Schedule Management Flashcards

1
Q

What does the BACKWARD PASS identify?

A

Late Figures

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is Free Float?

A

Amount of delay an activity can have w/o delaying the START DATE of its SUCCESOR

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Describe Path Divergence

A

Activity has TWO OR MORE SUCCESORS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Float Formula

A

LS - ES

or

LF - EF

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

When would you use a Milestone Chart?

A

Reporting to Senior Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What does FORWARD PASS identify?

A

Early Figures

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Describe Path Convergence

A

Activity has TWO OR MORE direct PRECEDING activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

In Backwards Pass, how do you identify the Late Finish if the activity has a Path Divergence?

A

Use the earliest Late Start of the proceeding activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Define Project Calendar

A

Identifies WORKING DAYS and SHIFTS available

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Which activity would you try to shorten if you need to shorten project duration?

A

One that is…

  • one CPM
  • longest duration
  • earliest (if multiple long durations)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is Project Float?

A

AKA = Positive Total Float

Amount of delay an activity can have w/o delaying the externally imposed project completion date required by customer, management, or baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Free Float Forumula

A

ES - EF - 1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly