TIA Ramdal - MOC EXAM 1st Attemp Flashcards
PMP PREP
Difference resource breakdown structure and resource requirements
The resource breakdown structure is a breakdown of the resources by categories or types
The resource requirements describe all the resources needed to complete an activity.
In which Process, the PM assess the team’s performance and try to improve it
During the executing process group, the project manager will assess the team’s performance and try to improve it through the executing process of developing and managing the team.
Difference Ressource leveling and smoothing
- Resource leveling is a technique used when resources are limited or over-allocated. Resource leveling ensures that no resource is assigned to more than one activity at a time, ensuring that no resource is overworked.
- Resource smoothing may accomplish the same task, but it only works if there is slack available on the activities.
difference Lag and Led
- Free float is the amount of time you can delay an activity without delaying the next activity.
- Lag is the amount of time you need to delay an activity before the next activity starts.
Difference Manage and Control Quality
Manage quality is an executing process where you will improve processes by conducting audits and process analysis.
<aside>
💡 Manage Quality is about **PROCESSES** / Control quality is about **Delivrables**
</aside>
What to do with changes OUTSIDE scope
Although all change requests should be considered by the project manager, they should be related to the project work. No change should be approved if it is outside the scope of the project charter, since that would not be considered work within the current project.
If a change request is denied by the CCB, what to do
You should not add changes to a project management plan without it being first approved, and there is no need to inform the change control board again since its members have already denied it.
Once a change has been approved,
Once a change has been approved, it is time to execute the change, which is done in the executing process of direct and manage project work.
Difference Validate Scope and control quality
- Control quality is done to check the deliverables to ensure they meet the quality requirements.
- Validate scope is done to get formal acceptance from the stakeholders.
What is included in the Project Scope Statement
The project scope statement would have a list of deliverables and include things such as
- Acceptance criteria
- Exclusions
- Constraints
- and Assumptions.
> The “scope statement” is created in the process of “Define the scope”
Main Output of every Process group
Planning : Project management plan
Execution : Project deliverables
Monitoring and controlling : **Accepted deliverables* & the work performance reports WPR
Closing : Final products service or result transition & the **final report.*
- Plan procurement management
- Conduct procurement
- Control procurement
- Plan procurement management is done to select WHAT needs to be procured and HOW to conduct the procurement.
- Conduct procurement is done TO select a seller and award a contract.
- Control procurement is when the agreement has already been signed and the contractor is completing the work, and the contractor should be paid according to the terms in the contract.
Project scope statement & exclusions
A project scope statement not only contains the project’s deliverables but also the exclusions, which are features the project will not accomplish.
- The project scope statement
- Work listed in the WBS
- The project charter
- The requirements documentation
- The project scope statement includes a list of all the project deliverables as well as any requirements that should be excluded from the scope.
- Work listed in the work breakdown structure WBS will need to get done on the project.
- The project charter has a high-level list of requirements.
- The requirements documentation lists requirements provided by customers that they would like to be done.
Verified Delivrables and Accepted Delivrables
The process of quality control is when the deliverables are inspected to see if they meet the quality requirements. The output of this process is VERIFIED deliverables.
Control quality is generally done before the process of validate scope, where the deliverables will be inspected by the customers for a formal acceptance.
<aside>
💡 accepted deliverables, is **NOT** output of the control quality process. Verifies Delivrables are
</aside>
How team determines how much stories can get done in an iteration
When determining how much stories can get done in an iteration the team should look at its velocity which is based on how much points they were able to get done in previous iterations.
<aside>
💡 Customer defines **priority**, Team defines **Velocity** and how much work to do
</aside>
Qualitative Vs Quantitative Risk Analysis
Perform qualitative risk analysis is a process used to rank risks according to probability and/or impact.
Perform quantitative analysis is done in order to assign values to the risk.
<aside>
💡 “Rank risks” is not a valid process.
</aside>
While working on the web design project, the change control board approved a change to the layout of the menu. What process should the project manager conduct next to ensure the change is implemented?
A- Update change Log
B- Verify Scope
C- Direct and Manage Project Work
D- Update Project Management Plan
Explanation
> Once a change has been approved, it is then moved to the direct and manage project work process for implementation.
Verify scope is done when ALL the deliverables are completed and require stakeholders’ acceptance.
<aside>
💡 “Update project management plan” and “Update change log” are **not processes**.
</aside>
- sprint review
- sprint planning meeting
- retrospective.
- During a sprint review, the customers review the partially finished product and give the team their feedback.
- A sprint planning meeting is held to determine what requirements will be met in the next sprint.
- A retrospective is conducted to capture the lessons learned from the sprint.
Does the RMP include Positive risks ?
The risk register lists both positive and negative risks, not the risk management plan.
The risk management plan includes the risk breakdown structure RBS that categorizes risks, roles, and responsibilities for the team members and the methodology they would use to perform the risk processes on the project.
Role of the PM to Conflict Resolution
When managing conflicts in a project, the project manager should facilitate a satisfactory resolution for the conflict.
Relation between “Work performance report” and the process of “performing integrated change control”
Work performance report is an input to the process of performing integrated change control, as it will show the overall status of the project.
quick view of data and the project schedule to management personnel.
A milestone chart is a high-level view of major accomplishments on a project. These are best used when presenting a quick view of data and the project schedule to management personnel.
WBS, Network Diagram, Gant chart : Would give you a detailed view of the project schedule and work.
Ho can a customer add a change to an agile project,
When a customer would like to add a change to an agile project, they simply add it to the product backlog. That new feature will then be prioritized based on his value in the product backlog.