Schedule Management Flashcards
What does the BACKWARD PASS identify?
Late Figures
What is Free Float?
Amount of delay an activity can have w/o delaying the START DATE of its SUCCESOR
Describe Path Divergence
Activity has TWO OR MORE SUCCESORS
Float Formula
LS - ES
or
LF - EF
When would you use a Milestone Chart?
Reporting to Senior Management
What does FORWARD PASS identify?
Early Figures
Describe Path Convergence
Activity has TWO OR MORE direct PRECEDING activities
In Backwards Pass, how do you identify the Late Finish if the activity has a Path Divergence?
Use the earliest Late Start of the proceeding activities
Define Project Calendar
Identifies WORKING DAYS and SHIFTS available
Which activity would you try to shorten if you need to shorten project duration?
One that is…
- one CPM
- longest duration
- earliest (if multiple long durations)
What is Project Float?
AKA = Positive Total Float
Amount of delay an activity can have w/o delaying the externally imposed project completion date required by customer, management, or baseline
Free Float Forumula
ES - EF - 1