What is the process of risk management?
Plan risk management Identify risks Perform qualitative risk analysis Perform quantitative risk analysis Plan risk responses Control risks
What is the key output of the Plan Risk Management process?
Risk management plan
What is the key output of the Identify Risks process?
Risk register
What key outputs of the Perform Qualitative Risk Analysis process are added to the risk register?
Risk ranking for the project
Prioritized risks and their probability and impact ratings
Risks grouped by category
List of risks requiring additional analysis and response
List of risks requiring analysis in the near term
Watch list (noncritical risks)
What key outputs of the Perform Quantitative Risk Analysis process are added to the risk register?
Prioritized list of quantified risks, initial amount of contingency time and cost reserves needed, possible realistic and achievable completion dates and project costs, quantified probability of meeting project objectives, trends in quantitative risk analysis
What key outputs of the Plan Risk Responses are added to the risk register?
Residual risks, contingency plans, fallback plans, risk owners, secondary risks, risk triggers, contracts, reserves for time and cost
What are the key outputs of the Control Risks process?
Work performance informaiton, risk register updates, change requests, updates to the project management plan and project documents, updates to organizational project assets
What key outputs of the Control Risks process are added to the risk register?
Outcomes of risk reassessments and risk audits, results of implemented risk responses, updates to previous parts of risk management, closing of risks that are no longer applicable, details of what happened when risks occured, lessons learned
What is a risk?
A future occurrence that may or may not happen that can have a positive (opportunity) or negative (threat) impact on the project
What are the four key factors that need to be determined for each risk?
Probability, impact, timing, frequency
A person who is risk averse is:
Unwilling to take risks
Define risk appetite, risk tolerance, and risk threshold.
Appetite: a general high-level description of the acceptable level of risk
Tolerance: a measurable amount of acceptable risk
Threshold: the specific point at which risk become unacceptable
What are the inputs to the risk management process?
Project background information and other organizational process assets, enterprise environmental factors, project charter, network diagram, and other project documents, project management plan (including scope baseline and the knowledge area plans, time and cost estimates, procurement documents, stakeholder register, risk register, work performance data and reports
What are some examples of sources of risk?
Technical, project management, schedule, cost, quality, scope, resources, customer satisfaction
What are some examples of risk identification techniques?
Documentation reviews, information-gathering techniques, SWOT analysis (strengths, weaknesses, opportunities, threats), checklist analysis, assumptions analysis, diagramming techniques