Sequence of Startup Events Flashcards

1
Q

What is done prior to 180F?

A

Prior to 180F, line up CNM to RPV - One condensate pump and one booster pump.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is done prior to 325F?

A

R\Prior to 325F, verify WCS is lined up to reduce FWS stratification - Required anytime above 325F when below 20% power.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is done at 5psig?

A

-Verify open all MSIVs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is done at 60psig?

A
  • Turbine Shell/Chest Warming

- Place RCIC in standby when isolation signal clears (75PSIA)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is done at 100psig?

A

-RCIC piping fill, downstream of MOV126

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is done at 150psig?

A
  • Perform RCIC Flow testing if Req’d
  • Verify Turbine Bypass Valves are controlling pressure
  • Initiate Condenser Neck Spray
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is done at 250psig?

A

-Prior to LV137 being greater than 40% open and place LV55A/B in service

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is done at 500psig?

A
  • Place SJAEs and OFG in service

- Start First FW Pump

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is done at 766psig?

A

-Verify MSL Low Pressure isolation clears

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is done at 925psig?

A

-APRM Gain Adjustments

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is done at 960psig?

A
  • Raise EHC pressure setpoint to 960psig.

- Open MOV47’s for non operating feed pumps

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is done at 1.5 to 2 Bypasses Open?

A
  • Transfer level control from LV55 to LV10

- Verify Shell/Chest warming complete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is done at 2.5 to 3 Bypasses Open?

A
  • Verify Turbine reset and roll Turbine
  • Synch Generator to Grid
  • Transfer House Loads
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is done at 15-19% power?

A

-Transfer FWLC to Master Manual

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is done at 20-25% power?

A
  • Return WCS to Feedwater

- Prior to 25% power, perform APRM Gain adjustments

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is done at 25% power?

A
  • Place FWLC in 3 element control
  • Verify Thermal Limits within 12 hours of 25%(TS is 23%)
  • Verify Jet Pump operability within 24 hours of 25%
17
Q

What is done at 35% power?

A

-Verify Scram timing is complete prior to 40% power and Upshift RCS Pumps to Fast Speed

18
Q

What is done at 45% power?

A

-Start HDL Pumps on min-flow

19
Q

What is done at 55% power?

A

START standby Condensate AND Condensate Booster pumps

20
Q

What is done between 45-65% power?

A
  • Start a second Feed Pump

- Place 4th point Heater drain pumps in service

21
Q

What should happen automatically at ~65% power?

A

-WHEN Reactor power is approximately 65%,
THEN VERIFY Clean Steam Reboiler Steam Supply auto transfer to Extraction Steam
-WHEN Reactor power is greater than 65%,
THEN VERIFY the following Reheat Steam Load Control Valves are full open(PV28/29s)

22
Q

What should be done prior to reaching 70% power?

A

BEFORE reaching 70% Reactor Thermal Power, VERIFY Offgas System Charcoal Adsorbers are in service PER N2 OP 42.

23
Q

When do we place the Mode Switch to RUN?

A

Placed in run between 5-11% power on the APRMs.

OP-101A E.3.9