Q

what is the purpose of the change theme in Prince2

A

to identify, assess and control any potential and approved changes to baselines.

Note: Baseline = reference levels against which an entity is monitored and controlled

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

what is defined as an issue

A

anything that happens during a project which, unless resolved, will result in a change to a baselined product, plan or performance target, including time, cost, scope, quality, risk and benefits

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

describe the 3 types of issues

A
  • A request for change: a proposal to change a baseline
  • An off-specification: something that should be provided but is currently not being provided or is forecast not to be provided
  • A problem or concern: which is any other matter that requires the Project Manager to either resolve or escalate to the Project Board for a decision or action
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

which stage of a project are the controls for addressing change and issues defined and documented in the change control approach

A

during the initiation stage

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

what is documented in the change control approach

A
  • the procedure for change control and issue management
  • specify the roles and responsibilities for change control and issue management
  • Records, timing of activities, assessment scales etc

note: These products are used as part of the change control process: , Change control approach, Configuration item record, Product status account, Daily log, Issue register, Issue reports

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

what is the change authority

A

the responsibility for agreeing to implement a change

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

what is the change budget

A

the method of funding for changes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

can authority be given to Project managers to make decisions about changes?

A

yes - limited authority can be given by the project board to the project manager for day to day changes

Note: the project board normally make decisions about changes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

what is the configuration item

A

records document information about a product such as its status, version and variants of each configuration item and the relationship between them

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

what is a product status account

A

describes the state of all products within a set of limits

for example: a stage, the whole project, a particular product or a set of products

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

what is the purpose of the daily log

A

used to record, amongst other things, problems or concerns that the Project Manager can manage informally

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

what is the purpose of the issue report

A

used when an issue requires formal consideration.

An issue report is created and documented in the issue register

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

what must a Prince2 project have as a minimum in regards to the change control approach

A

must define its change control approach covering:

  • How issues are identified and managed
  • Assessing whether issues have a material impact on the project’s business justification
  • It should also include the roles and responsibilities for change control

two important products are required and these are the issue register and the change control approach