Quiz 2 Planning Performance Domain Flashcards

1
Q

A quantitative assessment of the likely amount or outcome of a variable, such as project costs, resources, effort, or durations.

A

Estimate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Within the quality management system, accuracy is an assessment of correctness. (Refers to CORRECTNESS)

A

Accuracy

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Within the quality management system, precision is an assessment of exactness. (Refers to EXACTNESS)

A

Precision

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

A method used to shorten the schedule duration for the least incremental cost by adding resources.

A

Crashing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

A schedule compression method in which activities or phases are normally done in sequence are performed in parallel for at least a portion of their duration.

A

Fast Tracking

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

The approved estimate for the project or any work breakdown structure (WBS) component or any schedule activity.

A

Budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

3 Development Approach Examples

A

1) Specific Planning Phase
2) High-Level Planning with Prototyping
3) Adaptive Iterative Approach

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

4 Aspects Impacted by Project Phase

A

1) Range
2) Accuracy
3) Precision
4) Confidence

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

5 Steps in Predictive Schedule Planning

A

1) Decompose
2) Sequence
3) Estimate
4) Allocate
5) Adjust

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

4 Types of Dependencies

A

1) Mandatory
2) Discretionary
3) External
4) Internal

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

6 Questions for Communication Planning

A

1) Who needs information
2) What information does each stakeholder need
3) Why should information be shared with stakeholders
4) What is the best way to provide information
5) When and how often is information needed
6) Who has the information needed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Linkage between 3 key elements

A

1) Planning
2) Delivering
3) Measuring work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

3 Broad Types of Metrics

A

1) Product
2) Schedule Performance
3) Budget Performance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Addresses activities and functions associated with the initial, ongoing, and evolving organization and coordination necessary for delivering project deliverables and outcomes.

A

Planning Performance Domain

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

3 Things the Triple Bottom Line Considers

A

1) Financial
2) Social
3) Environmental

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

The features and functions that characterize a product, service, or result. It defines what the final product will include.

A

Product Scope

17
Q

The work required to deliver the product, service, or result with the specified features and functions. It focuses on the effort needed to complete the project.

A

Project Scope

18
Q

3 Factors Associated with Computer Simulation Probabilistic Estimates

A

1) Point Estimate with a Range
2) Statement of Confidence
3) Probability Distribution