Summarise project?
- Significance
- Size
- location
- Aim
- Context
Revitalization of 6 alleyway spaces within Belfast City Centre - painting, lighting and artwork.
In response to the need to increase the pedestrian permeability of the city center following a large fire in one of Belfast’s iconic, central buildings in 2018 that caused major issues with pedestrian and vehicular flow
Project value?
£450,000
Programme?
August 2019 to February 2020 (7 months)
Client?
Belfast City Council (local authority)
Site context?
Belfast city centre, connecting high streets
Procurement route?
Design and Build
AECOM appointment?
- RIBA stages 2 – 7
Project management led Integrated Consultant Team – appointed through framework SCAPE?
NEC3 PSC opt A short form (NEC short form is possible when the project budget is under 500k and short term)
Legal review - Approved by AECOM legal team
- Design, Manage Stakeholders, Management of Integrated Supply Team during commissioning and handover, defects management, project completion.
- Design coordinators for sub consultant signage specialist - tandem
- Creating brief for artists
- FEE????
Construction tender method?
Artists - framework?
Quotes?
Contractor appointment?
Tendered as 3 separate works packages low value works packages All just under £30k - 4 quotes required as per councils tender rules for low value works packages (£8-30k) - Lighting - General Painting - General works / repairs
Your Role?
Helping client develop brief Statutory Consultees Works packages - concept, planning, tender H&S / Risk Stakeholder engagement
Designer
Lead Landscape Architect
Initial site visit to determine extent of works required – determining key components requiring repair for high impact improvements.
Consultees Meeting
- NIE & DFI – service and lighting
- BCC and DFI – cleaning, sanitizing
- DFI and BCC – paving, making good surfacing
- Stakeholders/landowner – cleaning and repainting facades
LIGHTING – identified key impact areas
Appointment of initial contractor to undertake feasibility study - then M&E team designed fittings and spec. D&B
GENERAL WORKS - layouts, spec
PAINTING - locations, spec, style, measurements for QS.
ART - coordinating with subconsultant tandem, developing theme, determining locations, determined locations and brief for mural artists
H&S- Designers Risk assessment
STAKEHOLDER ENGAGEMENT
Newsletter for stakeholder engagement, meeting stakeholders - business owners on site.
Planning application, info to tender for each package
I fed into the tender documents with drawings, specifications and scope of works for each contract.
Managing of D&B contractor on site
Relevant Legislation and guidance?
Below threshold public procurement
Code of conduct?
Regard for end user?
Was planning a requirement?
No, plans were prepared but it was confirmed the proposals were permitted development by the case officer.
Specific challanges?
CHALLENGE – loose scope
SOLUTION – site visit with client to draw out what they were envisioning and begin discussion of proposals, presentation of proposals to first entry to client and stakeholders to ensure approval of themes before progressing to other drawings. Regular discussions with client over proposals and costs.
CHALLENGE - budget
SOLUTION – prioritising – maximum effect- entrances to local businesses, lighting
CHALLENGE – stakeholder engagement – multiple stakeholders, city centre scheme, permitted development
Solution – large meeting to get cooperation –
initial meetings and regular updates, leaflets to local businesses, drop ins to local businesses, ensuring happy with artworks and coordinate with their own improvement programmes