Projects and Principles Flashcards

1
Q

what is the project board responsible for

A

Responsible for overall direction and management of the project. The executive is ultimately accountable for the project

  • it consists of an executive, senior user and senior supplier.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

what is the project manager responsible for

A

runs the project on a day-to-day basis. Responsible for producing the required product to the required standard in quality.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

what are team managers responsible for

A

responsible for delivering the products that the project will create. They can be internal or external to the customers organisation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Name the 4 elements that are integrated together in Prince2 project management

A
  • Principles
  • Themes
  • Processes
  • The project environment

note there are 7 each of the principles, themes and processes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What makes a project a Prince2 project

A

To be considered as a PRINCE2 project the project must be able to demonstrate that it is:

  • Applying all the PRINCE2 principles
  • Meeting the minimum requirements set out in the PRINCE2 themes
  • Using processes that satisfy the purpose and objectives of the PRINCE2 processes
  • Using the recommended techniques suggested by the method or other equivalent techniques
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

what does BAU mean

A

BAU = business as usual. These are the current business operations.

*note: BAU is different from projects because projects:
- introduce change (BAU remains the same)
- they are temporary (BAU is ongoing)
- They are cross functional (BAU tends to use the same skill set)
- Unique (BAU uses the same repetitive operation)
- Carry risk (BAU tries to eliminate risks)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

what is the definition of a project

A

a temporary organization that is created for the purpose of delivering one or more business products according to an agreed business case

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the 6 aspects of performance that need to be managed in a project

A
  • Scope: everything we are going to buy or build, and all the work involved in doing it.
  • Quality: the standards which the delivered scope must meet to be fit for purpose
  • Risk: the things that might not go exactly to plan. Risks that happen can have negative consequences, which we call threats, or positive outcomes which we call opportunities
  • Cost: the project’s budget
  • Time: the duration of the project
  • Benefits: the measurable improvement within BAU because of the project
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Describe the customer / supplier environment

A

This is when you have:
A customer: who will specify the desired results

AND

A supplier: who will provide the resources and skills to deliver that result to the customer

note: customers can also be called: corporate or programme management. They are the organisation that commission the project and provide the project’s mandate. They are responsible for governing the project and realising the project’s benefits. Sometimes it is not just a simple customer/supplier relationship, there may be a hierarchy of multiple suppliers due to several contracts/subcontracts in a project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

what is a project mandate

A

The trigger to start a new project. This can vary from a verbal instruction to a well-defined and justified project definition.
- This happens in the “pre - project” stage.

it is provided by the commissioning organization (corporate, programme
management or the customer)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

what is the definition of a programme

A

a group of related projects which deliver outcomes and benefits related to the organization’s strategy

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the Project initiation documentation (PID)

A

a document which defines the project, in order to form the basis for its management and
an assessment of its overall success. It gives the direction and scope of the project

  • The project board review this to decide on whether to authorise the project
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Explain the Prince2 principle of: continued business justification

A

To start a project, you need a suitable business case (document with the justification for starting the project and any anticipated benefits / risks). If the business case becomes invalid, the project should be stopped.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is a business case

A

A business case documents the justification of undertaking a project based on the estimated costs against the anticipated benefits and risks. It should outline how and when the anticipated benefits can be measured.

note: most benefits of a project are usually seen after a project has finished

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Explain the Prince2 principle of: Learn from experience

A

We should record what went well and what didn’t go well from previous projects to use as lessons. These can be applied to new projects

  • This is everyone in the team’s responsibility
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Explain the Prince2 principle of: Defined roles and responsibilities

A

projects have teams with cross functional skills so everyone must know what is expected of them.

All these groups and individuals involved in a project are known as stakeholders

17
Q

What is the definition of a stakeholder

A

Stakeholders are those who have an interest in the project, are affected by it, or can affect the project.

  • This includes an groups or individuals involved in the carrying out the project (e.g members of the project team)
18
Q

Explain the Prince2 principle of: Manage by stages

A

Projects are broken down into discrete sequential sections known as management stages.

  • team members execute assigned work packages (tasks that will deliver one or more products) throughout the project.
19
Q

Explain the Prince2 principle of: Manage by exception

A

Authority to work within specified limits is delegated through the project team structure. These limits are known as tolerance.

If the project is running in the defined tolerances there is no need for regular update meetings.

20
Q

Explain the Prince2 principle of: Focus on products (also known as outputs or deliverables)

A

Doing this ensures the project only undertakes work that directly contributes to the delivery of a product, helps manage uncontrolled change or “scope creep”.

Focusing on products also reduces risk of user complaints and acceptance disputes by clearly establishing what will be delivered at the start of a project.

21
Q

Explain the Prince2 principle of: Tailor to suit the project

A

It is making sure that the method and it’s use is appropriate for the size of the project and the project controls are appropriate to the project’s complexity, importance, team capability and risk.

The things that can be tailored in a project are: processes, themes, roles, product descriptions and terminology.

22
Q

Which aspects of a project be tailored

A

The things that can be tailored in a project are: processes, themes, roles, product descriptions and terminology.

23
Q

Who is responsible for tailoring a project and how can tailoring decisions be documented

A

It is the Project Manager’s responsibility to identify and document the level of tailoring for the project and make sure this is documented
in the PID (project initiation document)

note: Project assurance and project support can provide ADVICE on tailoring

24
Q

What are the tolerances that can be set for each aspect of performance in a project

A
  • Cost: the allowable range to underspend or overspend compared to the budget
  • Time: The amount of time either side of the target date within which the project
  • Scope: The allowable variation in a projects outputs, for example differentiating between mandatory and desirable output
  • Risk: The limits on the plan’s aggregated risk for example less than 10% of the project budget
  • Benefits: The degree to which it is allowable to under or over deliver the benefits
25
Q

What is a ‘principle” in Prince2

A

a Principle is a core value that must always exist in a PRINCE2 project.

Think of it as a guide for good practice

26
Q

what is the purpose of a checkpoint report

A

to report, at a frequency defined in the work package, the status of the work package

27
Q

what is the purpose of a highlight report

A

to provide the Project
Board (and possibly other stakeholders) with a
summary of the management stage status at intervals defined by them

  • it is used to monitor project progress by the Project Board and also allows the Project Manager to advise the Project Board of any potential problems or areas where the Project Board could help
28
Q

what happens in the final stage of a project

A
  • time to decommission the project (this is part of the process of closing a project)
  • The Project Board needs to be satisfied that the recipients of the project’s products are in a
    position to own and use them on an ongoing basis
  • the project should be assessed for performance against its original plan (PID)