There's a 30% chance that it's already raining Flashcards
What is joint probablity
the likelihood of an event occurring, given that another event has already occurred
What is a pull production process
the production schedule is determined by the actual sale of goods
what is a push production process
the demand is forecasted and production is produced to that forecast.
In a cost of quality system, liability costs would be classified where?
in the external failure category
List types of preventive costs to prevent defects before the products are produced?
employee training
preventive maintenance
supplier education expense
What is safety stock?
a buffer for variations in demand and lead-time for the delivery of material. affects the reorder point but does not enter into the quantity to be ordered
What is an internal failure cost?
incurred when a product that does not conform to its design specifications is detected before shipment to customers.
Examples of internal failures
Rework
Spoilage
Scrap
Breakdown maintenance
What are conformance costs?
prevention and appraisal
What are non-conformance costs?
internal and external failure