Schedule Flashcards

1
Q

Schedule Network Diagram vs Critical Path Methd vs Critical Path?

A
  • SND: Master schedule depiction of relationships btw activities
  • CPM: Sched analysis method calculate shortest path for project, float for each activity, and possible start and finish dates for each activity.
    • Used on SND path w/ 0 float is CP
  • CP: : Path along activities which any delays would cause project to be delayed. Longest duration path through SND, chain of paths w/ least amount of float.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Study Further

Need to know scheduling sequence for Define actv, seq actv, estimate actv durations, dev sched and Resource Mgmt: Plan resc mgmt. and estimate actv dur

A
  1. Plan Project Schedule Process: Process to develop and control project Schedule
  2. Define Activities: Decompose Work packages to make activity list
  3. Sequence Activities: See what are predecessor/successor orders and creating a schedule network diagram.
    * 4 types of relationsips: FS, SS, SF, FF
    * 4 types of Dependencies: Mand, discrectionary, internal, external
    * Leads and lags
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Types of activity dependencys?

A

Mandatory, discretionary, internal, external

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is Lead time and Lag time?

A

Used in Precedence relationships btw activities.

Lead: Start an activity PRIOR to the preceding activity; getting a head start on the activity. Pull activity forward to now.
* Pulling a succor activity forward to present prior to a preceding activity to get head start on it.
* Ex FS relationships btw 2 actv, w/ 2 day LEAD= –2(negative number pulling activity forward to present.
* FS: Act A -> FS-2D -> Act E

Lag: Delay the start of the preceding activity.
* FS relationships btw 2 actv, w/ 3 day LAG= +2(Positive) pushing activity further back
* FS: Act A -> FS +3D -> Act E

** Preceding Activity def: is a task that must be completed before another task can begin. Predecessor.
A(Predecessor)>B(Successor)
* Succeding activity: task that begins after another task has finished.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

3 point estimate formulas?

A

Triangular Est: O + ML + P/ 3
Pert(beta Distr): O + 4ML + P / 6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Types of float:
1. Free Float
2. Total Float:
3. Project Float:

https://projectmanagementacademy.net/resources/blog/free-float-vs-total-float/

A
  • Free float= activity float, amount of time activity can be delayed w/out delaying the earliest following activity.
  • Formula: ES(
  • Total Float: Amount activity can be delayed w/out delaying project completion date
    • Formula: LF-EF or LS - ES
  • Project float: Amount of time project can be delayed without impacting an imposed deadline or comitment by the PM
    • Imposed deadline - planned finish date.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Mapping Precedence relationships
FS
SF
FF
SS

A

Tip: reading and applying relationships on predence relationship A>B
*Relationship[a,b], b is 2nd activity sucessor, a is predecessor activity.
* Reading Relationship exs: [a=act1 pred, b=act2 succ]
* FS=[a,b], b has to start before a can finish
* SF=[a,b], b has to finish before a can start
* SS=[a,b], b has to start before a can start
* FF=[a,b], b has to finish before a can finish
* Drawing arrow relationship: Each activity box sides represent Start(left side box), Finish(right side of box)
*

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Schedule Estimating
Give example of Accuracy and Precision for estimating days

A

Precisions: How precise the timeframe is:
* Less Precise: Years, months
* More Precise: hours, minutes, seconds

Accuracy: Range of estimation 53 days to 75 days.
* Think Rough order mag(-25 to 75% accuracy low accuracy
* Defnitieve est: -5 to +10% higher accuracy.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Which is the CP of all the paths?
ABCF= 34wks
ADEF= 40wks
ABEF=38wks

A

ADEF= 40wks
CP is the path with longest duration. Also means this is the shortest amount of time we can complete the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Network Diagram steps

A

Forward Pass:
Act 1: ES= Start at 0
* Rule start at zero then add duration. sucessor activity keep number don’t add 1+XX.
EF= ES + Dur
Act 2 ES= Act 1(LS)
* Rule: for activities with 2 predecessors pick biggest. Forward = bigger
* Fill all forward top passes.
Critical Path
* Last Activity LS = Paths total dur
* Last Act LF = LS
* Last Act Float = 0 = LS- LF

Backward Pass
* LS = Dur - LF; Work bottoms all way back
* Rule: If two activities Successors to activity pick smalled for bottom backawrd pass

Float = LS-ES or LF-EF

How well did you know this?
1
Not at all
2
3
4
5
Perfectly