Contract Administration Flashcards

1
Q

What is nomination?

A

Under certain circumstances, the client may wish to select (nominate) a subcontractor themselves, rather than allowing the contractor to select them. This is referred to as a nominated subcontractor.

  • Selection of a particular subcontractor to carry out works, manufacture or supply of materials.
  • This provides the architect and client with greater control of material choice and therby quality.
  • It is often used where there are long lead-in times with the employer placing orders prior to the Main Contract aware which reduces potential delays on site.
  • The Main Contractor is relieved of liability of design and compliance with the performance spec in addition to subcontractor delays in respect of the works that have been nominated.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Do nominated subcontractors get paid separately?

A

Nominated Contractors are normally paid via the Main Contract with sums identified separately.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Can the contractor object to a nominated subcontractor?

A

Any objections must be made during the tender period.

There are specific exclusions and grounds for an objection for example if they have found out the subcontractor is having financial difficulties and may be going insolvent.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

If there are problems with the design, after Novation or the architect, who would be responsible?

A
  • At the point of novation, the client would agree the level of design was satisfactory and would be signed off by all parties.
  • The contractor would then become responsible for the Architect and his design should any problems arise during constriction.
  • Disputes may arise where it becomes unclear when problems have arisen, either prior to the transfer of services or afterwards.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the difference between Novation and Assignment?

A
  • Novation is a mechanism whereby one party can transfer all its obligations under a contract and all benefits arising from that contract to a third party.
  • Assignments is where contractual benefits are assigned however contractual burdens cannot be transferred under assignment.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is a set-off?

A

Set off are any monies owed to the employer by the contractor which are deducted against any payments due to the contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Describe differences between Statutory Provisions and Contract provisions?

A
  • Statutory provisions are set out by law & must be compiled with.
  • Contract provisions relate to the contract in question and therefore only apply to a specific project.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are domestic subcontractors?

A
  • This is a standard appointment of a Subcontractor by the Main Contractor
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are named subcontractors?

A
  • Clients provide the Main Contractor with a choice of names Sub Contractors for a portion of the works.
  • Once appointed they become a domestic subcontractor in terms of the conditions of contract.
  • Additional names may be added if approved by all parties.
  • This allows the client a level of control over the quality of the works packages and in some cases cost.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

If an instruction was issued during the contract which involved the fabrication of a substantial amount of materials off site would you pay for them as off site materials within the valuation?

A

There is no obligation on the client to pay for materials off site if this is identified in the contract.

Under NEC the title for plant and material which are outside the Working Areas can pass to the client if the Supervisor has marked them as for the contract. This can then allow the material to be identified for payment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

How would you deal with the urgent verbal instructions?

A

I would communicate the instruction using the language of the contract of writing using a communication system if specified in the scope. This will be either issuing the instruction or notifying of rejecting the instruction using the reasons set out on the contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Could an email constitute a contract document?

A

Yes providing there is offer, acceptance, intention to create legal relations and the responding email does not vary the conditions, a contract will be created.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is your opinion of oral contracts?

A

Whilst they are legally blinding the difficult lies in proving the specific terms and conditions.

Under the Construction Act: The act now applies to construction contracts including those that are not in writing. Adjudication clauses must still be in writing, otherwise the scheme for construction contracts applies.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is Frustration?

A

Frustration occurs when any event or circumstances beyond control of both parties changes the contractual obligations or makes it impossible or illegal to fulfil their contractual obligations. The happening of such events automatically discharges a contract.

Under NEC ECC this is called ‘Prevention’ – it is notified as an early warning under clause 15 and the PM gives an instruction to the Contractor stating how the event is to be dealt with (clause 19)

Prevention - event occurs that stops the contractor completing the whole of the works or stops completing whole of the works by the date for planned completion shown on the Accepted Programme.
and which neither party could prevent or an experienced contractor would have judged at the contract date to have such a small change of occuring if would have been unreasonable to have allowed for it.

The PM gives an instruction to the contracto stating how the event is to be dealt with.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the difference between an information requirement schedule & an information release schedule?

A

The information required schedule asks the Contractor to provide dates when design information if required.

The information release schedule informs the contractor when the design information will be available.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the difference between NEC and JCT?

A

The main differences between the 2 forms is its usage

NEC

can be used within the building & Civil engineering projects whereas JCT is specifically for building projects.

CE and no provisional sums, as well as EWN.

JCT has variations due to relevant matters and relevant events and NEC has Compensation Events.

17
Q

What is the role of the Quantity Surveyor?

A

Role of the QS post contract:
Value variations
Ascertain loss and/or expense
Carry out interim valuations
Prepare the final account.

18
Q

What is a Compensation Event?

A

‘Compensation events’ are events that entitle the Contactor to a possible increase in the ‘Prices’; and/or delay to the ‘Completion Date’ or ‘Key Date’.

19
Q

Please provide some examples of a Compensation Event :

A

60.1 (1) PM gives an instruction changing the Works Information (ECC4 Scope)
(2) The Employer does not allow access to and use of part of the Site …. Accepted Programme
(3) The Employer does not provide something he is to provide….Accepted Programme
(5) Default by Employer or Others
(12) The Contractor encounters physical conditions….
(13) A weather measurement is recorded…less frequently than once in ten years
(14) An event which is an Employer’s risk stated in this contract

20
Q

Please explain the Change control procedure for x Project

A

Change control is implemented by notifying the PM or the Contractor of a Compensation Event. A compensation event is an event that, if they occur, and do not arise from the Contractor’s fault, entitle the Contractor to be compensated for any effect the event has on the Prices, Completion date or a Key date. Contractor has 8 weeks to notify. PM may request a quotation; Contractor has 3 weeks to provide a quotation. The quotation is assessed and PM will notify either acceptance, request to resubmit, PM will be making the assessment. THE CE is implemented when PM notifies Contractor:
- acceptance of the Contractors quotation
- of an assessment made by the PM
- Contractor’s quotation is treated as having been accepted by the PM
When CE is implemented, the Prices, Completion Date and Key Dates are changed accordingly.

21
Q

Please explain the Early Warning Notice

A

If either the Contractor or PM becomes aware of any matter which could affect time, cost or quality that part must notify the other party as an ‘early warning’ as soon as they become aware. This triggers an ‘early warning meeting’ to discuss how best to mitigate the risk.

22
Q

What is an Early Warning Meeting?

A

An Early Warning Meeting occurs after the PM or Contractor notifies the other of an early warning. The early warning is entered into the early warning register and during the meeting those who attend make and consider proposals for how the early warning could be avoided or reduced, seek solutions that will bring an advantage to those affected, deciding on actions to be taken and responsibilities (in relation to the contract), what matters can be removed from the register and review actions recorded in the register. The PM then revised the register to record decisions made and issues the revised register to the contractor within a week from the meeting. If decision changes the scope of works the PM instructs the change at the same time as the revised register is issued.

23
Q

When is an event that complies with the compensation event clauses in 60.1 not a compensation event?

A

If it is time barred.

In the case of the Contractor, clause 61.3 requires notification within 8 weeks of becoming aware of the event. However, the Contractor would not be time
barred if he failed to notify an event which the,Project Manager should have notified to the Contractor, but did no

24
Q

How does the PM use programme in assessing CE?

A

How does the PM use programme in assessing CE?
63.5 delay to the Completion Date assessed as the length of time that, due to the CE, planned Completion is later than planned Completion as shown on the Accepted Programme current at the dividing date.
Delay to a Key Date assesses as the length of time that, due to the CE, the planned date when the Condition stated for a Key date will be met is later than the date shown on the Accepted Programme current at the dividing date.

Any delay caused by the CE already in the Accepted Programme

Events which have happened between the date of the accepted programme and the dividing date.

Dividing date
CE arises from PM or Supervisor giving an instruction or notification DD is date of that communication
For other DD is date of the notification of the CE.