Outputs Flashcards

1
Q

Develop Project Charter

Outputs

A
  • Project Chart

- Assumption Log

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Identify Stakeholders

Outputs

A
  • Stakeholder Register
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Develop Project Management Plan

Outputs

A
  • Project Management Plan
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Plan Scope Management

Outputs

A
  • Scope Management Plan

- Requirements Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Collect Requirements

Outputs

A
  • Requirements Documentation

- Requirements Traceability Matrix

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Define Scope

(Outputs)

A
  • Scope Statement
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Create WBS

Outputs

A
  • Scope Baseline
    1. Scope Statement
    2. WBS
    3. WBS Dictionary
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Plan Schedule Management

Outputs

A
  • Schedule Management Plan
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Define Activities

(Outputs)

A
  • Activity List
  • Activity Attributes
  • Milestone List
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Sequence Activities

Outputs

A
  • Schedule Network Diagram
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Estimate Activity Duration

Outputs

A
  • Duration Estimates

- Basis of Estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Develop Schedule

Outputs

A
  • Schedule Baseline
  • Project Schedule
  • Project Calendars
  • Schedule Data
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Plan Cost Management

Outputs

A
  • Cost Management Plan
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Estimate Costs

Outputs

A
  • Cost Estimates

- Basis of Estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Determine Budget

Outputs

A
  • Cost Baseline

- Project Funding Requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Plan Quality Management

Outputs

A
  • Quality Management Plan

- Quality Metrics

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Plan Resource Management

Outputs

A
  • Resource Management Plan

- Team Charter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Estimate Activity Resources

Outputs

A
  • Resource Requirements
  • Basis of Estimates
  • Resource Breakdown Structure
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Plan Communications Management

Outputs

A
  • Communications Management Plan
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Plan Risk Management

Outputs

A
  • Risk Management Plan
21
Q

Identify Risks

Outputs

A
  • Risk Register

- Risk Report

22
Q

Perform Qualitative Risk Analysis

Outputs

A
  • Project Document Updates
    1. Risk Register
    2. Risk Report
23
Q

Perform Quantitative Risk Analysis

Outputs

A
  • Project Document Updates

1. Risk Report

24
Q

Plan Risk Responses

Outputs

A
  • Project Document Updates
    1. Risk Register
    2. Risk Report
25
Q

Plan Procurement Management

Outputs

A
  • Procurement Management Plan
  • Procurement Strategy
  • Procurement Statement of Work
  • Bid Documents
  • Make-or-Buy Analysis
  • Source Selection Criteria
  • Independent Cost Estimates
26
Q

Plan Stakeholder Engagement

Outputs

A
  • Stakeholder Engagement Plan
27
Q

Direct and Manage Project Work

Outputs

A
  • Deliverables
  • Work Performance Data
  • Issue Log
28
Q

Manage Project Knowledge

Outputs

A
  • Lessons Learned Register
29
Q

Manage Quality

Outputs

A
  • Quality Reports

- Test and Evaluation Documents

30
Q

Acquire Resources

Outputs

A
  • Physical Resource Requirements
  • Project Team Assignments
  • Resource Calendars
31
Q

Develop Team

Outputs

A
  • Team Performance Assessments
32
Q

Manage Team

Outputs

A
  • Project Document Updates

1. Project Team Assignments

33
Q

Manage Communications

Outputs

A
  • Project Communications
34
Q

Implement Risk Responses

Outputs

A
  • Project Document Updates
    1. Risk Register
    2. Risk Reports
35
Q

Conduct Procurements

Outputs

A
  • Selected Sellers

- Agreements

36
Q

Manage Stakeholder Engagement

Outputs

A
  • Project Document Updates

1. Stakeholder Register

37
Q

Monitor and Control Project Work

Outputs

A
  • Work Performance Reports
38
Q

Perform Integrated Change Control

Outputs

A
  • Approved Change Requests
  • Project Documents Update
    1. Change Log
39
Q

Validate Scope

Outputs

A
  • Accepted Deliverables

- Work Performance Information

40
Q

Control Scope

Outputs

A
  • Work Performance Information
41
Q

Control Schedule

Outputs

A
  • Work Performance Information

- Schedule Forecats

42
Q

Control Costs

Outputs

A
  • Work Performance Information

- Cost Forecasts

43
Q

Control Quality

Outputs

A
  • Quality Control Measurements
  • Verified Deliverables
  • Work Performance Information
44
Q

Control Resources

Outputs

A
  • Work Performance Information
  • Project Document Updates
    1. Physical Resource Assignments
    2. Resource Breakdown Structure
45
Q

Monitor Communications

Outputs

A
  • Work Performance Information
  • Project Document Updates
    1. Project Communications
46
Q

Monitor Risks

Outputs

A
  • Work Performance Information
  • Project Document Updates
    1. Risk Register
    2. Risk Report
47
Q

Control Procurements

Outputs

A
  • Close Procurements
  • Work Performance Information
  • Procurement Documentation Updates
48
Q

Monitor Stakeholder Engagement

Outputs

A
  • Work Performance Information
  • Project Document Updates
    1. Stakeholder Register
49
Q

Close Project or Phase

Outputs

A
  • Final Report
  • Final product, service, or result transition
  • Project Document Updates
    1. Lessons Learned Register
  • OPA
    1. Lessons Learned Repository