Performance + EVM Flashcards
1
Q
TCPI: To Complete Performance Index
A
The efficiency that must be maintained in order to complete the project as planned
TCPI= (BAC - EV)/(BAC - AC)
* TCPI>0 Harder to complete as planned need to improve efficiency
* Could be over budget or behind schedule at current performance
* TCPI<0 Easier to complete as planned
2
Q
VAC: Variance At COmpletion
A
- VAC = BAC - EAC
- VAC>0 ; Under budget
- VAC<0 Over budget
- VAC= On budget
3
Q
ETC: Estimate To COmplete
A
Expected cost to complete all remaining work from curent point in time
* Remaining cost of project
* ETC = EAC-AC
* Current performance(EAC) - of actual costs so far
4
Q
Performance Index cost sched
CPI
SPI
A
CPI: EV/AC
SPI: EV/PV
5
Q
Variance Sched and Cost
A
CV = EV - AC
SV = EV - PV