Schedule Mgmt Flashcards
Schedule mgmt
Concerned with how work will be done (activities)
Schedule management processes
Initiating - none
Planning - plan schedule mgmt, define actinides, sequence activities
Executing - none
Monitoring and controlling - control schedule
Closing - none
Plan schedule mgmt output
Schedule mgmt plan
Define activities output
Activity list, activity attributes
Sequence activities output
Project schedule network diagrams
Estimate activity durations output
Activity duration estimates
Develop schedule output
Project schedule, schedule baseline
Control schedule output
Work performance info, change requests, schedule forecasts
Schedule mgmt plan
Part of the project plan, defines how the schedule will be defined, measured, how and how often the team will track progress, what will happen if project veers and how progress will be reported
Define activities
Baseline is more granular, decomposed into individual schedule activities
Define activities tools
Expert judgement
Decomposition
Rolling wave planning
Rolling wave planning
Progressive elaboration that models project planning
Decompose those that are coming up rather than those in the future
Activity list
All of the schedule activities that need to be performed in order to complete the project
Each activity should map to only one work package
Work package is delivery focused, activity is actual work focused
Activity attributes
Additional info about activities
Sequence activities
Taking activity list and arranging in order they must be performed
Network logic diagram
Each activity is drawn and placed in the order it must be performed and the amount of time required is represented by a number
Preferred method for activities
Sequence activities tools
Precedence diagramming method
Dependency determination and integration
Leads and lags
Precedence diagramming method (PDM)
Graphical representation to schedule activities in order they must be completed
Mandatory dependency
Required, cannot be broken
Discretionary dependency
Soft/preferred, based on historical info and expert judgement
External dependency
Must be considered although outside control and scope
Internal dependency
Team can control
Project schedule network diagram
Graphical way of depicting schedule activities, dependencies and sequence
Estimate activity duration
Duration depends on who, when, how many people and how long it will take
Estimate activity tools
Analogous estimating
Parametric estimating
Three point estimating
Bottom up estimating