Quantification & Costing Flashcards
What is a schedule of rates?
A list of agreed costs at which the contractor will do the works. Usually best for simpler, repeat works
- Lists staff, types of labour and plant hire rates which a contractor lists an hourly rate.
What is a provisional sum?
allowance for works where the cost cannot be defined.
What is the difference between defined and undefined provisional sums?
A defined prov sum allowance for works where the cost cannot be accurately measured.
Where there is insufficient information the works are classed under an undefined provisional sum entitling the contractor to costs for prelims and an extension to the programme.
What is a prime cost?
Allowance for the supply of work or materials, without percentages on top (no prelims ertc)
Prime cost sums are the financial adjustments of work whose extent is known but whose specification is yet to be determined.
What are provisional quantities?
These are provisional quantities of work whose specification in known, but the exact amount is yet to be determined.
How would you cost a project?
Benchmarking using BCIS, previous projects or using pricing books such as Spon’s
What does NRM stand for?
New Rules of Measurement – you should complete a cost plan and measure using this book.
What are the three NRM books for?
1 – Order of cost estimating and cost planning for capital building works
2 – NRM 2: Detailed measurement for building works(BoQ)
3 – NRM 3: Order of cost estimating and cost planning for building maintenance works
When were the NRMs published?
1st May 2009
Why were the NRMs introduced?
The previous SMM7 was purely designed for the production of BOQ for tender purposes.
This resulted in a lack of guidance and uniformity around preparing cost estimates and cost plans when using SMM7.
NRM was introduced to provide a common and consistent basis for the production of order of cost estimates and cost plans and to give employers more confidence around the inclusions.
Why should you use the NRMs?
The NRM provides a common and consistent basis for the production of order of cost estimates and cost plans.
Added confidence to Employers
NRM is best practice
However – QSs are not required to follow the NRM if they judge it as unsuitable for their specific project but they must have a good reason as to why this approach has been taken.
What is NRM 1?
NRM 1: Order of cost estimating and cost planning for capital building works
This provides a structured basis for measuring building works and for the production of Cost Estimates and Cost Plans. Includes guidance on how to describe and quantify not only measured works but also wider costs such as preliminaries, overheads and profit, risk allowances and inflation.
Also provides guidance on the preparation of benchmark analysis
What is NRM 2?
NRM 2: Detailed measurement for building works
Replaced SMM7 in 2013. Used when obtaining tender prices (BoQ and Schedule of rates).
* Example: screed is first level and if it’s under 600mm wide it is measured as m and if it is over 600mm wide it is measured as m2.
What is NRM 3?
NRM 3: Order of cost estimating and cost planning for building maintenance works
Used for:
o Asset-specific cost plans during pre-construction phase.
o Procurement and cost control of maintenance work
What is meant by the abbreviations GEA
Gross External Area (GEA) The area of the building measured externally at each floor area.
What is meant by the abbreviations GIA
Gross Internal Area (GIA) Area of the building measured to the internal face of the perimeter wall at each floor level. Excludes external open sided balconies, fire escapes, canopies, external walls and fuel stores.