Projects and Principles Flashcards
what is the project board responsible for
Responsible for overall direction and management of the project. The executive is ultimately accountable for the project
- it consists of an executive, senior user and senior supplier.
what is the project manager responsible for
runs the project on a day-to-day basis. Responsible for producing the required product to the required standard in quality.
what are team managers responsible for
responsible for delivering the products that the project will create. They can be internal or external to the customers organisation
Name the 4 elements that are integrated together in Prince2 project management
- Principles
- Themes
- Processes
- The project environment
note there are 7 each of the principles, themes and processes
What makes a project a Prince2 project
To be considered as a PRINCE2 project the project must be able to demonstrate that it is:
- Applying all the PRINCE2 principles
- Meeting the minimum requirements set out in the PRINCE2 themes
- Using processes that satisfy the purpose and objectives of the PRINCE2 processes
- Using the recommended techniques suggested by the method or other equivalent techniques
what does BAU mean
BAU = business as usual. These are the current business operations.
*note: BAU is different from projects because projects:
- introduce change (BAU remains the same)
- they are temporary (BAU is ongoing)
- They are cross functional (BAU tends to use the same skill set)
- Unique (BAU uses the same repetitive operation)
- Carry risk (BAU tries to eliminate risks)
what is the definition of a project
a temporary organization that is created for the purpose of delivering one or more business products according to an agreed business case
What are the 6 aspects of performance that need to be managed in a project
- Scope: everything we are going to buy or build, and all the work involved in doing it.
- Quality: the standards which the delivered scope must meet to be fit for purpose
- Risk: the things that might not go exactly to plan. Risks that happen can have negative consequences, which we call threats, or positive outcomes which we call opportunities
- Cost: the project’s budget
- Time: the duration of the project
- Benefits: the measurable improvement within BAU because of the project
Describe the customer / supplier environment
This is when you have:
A customer: who will specify the desired results
AND
A supplier: who will provide the resources and skills to deliver that result to the customer
note: customers can also be called: corporate or programme management. They are the organisation that commission the project and provide the project’s mandate. They are responsible for governing the project and realising the project’s benefits. Sometimes it is not just a simple customer/supplier relationship, there may be a hierarchy of multiple suppliers due to several contracts/subcontracts in a project
what is a project mandate
The trigger to start a new project. This can vary from a verbal instruction to a well-defined and justified project definition.
- This happens in the “pre - project” stage.
it is provided by the commissioning organization (corporate, programme
management or the customer)
what is the definition of a programme
a group of related projects which deliver outcomes and benefits related to the organization’s strategy
What is the Project initiation documentation (PID)
a document which defines the project, in order to form the basis for its management and
an assessment of its overall success. It gives the direction and scope of the project
- The project board review this to decide on whether to authorise the project
Explain the Prince2 principle of: continued business justification
To start a project, you need a suitable business case (document with the justification for starting the project and any anticipated benefits / risks). If the business case becomes invalid, the project should be stopped.
What is a business case
A business case documents the justification of undertaking a project based on the estimated costs against the anticipated benefits and risks. It should outline how and when the anticipated benefits can be measured.
note: most benefits of a project are usually seen after a project has finished
Explain the Prince2 principle of: Learn from experience
We should record what went well and what didn’t go well from previous projects to use as lessons. These can be applied to new projects
- This is everyone in the team’s responsibility