SPP ON REGULAR DESIGN SERVICES Flashcards
foreign architects reqs
(1)must secure a temporary/special permit
(2)work permit from dole
(3)must work in collaboration with a local architect who is RLA
are not authorized to provide architectural services for projects located on Philippine soil
business process outsource (bpo) and knowledge process outsourcing (kpo)
bpo and kpo are not allowed in ph unless???
they are prc-registered architectural firms satisfying sec 37 ra no. 9266
architects work starts at
inception of the project when the owner outlines his requirement to architect
scope of services (regular design services)
project definition phase
schematic design phase
design development phase
contract document phase
bidding or negotiation phase
construction phase
phase involves the definition of the requirements of project by owner
project definition phase
architects inform owner of the technical requirements of the project and concomitant professional fees
project definition phase
consults with the owner for a conceptual framework and related requirements of project
project definition phase
gathers relevant information and data leading to the definition of project requirements of project
project definition phase
reviews and refines the owner’s space requirements
project definition phase
prepares an initial statement of probable construction cost
project definition phase
phase consists of preparation of schematic design studies derived from project definition phase, leading to conceptual phase
schematic design phase
evaluates the owner’s program, schedule, budget, project site and proposes methods of project deliveries
schematic design phase
prepares the initial line drawings representing design studies leading to a recommended solution
schematic design phase
submits to owner a statement of probable project construction cost (sppcc)
schematic design phase
documents consisting of plans, elevations, sections and other drawings
design development phase
outline specifications to fix and illustrate the size and character of entire project as to type of materials, etc
design development phase
diagrammatic layout of construction systems
design development phase
updated sppcc for submission to the owner
design development phase
prepares the complete contract documents consisting of detailed designs and construction drawings
contract document phase
technical specifications describing type and quality of materials, finish, manner of construction and general conditions
contract document phase
submits to owner 7 sets of construction drawings and technical specifications for building permits
contract document phase
updates the sppcc based on changes in scope, requirements, or market conditions
contract document phase
assists the owner in filling the required documents to secure approval of government
contract document phase
architect prepares the bid documents for construction, forms for invitation, and instruction to bidders
bidding or negotiation phase
assists the owner from early stage of establishing list of prospective contractors
bidding or negotiation phase
furnishes complete sets of bid documents for purposes of bidding in as many sets as may required
for competitive bids / procurements, the architect
the contract documents
are intellectual property of architects and must be returned
helps in organizing and conducting pre-bid conferences
for competitive bids / procurements, the architect
responds to questions from bidders
for competitive bids / procurements, the architect
assists the owner in obtaining proposals from contractors, amalyzes bid results and prepares abstract of bids
for competitive bids / procurements, the architect
architect perform similar function but negotiates with one contractor only
negotiated contracts
makes decision on all claims of the owner and contractors on all matters relating to execution and progress
construction phase
prepares change orders, gathers and turns over to the owner written guarantees required of contractor and sub-contractor
construction phase
prepares change orders, gathers, turns over to the owner written guarantees required of contractor and sub-contractor
construction phase
makes periodic visits to the project to familiarize himself with general progress and quality of work and to ascertain that proceeding in accordance with contract documents
construction phase
determines amount of owing and due to contractor and issues corresponding certificates of payment for such amounts
construction phase
should more extensive inspection of full-time (8-hr) construction supervision required by client
construction phase
manner of providing services
(1) with a single contract between architect and owner
(2) with separate contracts with architect and engineer, other allied professionals