Set 9 Flashcards

1
Q
  • LOT 803.09 Monitor Plant Chemistry*
    • *

What are your actions for primary chemistry action level 3?

A

Generate a CR

S/D immediately

Lower temperature to < 250 ˚F as rapidly as possible.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
  • 0PGP03-ZT-0142 STA*
    • *

How long does the STA have to get to the control room once notified?

A

10 mins

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
  • LOT 803.09 Monitor Plant Chemistry*
    • *

What is the objective of secondary chemistry action level 3?

A

To correct a condition that can result in rapid corrosion of a secondary side component during continued operation.

Plant shutdown will minimize impurity ingress and limit exposure of steam generator, turbine, and other secondary materials to corrosive solutions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
  • LOT 803.09 Monitor Plant Chemistry*
    • *

What do the different primary chemistry action levels mean?

A
  • Action Level 1:*
  • *Long term reliability could be affected**
  • Action Level 2:*
  • *Significant damage could be done in a very short time**
  • Action Level 3:*
  • *Inadvisable to keep operating the plant**
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
  • 0PGP03-ZT-0142 STA*
    • *

When can the STA stand watch as the Unit Supervisor, Primary RO, or Secondary RO?

A

US / RO must be available to re-relieve the STA if STA becomes activated

US / RO must be in same unit as STA

US / RO must perform shift turnover on same unit

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
  • LOT 803.08 Respond to Off-Normal Conditions*
    • *

What is STP required to notify the owner QSE’s of?

A

Power reductions > 25 MWe (Non-Peak)

Power reductions > 5 MWe (Peak)

Unit / Plant Shutdowns

Changes in scheduled power generation

Notifications made by EMS website and then followed by a telephone call.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
  • LOT 803.08 Respond to Off-Normal Conditions*
    • *

Can alternate performance be applied to POP04’s and POP05’s?

A

No

Only applies to operating procedures

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q
  • LOT 803.09 Monitor Plant Chemistry*
    • *

What are your actions for primary chemistry action level 1?

A

Generate CR

Bring back in spec within 7 days

If cannot be fixed within 7 days, then more formal corrective actions will be performed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q
  • LOT 803.09 Monitor Plant Chemistry*
    • *

What chemistry transients warrant a Rx trip?

A

CP Fully bypassed
AND
Condensate Pump Discharge cation conductivity verified > 1.0 µS/cm

SG Cation conductivity rising
AND
SG Na, Cl, or SO4 > 1000 ppb

SG Cation conductivity > 15 µS/cm
AND
SG Na rising

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q
  • 0PGP03-ZT-0142 STA*
    • *

When is the STA activated?

A

Emergency Plan Entry

EOPs entered

SM / STA discretion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q
  • LOT 803.09 Monitor Plant Chemistry*
    • *

What actions shall be performed for a secondary chemistry action level 2?

A

Generate CR

Take actions for safe and orderly reduction of power to ≤ 50% and achieve ≤ 50% power within 24 hours of entering Action Level 2.

Have 300 hours until action becomes action level 3

Power reduction may be terminated when no longer in action level 2 but may not raise power until out of action level 1.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q
  • LOT 803.09 Monitor Plant Chemistry*
    • *

What are your actions for primary chemistry action level 2?

A

Generate CR

Fix within 24 hrs

If cannot be fixed within 24 hrs, S/D plant to cold S/D.

If heating up plant and > 250 ˚F and Cl, SO4, Fl > 150 ppb for 24 hrs or O2 > 100 ppb for 24 hrs then lower temperature < 250 ˚F.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q
  • LOT 803.09 Monitor Plant Chemistry*
    • *

What is the objective of secondary chemistry action level 1?

A

Identify and correct the cause of an out-of-normal value without a power reduction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q
  • LOT 803.09 Monitor Plant Chemistry*
    • *

What actions shall be performed for a secondary chemistry action level 1?

A

Generate CR

Return parameter < Action Level 1 Value

Have 21 days until it becomes action Level 2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q
  • LOT 803.09 Monitor Plant Chemistry*
    • *

What is the objective of secondary chemistry action level 2?

A

To minimize corrosion by operating at reduced power while corrective actions are taken.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q
  • LOT 803.09 Monitor Plant Chemistry*
    • *

If a chemistry waiver is desired and the waiver is for a control parameter, whose concurrence must be obtained?

A

Plant Manager

Chemistry Manager is required for all waivers.

17
Q
  • LOT 803.09 Monitor Plant Chemistry*
    • *

What actions shall be performed for a secondary chemistry action level 3?

A

Generate a CR

  • *Take Plant to ≤ 5% power as quickly as safe plant operation permits.**
  • Has to be done regardless of the duration into Action Level 3*
  • Note:*
  • If due to Hydrazine / FW O2 < 2, have 8 hrs to fix and then must go to cold shutdown.*