Performance + EVM Flashcards

1
Q

TCPI: To Complete Performance Index

A

The efficiency that must be maintained in order to complete the project as planned
TCPI= (BAC - EV)/(BAC - AC)
* TCPI>0 Harder to complete as planned need to improve efficiency
* Could be over budget or behind schedule at current performance
* TCPI<0 Easier to complete as planned

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

VAC: Variance At COmpletion

A
  • VAC = BAC - EAC
  • VAC>0 ; Under budget
  • VAC<0 Over budget
  • VAC= On budget
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

ETC: Estimate To COmplete

A

Expected cost to complete all remaining work from curent point in time
* Remaining cost of project
* ETC = EAC-AC
* Current performance(EAC) - of actual costs so far

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Performance Index cost sched
CPI
SPI

A

CPI: EV/AC
SPI: EV/PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Variance Sched and Cost

A

CV = EV - AC

SV = EV - PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly