2014 NRC RO Exam Flashcards
- A plant startup is in progress. Conditions are as follows:
- The Reactor Mode Switch is in STARTUP.
- The non-coincidence shorting links are installed.
- All IRMs are indicating mid-scale on Range 5.
- All SRMs indicate between 1000 and 5000 cps.
Then, SRM C fails upscale.
Which one of the following describes the resulting status of rod blocks and RPS?
A. A rod OUT block is received, only. No scram occurs.
B. A rod OUT block is received, only. A full scram occurs.
C. A rod IN and OUT block is received. No scram occurs.
D. A rod IN and OUT block is received. A full scram occurs.
Proposed Answer: A
Explanation: With IRMs on less than range 8, the SRM upscale rod out block is enabled. With the non-coincidence shorting links installed, the SRM scram function is bypassed. When SRM C fails upscale, a rod out block is generated. No rod in block is generated and no full scram is generated.
- The plant is at 100% power. Conditions are as follows:
- A tube rupture occurs in the Reactor Water Cleanup (WCS) Non-Regenerative Heat Exchanger.
- The resultant actual and indicated delta flow rate is 130 gpm.
Which one of the following describes the response of CCP surge tank level and the status of the WCS System one minute later?
A. Rises ; Isolated
B. Rises ; Not Isolated
C. Lowers ; Isolated
D. Lowers ; Not Isolated
Proposed Answer: B
Explanation: Water will flow from the WCS system into the CCP system due to the higher pressure in WCS. This will cause CCP surge tank level to rise. Because the delta flow rate is <150.5 gpm, WCS will not isolate on high differential flow.
***Must assume leakage will not cause a high NRHX Outlet Temp isolation at 140F***
- Which one of the following power supply failures would result in loss of power to RPS MG Set 2RPM-MG1B?
A. 2NJS-US1
B. 2NJS-US4
C. 2NJS-US5
D. 2NJS-US6
Proposed Answer: D
Explanation: 2NJS-US6 supplies power to 2NHS-MCC009 which supplies power to the RPS MG Set 2RPM-MG1 B drive motor.
A. Plausible - This is the alternate AC power supply to RPS A scram solenoids.
B. Plausible - This is the alternate AC power supply to RPS B scram solenoids.
C. Plausible- This is the power supply to RPS MG Set 2RPM-MG1A drive motor.
- The plant is at 100% power. Conditions are as follows:
- Division 3 is lined up to Line 5.
- An offsite power surge causes Annunciator 852536, 4KV BUS NNS 017 SPLY ACB 17-2 AUTO TRIP/FTC to alarm.
Which one of the following describes the plant AC bus(es) that immediately de-energize(s)?
A. 2ENS*SWG103 (Div. 2)
B. 2ENS*SWG101 and 2ENS*SWG1 02 (Div. 1 & 3)
C. 2ENS*SWG101 (Div. 1) and 2NNS-SWG014 (Stub Bus)
D. 2ENS*SWG103 (Div. 2) and 2NNS-SWG015 (Stub Bus)
Proposed Answer: A
Explanation: NNS-SWG017 is the normal supply for this bus from offsite power Line 6.
- A loss of offsite power and loss of coolant accident has occurred. Conditions are as follows:
- Drywell pressure is 5 psig and slowly rising.
- All EDGs have started and are powering their respective busses. Then, the following conditions occur:
- A lube oil leak causes 2EGS*EG2 lube oil pressure to lower to 5 psig.
- A governor failure causes 2EGS*EG3 speed to rise at 10 rpm per second.
Which one of the following describes the resulting status of 2ENS*SWG102 and 2ENS*SWG103 ten (10) seconds later?
2ENS*SWG102 ; 2ENS*SWG103
A. Energized ; Energized
B. Energized ; De-energized
C. De-energized ; Energized
D. De-energized ; De-energized
Proposed Answer: B
Explanation: 2EGS*EG2 and 2EGS*EG3 are initially powering 2ENS*SWG102 and 2ENS*SWG103, respectively, due to a loss of offsite power. Additionally, the EDGs are running with a LOCA signal (Drywell pressure > 1.68 psig), therefore numerous trips are bypassed. 2EGS*EG2 lube oil pressure is below the normal trip setpoint of 16 psig, however this trip is bypassed due to the LOCA signal. Therefore, 2EGS*EG2 remains running and powering 2ENS*SWG102. 2EGS*EG3 overspeed trip setpoint is 660 rpm and this trip is NOT bypassed by the LOCA signal. Therefore, 2EGS*EG3 trips after 6 seconds and 2ENS*SWG103 deenergizes.
- The plant is at 100% power. Conditions are as follows:
- Annunciator 603202, APRM TRIP SYSTEM UPSCALE I INOPERABLE, alarms.
- Computer point NMPBC14, APRM CHANNEL 1 INOP, is received.
- Operators bypass APRM 1.
Which one of the following describes the resulting status of Rod Block Monitor (RBM) A? RBM A…
A. is inoperable and enforces a control rod block.
B. automatically transferred to an alternate APRM input.
C. is unaffected because it does NOT receive an input from APRM 1.
D. is bypassed until it is manually transferred to an alternate APRM input.
Proposed Answer: B
Explanation: RBM A normally receives a Simulated Thermal Power input from APRM 1. When APRM 1 is bypassed, RBM A automatically receives an alternate Simulated Thermal Power input from APRM 3.
- The plant is at 100% power. Conditions are as follows:
- A loss of ALL offsite power has just occurred.
- Concurrently, a steam leak in the Drywell has resulted in a Drywell pressure of 2.5 psig and rising rapidly.
- All Emergency Diesel Generators (EDGs) automatically start.
- All EDG output breakers close simultaneously
Which one of the following describes the approximate time for the sequencing of the low pressure ECCS pumps onto the 4.16KV emergency switchgears after the EDG output breakers are closed?
RHR A&B ; CSL & RHR C
A. 1 second ; 6 seconds
B. 1 second ; 10 seconds C.
5 seconds ; 6 seconds D.
5 seconds ; 10 seconds
Proposed Answer: A
Explanation: Due to the presence of combined LOOP and LOCA (Drywell pressure > 1.68 psig) signals, RHS*P1A and RHS*P1B start 1 second after the EDG output breakers are closed. CSL*P1 and RHS*P1C start 5 seconds later (6 seconds from closure of the EDG output breaker).
- A plant startup is being conducted in accordance with N2-0P-101A. Conditions are as follows:
- All SRMs are reading between 5 x 10E4 and 9 x 10E4 cps.
- All IRMs are mid-scale on range 1.
- The operator has selected all the SRMs and the IRMs for withdraw.
Which one of the following will be the first automatic protective action as the detectors are withdrawn?
A. IRM Downscale rod block
B. SRM Downscale rod block
C. IRM Detector NOT Fully Inserted rod block
D. SRM Detector NOT Fully Inserted rod block
Proposed Answer: C
Explanation: When the withdraw function is selected the first action will be the movement of the SRM and IRM detectors from the core. Immediately the IRMs will be detected to be not fully inserted, which will immediately cause a rod block. This rod block is active whenever the mode switch is not in run.
- The plant is at 100% power. Conditions are as follows:
- Annunciator 603306, CRD SCRAM VALVE PILOT AIR HDR PRESS HIGH/LOW, alarms.
- 2IAS-TK3, RB Air Receiver, pressure is 120 psig and stable.
- An Operator reports the Scram Air Header pressure is 63 psig and stable.
- NO control rods are drifting.
Which one of the following statements describes the action that is to be attempted to restore Scram Air Header pressure, per N2-SOP-19, Loss of Instrument Air?
A. Verify lAS Compressors are loaded and bypass lAS Dryers.
B. Swap Scram Air Header Supply Filters and Pressure Control Valves.
C. Bypass Scram Air Header Supply Filters and Pressure Control Valves.
D. Verify lAS Compressors are loaded and isolate Service Air Header.
Proposed Answer: B
Explanation: Per N2-SOP-19, it is required to swap Scram Air Header Supply Filters and Pressure Control Valves.
- The plant is at 100% power. Conditions are as follows:
- Reactor water level is 183” and stable.
- The Feedwater master controller, 2FWS-HIC1600, is in AUTO.
- The individual Feedwater level control valve controllers, 2FWS-HIC1010A and 2FWS-HIC1010B, are in AUTO.
Then, Reactor power is lowered to 90% and plant conditions stabilize.
Which one of the following describes the effect of depressing the Feedwater master controller, 2FWS-HIC1600, MAN pushbutton at this time? Feedwater flow will (1) . Feedwater flow may be adjusted by depressing the (2) OPEN/CLOSE pushbuttons.
A. (1) rapidly rise (2) 2FWS-HIC1600
B. (1) rapidly rise (2) 2FWS-HIC1010A or 2FWS-HIC1010B
C. ( 1) remain near the current value (2) 2FWS-HIC1600
D. ( 1) remain near the current value (2) 2FWS-HIC1010A or 2FWS-HIC1010B
Proposed Answer: c
Explanation: Although Reactor power has been lowered by 10%, 2FWS-HIC1600 manual signal automatically tracks the current Feedwater flow. This feature allows a smooth transfer while placing the controller in MAN without any need for controller nulling. A small mismatch between steam and feed flow at the time of transfer may necessitate manual adjustments. In the given conditions, this would be performed by depressing the OPEN/CLOSE pushbuttons on 2FWS-HIC1600. The OPEN/CLOSE pushbuttons on 2FWS-HIC1010A or 2FWS-HIC1010B will not cause a flow change while those controllers are still in AUTO.
- Which one of the following power supply losses would cause a closure of the Group 8 and 9 INBOARD isolation valves?
A. 2BYS-SWG001A
B. 2BYS-SWG001 B
C. 2BYS*SWG002A
D. 2BYS*SWG002B
Proposed Answer: D
Explanation: Loss of 2BYS*SWG002B causes a portion of the PCIS logic to de-energize. The specific logic causes closure of just the inboard Group 8 and 9 isolation valves.
- The plant is at 100% power. Conditions are as follows:
- The 2VBB-UPS3A and B Manual Transfer Switches are selected to STATIC SWITCH position
- A complete loss of 2NJS-US1 occurs
- 10 seconds after 2NJS-US 1 is lost, a complete loss of 2BYS-SWG001C occurs.
With regards to UPS3A/B, which one of the following describes the effect of these electrical losses?
A. 2VBB-UPS3A loads are de-energized.
B. 2VBB-UPS3B loads are de-energized.
C. 2VBB-UPS3A loads automatically receive power from the maintenance supply via the static switch.
D. 2VBB-UPS3B loads automatically receive power from the maintenance supply via the static switch.
Proposed Answer: c
Explanation: UPS-3A receives normal AC power from 2NJS-US1, backup battery power from 2BYS-SWG001C, and maintenance power from 2NJS-US5. With the Manual Transfer Switches in the STATIC SWITCH position, the UPS’s are able to automatically transfer to the maintenance supply if normal AC and DC inputs are lost. Therefore, when 2NJS-US 1 and 2BYS-SWG001C de-energize, UPS-3A automatically receives power from the maintenance power supply, 2NJS-US5.
- The plant has experienced a failure to scram. Conditions are as follows:
- The DIV I ADS AUTOMATIC INITIATION DISABLE switch has been taken to ON.
- The DIV II ADS AUTOMATIC INITIATION DISABLE switch could not be operated and is stuck in OFF.
Then …
- 2CEC*PNL601 and 603 are terminated and prevented and Reactor water level is lowered to 5 inches.
- Reactor pressure is 920 psig and remains stable on the Turbine Bypass Valves.
Which one of the following describes the plant response two minutes later? Reactor pressure is …
A. stable and still being controlled on the Turbine Bypass Valves.
B. rapidly lowering with only the ‘A’ ADS solenoids energized.
C. rapidly lowering with only the ‘B’ ADS solenoids energized.
D. rapidly lowering with both the ‘A’ and ‘B’ ADS solenoids energized.
Proposed Answer: c
Explanation: With the Division II ADS Automatic Initiation Disable switch in OFF, the Division II ADS system is capable of automatically blowing down the RPV with the Division II ADS Solenoids (B solenoids). Since PNL601 has been terminated and prevented and level is less than Level 1, both RHS A and B are running. With these conditions met, after 105 seconds the Division II ADS system will actuate and rapidly lower Reactor pressure with the B solenoids.
- The plant has experienced a failure to scram. Conditions are as follows:
- Reactor power is 8%
- At time= 0 minutes, Standby Liquid Control (SLC) Pump 1A and 1 B keylock switches are placed in RUN.
- Initial SLC tank level was 1850 gallons.
Which one of the following describes the earliest approximate time range at which enough boron will be injected to the Reactor to ensure that the Reactor will be shutdown under all conditions, in accordance with the EOP Bases and N2-EOP-C5, Failure to Scram?
A. 10 to 15 minutes
B. 20 to 25 minutes
C. 30 to 35 minutes
D. 65 to 75 minutes
Proposed Answer: a
Explanation: With both SLC pumps injecting, the flow rate is approximately 88 gpm. Enough boron will be injected to ensure that the Reactor will be shutdown under all conditions per EOPC5 once SLC tank level lowers to 850 gallons (Cold Shutdown Boron Weight). The time required for this amount of boron injection can be calculated
- The plant is in Mode 3 with RHS B in Shutdown Cooling (SDC). Conditions are as follows:
- A transient occurs.
- Reactor water level drops to a low of 130 inches.
- Reactor pressure rises to a high of 115 psig.
After the transient, conditions are as follows:
- Reactor water level is 150 inches and very slowly rising.
- Reactor pressure is 115 psig and stable.
Which one of the following describes the status of SDC and, if necessary, the action required to mitigate the transient? SDC …
A. remains in service.
B. has isolated, but the isolation may be reset under the current conditions.
C. has isolated. Reactor pressure must be lowered before the isolation can be reset.
D. has isolated. Reactor water level must be raised before the isolation can be reset.
Proposed Answer: D
Explanation: SDC will isolate on a high Reactor pressure of 128 psig (nominal, 148 psig by TS) or a low Reactor water level of 159.3 inches (nominal, 157.8 inches by TS). In the given conditions, SDC isolated due to low Reactor water level, and still has an active isolation signal due to continued low Reactor water level. Therefore, Reactor water level must be raised before resetting the isolation.
- The plant is at 100% power when the CSH water leg pump (WTR LEG PMP 2) trips on motor electric fault.
Which one of the following describes the operational status of CSH and an appropriate mitigating action for the pump trip, in accordance with N2-OP-33, High Pressure Core Spray System? CSH Operational Status ; Mitigating Action
A. Operable ; Line up a Condensate Transfer pump to directly pressurize the CSH piping.
B. Operable ; Verify Condensate Storage Tank 1B level is greater than or equal to 47 feet.
C. Inoperable ; Line up a Condensate Transfer pump to directly pressurize the CSH piping.
D. Inoperable ; Verify Condensate Storage Tank 1B level is greater than or equal to 47 feet.
Proposed Answer: D
Explanation: With the water leg pump 2 out of service, the HPCS system is inoperable. Per N2-0P-33, in order for it to remain available, CST Tank 1 B level must remain above 47 feet.
A. Plausible- Trip of WTR LEG PMP 2 makes HPCS inoperable. Condensate Transfer pumps should not be used to keep HPCS piping pressurized due to potential to over-pressurize the CNS piping upon HPCS initiation.
B. Plausible- Trip of WTR LEG PMP 2 makes HPCS inoperable.
C. Plausible- Condensate Transfer pumps should not be used to keep HPCS piping pressurized due to potential to over-pressurize the CNS piping upon HPCS initiation.
- The plant has experienced a LOCA. Conditions are as follows:
- Drywell pressure is 5 psig and rising.
- Reactor pressure is 600 psig and lowering.
- Annunciator 601416, LPCS SYSTEM MOTOR OVERLOAD, has alarmed.
- Computer points show 2CSL*MOV104, LPCS INJ VALVE, has a motor overload condition.
Which one of the following is correct with regards to the operation of 2CSL*MOV104? As Reactor pressure lowers to the LPCS injection setpoint, 2CSL*MOV104 will …
A. automatically open. The valve is then throttleable from 2CEC*PNL601.
B. automatically open. The valve will NOT be throttleable from 2CEC*PNL601.
C. not automatically open and it can only be manually opened locally at the valve.
D. not automatically open, however it can be manually opened using the control switch on 2CEC*PNL601.
Proposed Answer: A
.Explanation: The motor overload feature for the LPCS injection valve is designed to allow the valve to automatically open if a LOCA signal is present and the DP interlock is met.
18 The plant is at 100% power. Conditions are as follows:
- Annunciator 852108, DIV I EMER BUS BYS 002A 125VDC SYSTEM TROUBLE, is in alarm.
- The next page of the exam gives the indications that are present at the rear of 2CEC*PNL852:
Which one of the following describes these indications?
A. A loss of battery has occurred.
B. Battery Cell Reversal is occurring.
C. A loss of battery charger has occurred.
D. A loss of 2BYS*SWG002A has occurred.
Proposed Answer: c
Explanation: The given indications show that battery charger output is zero amps and the battery is discharging. This indicates that a loss of the battery charger has occurred.
- The plant is at 1 00% power. Conditions are as follows:
• GTS Train B has been manually started and Reactor Building Ventilation has been
secured due to turbulent atmospheric conditions.
• The Shift Manager has directed 2GTS*PV5B, FAN RECIRC VALVE, be placed in
manual control due to inability of PV5B to automatically maintain Reactor Building
differential pressure (RB D/P).
• Indications for RB DIP and 2GTS*PV5B are as follows:
See Picture
Which one of the following describes the status of RB D/P and the action necessary to correct it?
RB D/P should be maintained (1) negative. Adjust the slider on GTS*PDIK5B to further (2) 2GTS*PV5B
A. Less ; Close
B. Less ; Open
C. More ; Close
D. More ; Open
Proposed Answer: c
Explanation: Per N2-0P-61 B, Section H.6.0, with RB D/P less negative than -0.35 in WG action must be taken to make RB D/P more negative. With the PV5B controller in manual, in order to make RB DIP more negative, you must close down on PV5B. In order to close down on PV5B, the slider on the controller must be taken to the left.
A. Plausible - RB D/P is not negative enough.
B. Plausible - RB D/P is not negative enough.
D. Plausible- This would be true if the candidate did not understand how PV5B works. By
shutting PV5B, you make RB D/P more negative, by opening PV5B, you make RB D/P less
negative.
- The plant has experienced a scram. Conditions are as follows:
- Reactor water level is 180 inches and stable with only RCIC injecting.
- Reactor pressure is 800 psig and slowly rising.
- The status of RCIC is shown below:
If Reactor pressure continued to rise, which one of the following describes the response of RCIC pump flow and the control(s) to be used to adjust RCIC pump discharge pressure while in this configuration?
RCIC Pump Flow ; Control(s) to Adjust RCIC Pump Discharge Pressure
A. Lowers ; 2ICS*FC101 thumbwheel
B. Lowers ; 2ICS*FC1 01 OPEN/CLOSE pushbuttons
C. Remains approximately the same ; 2ICS*FC101 thumbwheel
D. Remains approximately the same ; 2ICS*FC101 OPEN/CLOSE pushbuttons
Proposed Answer: B
Explanation: The given indications show the RCIC flow controller, 21CS*FC1 01, in manual control. In manual, RCIC turbine speed will be held constant, whereas in auto, RCIC flow would be held constant. This will cause pump flow to lower as Reactor pressure rises. With the flow controller in manual, the OPEN/CLOSE pushbuttons are used to control system parameters, not
the thumbwheel.
Note: The question avoids overlap with the GFE by testing specific operating characteristics of the RCIC system based on status of the system’s controls. Specifically, operators must have knowledge of how the RCIC Control System responds to plant parameter changes when operating the system in MANUAL (i.e. speed control) vice AUTOMATIC (flow control).
A. Plausible- The thumbwheel will not cause any system parameter changes while in manual, but would be used if in auto.
C. Plausible- If the controller were in auto, flow would be held relatively constant. However in manual, flow will lower as Reactor pressure rises. The thumbwheel will not cause any system parameter changes while in manual, but would be used if in auto.
D. Plausible- If the controller were in auto, flow would be held relatively constant. However in manual, flow will lower as Reactor pressure rises.
- The plant has experienced a LOCA and a complete loss of offsite power. Conditions are as follows:
- The Division 2 EDG failed to automatically start and CANNOT be started.
- Reactor water level is being controlled 160 to 200 inches using LPCS.
- Reactor pressure is 100 psig and slowly lowering.
- Drywell pressure is 1.5 psig and slowly lowering.
- The crew has exited N2-EOP-RPV, RPV Control.
- It is desired to cool down the plant to Cold Shutdown.
Which one of the following identifies the lineup to be used to cool down the plant to Cold Shutdown?
A. Place normal Shutdown Cooling in service using RHR pump A per N2-0P-31, Residual Heat Removal.
B. Place normal Shutdown Cooling in service using RHR pump B per N2-0P-31, Residual Heat Removal.
C. Place alternate Shutdown Cooling (Preferred Lineup) in service using RHR pump A per N2-SOP-31, Loss of Shutdown Cooling.
D. Place alternate Shutdown Cooling (Preferred Lineup) in service using RHR pump B per N2-SOP-31, Loss of Shutdown Cooling.
Proposed Answer: c
Explanation: N2-0P-31 P&L 22 references use of N2-SOP-31, Loss of Shutdown Cooling, if normal Shutdown Cooling cannot be established. N2-SOP-31 directs use of alternate Shutdown Cooling preferred lineup if you are in Mode 3 and attempting to cool down. RHR pump B is unavailable since 2ENS*SWG103 is de-energized. Therefore RHR pump A must be
used for alternate Shutdown Cooling (preferred lineup).
A. Plausible- With a loss of offsite power and Division 2 EDG not available, there is no power to open 2RHS*MOV112, the SOC suction line isolation valve inside Primary Containment.
Additionally, under LOCA conditions, it is not possible to enter Primary Containment to manually open the valve.
B. Plausible -With a loss of offsite power and 2EGS*EG3 not available, there is no power to RHR pump B.
D. Plausible- With a loss of offsite power and 2EGS*EG3 not available, there is no power to RHR pump B.
- The plant has experienced a LOCA. Conditions are as follows:
- Reactor water level is -10 inches and stable.
- RCIC is injecting at 600 gpm.
- No other injection systems are available.
Then …
- Annunciator 601332, RCIC EQUIP ROOM TEMPERATURE HIGH, alarms.
- RCIC equipment room temperature is 1 00°F and slowly rising.
- An Operator reports a steam leak is present in the RCIC equipment room.
Which one of the following describes the required response, in accordance with the Emergency Operating Procedures?
A. Shutdown and isolate RCIC immediately.
B. Defeat the RCIC high area temperature isolation and continue use of RCIC for Reactor injection.
C. Continue use of RCIC for Reactor injection until a high-high room temperature isolation is reached. Then if Reactor water level cannot be maintained above -14 inches, perform Steam Cooling.
D. Continue use of RCIC for Reactor injection until a high-high room temperature isolation is reached. Then if Reactor water level cannot be maintained above -14 inches, perform an RPV Slowdown.
Proposed Answer: b
Explanation: Reactor water level is just above the top of active fuel and stable with RCIC at maximum flow. Additionally, no other injection systems are available to replace RCIC. Therefore RCIC is required by N2-EOP-RPV to maintain adequate core cooling, the main mitigating strategy of the procedure. This is in contrast to the mitigating strategy of N2-EOPSC,
which would lead to eventual isolation of RCIC. The overall EOP strategy places greater importance on adequate core cooling, thus N2-EOP-RPV (and, as a result, ARP 601332) direct defeating the RCIC high area temperature isolation using N2-EOP-6.2 and continuing injection
using RCIC.
A. Plausible -This would be correct if RCIC was not necessary to maintain adequate core cooling. Since RCIC is needed to maintain adequate core cooling, it should be left in service and have the high temperature isolation bypassed.
C. Plausible- The high temperature isolation should be bypassed to allow continued RCIC operation for adequate core cooling.
D. Plausible- The high temperature isolation should be bypassed to allow continued RCIC operation for adequate core cooling. Additionally, with no other injection systems available, if RCIC trips/isolates, Steam Cooling would be performed, not RPV Slowdown.
- The Standby Liquid Control System (SLS) quarterly operability test on SLS pump A is about to be performed.
Which one of the following identifies how the automatic Reactor Water Cleanup System (WCS) isolation is avoided during this test?
A. WCS isolation signal is bypassed when using the SLS pump TEST switch to start the SLS pump.
B. WCS isolation bypass switches are placed in the BYPASS position prior to starting the SLS pump.
C. WCS system is shutdown and containment isolation valves closed prior to starting the SLS pump.
D. WCS containment isolation valve power supply breakers are opened prior to starting the SLS pump.
Proposed Answer: A
Explanation: Use of the TEST Switch for either pump bypasses the interlocks that open the MOV1A/B valves, fire the squibs, and isolate the respective divisional WCS isolation valve. This allows operation of the pump to circulate the contents of the test tank for surveillance testing.
B. Plausible - There are no bypass switches for this situation.
C. Plausible-WCS remains in operation.
D. Plausible- No breakers are opened.
- The plant is at 100% power. Conditions are as follows:
- The Mode Switch is placed in SHUTDOWN.
- A malfunction occurs such that the RPS B Scram Solenoids remain energized.
- All other RPS functions respond as designed.
Which one of the following gives ( 1) the value of Reactor power 20 seconds after the malfunction and (2) the action required?
A. 100% ; Initiate ARI per N2-SOP-101C, Reactor Scram
B. 100% ; Actuate the MANUAL SCRAM PUSHBUTTONS per N2-SOP-101C, Reactor Scram.
C. Downscale (<4%) ; Enter N2-EOP-RPV, RPV Control, and stabilize/control Reactor water level and pressure.
D. Downscale (<4%) ; Enter N2-EOP-RPV, RPV Control. Exit N2-EOPRPV and enter N2-EOP-C5, Failure to Scram
Proposed Answer: c
With a failure of the RPS B Scram Solenoids to de-energize, the Scram Pilot Valves (SOV139’s) could not reposition themselves to vent off their associated HCUs and insert the control rods. However the backup scram valves are still functional and are energize to function valves. Since the backup scram valves would still operate, the scram air header would depressurize which will cause all rods to insert and power to go <4% (downscale). Since all rods would go in, there would be no A TWS and so normal pressure/level control would be used per N2-EOP-RPV.
A. Plausible - This action would be taken if the rods did not insert and the manual scram pushbuttons did not deenergize the RPS solenoids
B. Plausible -Although the operator could operate the manual scram pushbuttons, reactor power would not be 100%, it would be downscale after 20 seconds.
D. Plausible- Even though power would be <4%, if not all rods went in, entry into N2-EOP-C5 would be required.
- A loss of high pressure injection has occurred. Conditions are as follows:
- ADS automatically initiated.
- Reactor pressure is 80 psig and stable.
- Reactor water level is 180 inches and stable.
Which one of the following identifies the status of the Control Room P601 and P628/P631 RED indicating lights for SRV137?
P601 ; P628/P631
A. On ; On
B. On ; Off
C. Off ; On
D. Off ; Off
Proposed Answer: c
Explanation: SRV137 is one of the ADS valves, so it would have opened upon ADS initiation. Therefore, the red solenoid lights on P628/631 will be on. However, Reactor pressure is too low (<400 psig) to cause the red acoustic monitor light on P601 to be on.
A. Plausible- This is the expected condition at higher Reactor pressures (>400 psig).
B. Plausible -This would be correct if the valve opened by relief or safety mode.
D. Plausible- This would be correct for a non-ADS valve that remained closed.
- A plant startup is in progress with power about 15% and the Main Generator about to be synchronized with the grid.
Which one of the following describes (1) the number of Turbine Bypass Valves (TBVs) that should be open prior to synchronization and (2) the method for closing the TBVs after synchronization, in accordance with N2-0P-101A, Plant Startup, and N2-0P-68, Main Generator?
(1) TBVs should be open prior to synchronization. After synchronization, TBVs are closed by pressing the INCREASE pushbutton on the (2)
A. 1 to 1.5 ; Load Selector
B. 1 to 1.5 ; Pressure Setpoint Selector
C. 2.5 to 3 ; Load Selector
D. 2.5 to 3 ; Pressure Setpoint Selector
Proposed Answer: c
Explanation: N2-0P-1 01A directs achieving 2.5 to 3 TBVs open before synchronizing the Main Generator. This is to ensure the Main Generator is able to be quickly loaded to a sufficient level to prevent tripping on reverse power. This concern results from the principles involved in paralleling a finite source, such as the Main Generator, with an infinite source, such as the grid. Once the Main Generator is synchronized, the TBVs are closed using the load selector. The pressure setpoint has previously been raised to 925 psig to support successful Main Generator loading, therefore further operation of the pressure setpoint is not desired. With the Main Generator synchronized to the grid, adjusting load selector affects TCV/TBV positioning. Note: This question matches the KIA because it tests the operational implication of the concept of needing to have adequate capability to assume load on the Main Generator immediately after paralleling with the grid to prevent the Main Generator from tripping on reverse power. This concept is handled in practice by having adequate TBVs open with Reactor pressure high enough.
A. Plausible- N2-0P-101A directs 2.5 to 3 TBVs open.
B. Plausible- N2-0P-1 01A directs 2.5 to 3 TBVs open. Load Selector is used after synchronization to close TBVs. Pressure Setpoint was used earlier in the startup for this purpose.
D. Plausible- Load Selector is used after synchronization to close TBVs. Pressure Setpoint was used earlier in the startup for this purpose.
- The plant is at 100% power. Conditions are as follows:
- 2CCS-TV104, TB CLOSED LOOP COOLING TEMPERATURE CONTROL VALVE, is stuck and cannot move
- Due to changing lake conditions, Service Water supply temperature has lowered 5°F.
Which one of the following describes the response of Main Turbine Lube Oil temperature and the Main Generator leads temperature?
Main Turbine Lube Oil Temperature ; Main Generator Leads Temperature
A. Remains approximately the same ; Remains approximately the same
B. Remains approximately the same ; Lowers
C. Lowers ; Remains approximately the same
D. Lowers ; Lowers
Proposed Answer: B
Explanation: Service Water supplies the cooling water to the TBCLC heat exchangers and TBCLC supplies the cooling water to the Main Turbine Lube Oil and Main Generator Leads coolers. With Service Water temperature lowering and 2CCS-TV104 remaining in the initial position, TBCLC supply temperature will lower. The Main Turbine Lube Oil coolers have a dedicated temperature control valve that will adjust to maintain Lube Oil temperature approximately constant. The Main Generator Leads coolers do NOT have a dedicated temperature control valve, therefore Leads temperature will lower along with the TBCLC supply temperature.
A. Plausible - The Main Generator Leads coolers clo NOT have a dedicated temperature control valve, therefore Leads temperature will lower along with the TBCLC supply temperature.
C. Plausible -The Main Turbine Lube Oil coolers have a dedicated temperature control valve that will adjust to maintain Lube Oil temperature approximately constant. The Main Generator Leads coolers do NOT have a dedicated temperature control valve, therefore Leads temperature will lower along with the TBCLC supply temperature.
D. Plausible- The Main Turbine Lube Oil coolers have a dedicated temperature control valve that will adjust to maintain Lube Oil temperature approximately constant.
- The plant is at 100% power when 2NNS-SWG012 de-energizes.
Which one of the following describes the impact on the Fire Protection system?
A. The Electric Fire pump motor loses power.
B. The Diesel Fire pump starting circuit loses power.
C. Both Pressure Maintenance pumps lose power. The Electric Fire pump auto-starts.
D. One Pressure Maintenance pump loses power, but the other maintains system pressure.
Proposed Answer: A
Explanation: 2NNS-SWG012 is the power supply to the Electric Fire pump motor.
B. Plausible- The Diesel Fire pump start circuit is not powered from 2NNS-SWG012, it is powered from 2SCA-PNL 102 which is powered from US 1.
C. Plausible- The Pressure Maintenance pumps are powered from 2NHS-MCC015, which does not receive power from 2NNS-SWG012.
D. Plausible- The Pressure Maintenance pumps are both powered from 2NHS-MCC015, which does not receive power from 2NNS-SWG012.
- The plant is at 80% power. Conditions are as follows:
• A malfunction occurs in the M/A station for Recirculation Flow Control Valve 2RCS*HYV17A.
• The failure exactly mimics the slider being in the slow detent position in the direction indicated by the arrow below.
• The malfunction occurs for approximately 15 seconds and then clears.
Which one of the following describes how the EHC system controls Reactor pressure in response to this malfunction?
EHC …
A. adjusts Turbine Control Valves and stabilizes Reactor pressure at the initial value.
B. adjusts Turbine Control Valves and stabilizes Reactor pressure slightly higher than the initial value.
C. adjusts Turbine Control Valves and stabilizes Reactor pressure slightly lower than the initial value.
D. controls Reactor pressure at the initial value with no significant Turbine Control Valve adjustment because 2RCS*HYV17A locks up.
Proposed Answer: c
Explanation: This failure gives a close signal to 2RCS*HYV17A. Since the failure is the same as the M/A station being in the slow detent position, none of the FCV lockup signals will cause a lockup. The loop flow controller will throttle the FCV further closed. This will lower Recirculation flow and Reactor power. Reactor pressure will begin to lower and EHC will throttle Turbine Control Valves further closed to prevent a major drop in Reactor pressure. However, the EHC system controls Reactor pressure proportionally to Turbine steam flow. As Turbine steam flow lowers, Reactor pressure will be controlled at a lower value.
A. Plausible- The EHC setpoint will remain constant, however the control characteristics of the system are such that at lower steam flow, Reactor pressure will be controlled at a lower value.
B. Plausible- The given failure shows the loop flow controller with a close signal, not an open signal. Reactor pressure would rise if the FCV moved in the open direction.
D. Plausible- The FCV does have numerous lockup signals, however none that would prevent valve motion in this circumstance.
- The plant is at 100% power. Conditions are as follows:
- Annunciator 602319, RWCU FILTER DEMIN INLET TEMP HI-HI, alarms.
- The running Reactor Water Cleanup pump trips.
- 2WCS*MOV112, CLEANUP SUCT OUTBOARD ISOL VLV, closes.
- 2WCS*MOV200, CLEANUP RETURN ISOL VLV THROTTLE, remains open.
Which one of the following describes this RWCU response?
High non-regenerative heat exchanger outlet temperature ….
A. directly caused the pump to trip, which caused MOV112 to close.
B. directly caused MOV112 to shut and MOV200 should have closed.
C. directly caused MOV112 to shut and the system responded properly.
D. should not have caused MOV112 to shut and the system responded improperly.
Proposed Answer: c
Explanation: Annunciator 602319 corresponds to a RWCU filter demin inlet temperature of 140°F. This causes closure of MOV112 to protect the resin. The closure of MOV112 trips the
running WCS pump.