Formulas Flashcards
1
Q
Number of Communication Channels
A
n(n-1) / 2
2
Q
BAC
A
Total Budget
3
Q
Planned Value (PV)
A
Planned % Complete x BAC
4
Q
Earned Value (EV)
A
Actual % Complete x BAC
5
Q
Actual Cost (AC)
A
Sum of Actual Costs
6
Q
Cost Variance (CV)
A
EV - AC
7
Q
Schedule Variance (SV)
A
EV - PV
8
Q
Schedule Performance Index (SPI)
A
EV / PV
9
Q
Cost Performance Index (CPI)
A
EV / AC
10
Q
Estimate At Completion (EAC)
A
BAC / CPI
11
Q
Estimate To Completion (ETC)
A
EAC - AC
12
Q
Variance At Completion (VAC)
A
BAC - EAC
13
Q
To-Complete Performance Index (TCPI)
A
(BAC-EV) / Remaining Funds
14
Q
Point of Total Assumption (PTA)
A
((Ceiling Price - Target Price) / Buyer’s Share) + Target Cost