SPP DOCUMENT 204-A: FULLTIME SUPERVISION SERVICES Flashcards
4 principal members involved in design and building construction
- owner
- architect and his specialist consultants
- contractor
- individuals or group of individuals who assist in supervision
directly and professionally involved responsible and liable for the construction supervision of project.
architect-in-charge
when projects are still manageable in size, architect was then assisted by construction, traditionally called
clerks-of-works
as projects became complex, it becomes necessary for ____ to do full-time inspection at project site.
construction supervision
normally recommended by the architect based on their performace and hired by owner
construction supervision group (csg)
scope of services in fulltime suoervision services
- quality control
- evaluation of construction work
- preparation of daily inspectiin reports
- filling of documents
manner of services in fulltime supervision
- working in dual capacity: architect-of-record and consulting architect or as CSG
- working as consulting architect for fulltime
method of compensation
1.percentage (%) of project construction cost
2.multiple of direct personnel expenses
3. professional fee plus expenses
4. lump sum or fixed fee
5. per diem, honorarium plus reimburse expenses
6. mixed methods of compensation
limitation of authority
- CSG shall not assume the responsibility of the contractor’s project superintendent.
- CSG shall not make decisions on matters that are the sole responsibility of an architect-of-record
legal responsibility
- CSG is:
1.1 responsible to the owner only for administrative matters
1.2 responsible to architect-of-record for technical matters - under article 1723 CSG may appear not to have any legal responsibility since a-o-r and e-o-r are responsible for design while contractor is responsible for construction
2.2 service contract between csg and owner may stipulate certain professional responsibilities - if aor and eor is sued by owner for performance/non that is traceable to csg, aor and eor may file vross claims against csg
qualifications of construction supervision group
- Bachelor of Science in architecture degree
- extensive experience in design and building construction and must be very knowledgeable in building materials and construction detailing
the architect’s fee for fulltime supervision as based on the PPC shall be detailed in the architect’s guidelines
percentage (%) of project construction cost (PCC)
this cost-based method of compensation is applicable only to non-creative work such as accounting, secretarial, research, data gathering, preparation of reports and like.
multiple of direct personnel expenses
this method of compensation is based on technical hours spent and does not account for creative work since the value of creative desihn cant be measured by the length of time the designer has spent on his work
multiple of direct personnel expenses
the multiplier in multiple of direct personnel expenses (spp document 204-a) ranges from?
1.5 to 2.5