?

A

The schedule model consists of all the project data that will be used to calculate the schedule, such as the activities, dependencies, leads and lags, etc.
The project schedule is the output of the schedule model - this refers to the final printed dates that make up the schedule that becomes the baseline and part of the project management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the critical path?

What is the near-critical path?

A

Critical: the longest path through the network diagram

Near-critical: the path closest in length to the critical path

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How does the critical path help us manage the project?

A

It shows the project manager the shortest time in which the project can be completed
It shows the project manager where to focus his/her time
It is used in compressing or adjusting the schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Define total float, free float, and project float

A

Total float: the amount of time an activity can be delayed without delaying the project end date or an intermediary milestone
Free float: the amount of time an activity can be delayed without delaying the early start date of its successor(s)
Project float: the amount of time the project can be delayed without affecting the projects required end date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the two formulas for calculating float?

A

Late start - early start
OR
Late finish - early finish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the methods that can be used to compress a schedule?

A

Crashing

Fast Tracking

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is crashing?

A

Adding or adjusting resources in order to compress the schedule while maintaining the original project scope

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is fast tracking?

A

Compressing the schedule by doing more critical path activities in parallel

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the critical chain method?

A

A schedule network analysis tool that builds in buffers at critical milestones

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is reestimating?

A

Estimating the project again after planning to make sure you can still meet the end date, budget, or other objectives, and adjusting the project if you cannot

16
Q

What is resource optimization?

A

Finding ways to adjust the use of resources

17
Q

What is resource leveling?

A

A resource optimization technique that keeps the amount of resources used for each time period constant, resulting in a more stable level of resources and a longer project duration

18
Q

What is resource smoothing?

A

A modified form of resource leveling where resources are leveled only within the limits of the float of their activities, so the completion dates of activities are not delayed

19
Q

What is the schedule baseline?

A

The approved version of the schedule model, along with any approved changes, used to measure the project schedule performance

20
Q

What are the main presentation formats for a schedule?

A

Network diagram
Bar charts
Milestone charts

21
Q

What do network diagrams show?

A

Dependencies (logical relationships) between activities
How project activities will flow from beginning to end
May also be used to determine the critical path

22
Q

What do simple bar charts show?

A

Project schedule or project status

23
Q

What do milestone charts show?

A

High-level project status

24
Q

What is Monte Carlo analysis?

A

A schedule network analysis technique used to simulate the project to determine the likelihood that the project will be completed by a specific date or for a specific cost
Also used in Perform Quantitative Risk Analysis to determine the overall level of risk on the project