Procurement and Tendering Flashcards

1
Q

What are the main types of tendering procedures?  

A

Single-stage tendering
Two-stage tendering
Negotiated tender

  • Single Stage – design and tender documentation issued to contractors, tenders are received and an appointed made.
  • Two Stage – initial tenders received based on outline spec and contractor is appointed. Detailed design is undertaken and further cost negotiations take place.
  • Negotiated – contractor is selected based on experience or previous usage. Design is procured and a cost negotiated on the design with the selected contractor
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is Procurement?

A

The overall process of acquiring construction work or services.

How the building works are obtained

Main routes - traditional, Design and Build, Management Contracting and Construction Management.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is tendering?

A

A phase in the procurement strategy. The bidding process, to obtain a price and how a contractor is actually appointed.

How the successful contractor is selected.  

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is single stage tendering, why would it be used , why wouldn’t it be used?

A

Process where the tedner is completed in a single action.

The ITT are issued and the competing contractors compete against one another, a preferred contractor is selected and is awarded the contract.

Suitable when information in ER’s is developed enough for contractor to calculate a realistic price and carry out design work in tender period.

Would not use if design a scope was not well defined. A two stage tender would be beneficial if early contractor involvement required.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is two stage tendering, why would it be used , why wouldn’t it be used?

A

Initial tenders recieved based on outline spec and contractor is appointed. Detailed design is undertaken and further cost negotiations take place.

Where ERs are not sufficiently developed for the contractor to calculate a realistic price. If required, contractor will tender first stage with a schedule of rates which can be used to establish the construction price in the second stage.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is negotiated tendering, why would it be used , why wouldn’t it be used?

A

Negotiated Tendering is a procurement method where a buyer selects a supplier based on their industry track record or previous relationship, and then negotiates the contract terms.

It’s often used for specialist contracts with limited suppliers, allowing the buyer to tailor the process to the project’s needs. This method can be more efficient and cost-effective than open or closed tendering, facilitating direct communication and collaboration. It’s commonly used in the private sector, especially in construction and engineering.

However, it can be seen as exclusive and unfair due to potential ‘cosy’ relationships, making it difficult for smaller businesses to compete. The lack of competition may lead to higher costs, favouritism, or collusion among contractors. The design could be influenced by the selected contractor, and it can be challenging for new firms to secure work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are Employer’s requirements (ERs)?

A

They set out the client’s requirements including the function, size, accommodation and quality requirements of the project.

Their level of detail depends on how much design development has been carried out prior to tender.

They normally include the current state of planning permission

It should also detail the level of design structure and specification information to be provided by the tenderers.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the Contractor’s Proposals?

A

The Contractor’s response to the ERs

Key documentation for the client to consider at the tender review

They often include plans, elevations, sections and typical details

Layout drawings and specifications for materials and workmanship are also provided.  

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is a PQQ?

A

Pre-qualification questionnaire. This stops time wasting. As uncapable contractors don’t tender, and
less tenders need to be assessed.
The document will likely include financial status, legal status, relevant experience, available
resources, performance history (H&S, claims), demonstrate project understanding.

Details of contract particulars, Company turnover, previous relevant experience and references, company accounts, management and organisational structure, H&S records, quality systems and environmental policy, provision of bonds, warranties & PCGs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What should be considered when selecting a procurement route?

A
  • The specifics of the project
  • The client objectives regarding:
  • Cost
  • Time
  • Control
  • Quality
  • Risk
  • Whether MMC is to be used? Require manufacturer early in the project.  
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the Main Procurement Methods?

A

Traditional
Design & Build
Management Contracting
Construction Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is traditional procurement?

A

Design is competed by the client’s design team before competitive tenderers are invited and a contractor is awarded the project (usually with the lowest price).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How does traditional procurement work?  

A

The contractor takes responsibility and financial risk for the construction of the works to the design produced by the client’s design team. The client takes the responsibility and risk for the design and design team performance.  

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

When might the traditional procurement route be appropriate?

A

If the employer has had the design prepared, if the design is substantially completed at time of tender.

The client wishes to retain control over the design and the spec.

If cost certainty at start on site is important

The shortest overall programme is not the client’s main priority.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are the Advantages of traditional Procurement?

A

Retaining control over the design can lead to higher quality.

It offers increased level of cost certainty before commencement.

Design changes are reasonably easy to arrange and value.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are the Disadvantages of traditional Procurement?

A

The overall project duration may be longer than others due to lack of overlap between design and construction

There is no input into design and planning by the contractor

A strategy based on price competition can lead to confrontational relations.

There is a dual point of responsibility with the design team controlling the design and the contractor retaining responsibility for the construction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What is Design and Build?  

A

Where the contractor is responsible for the design, planning, organisation, control and construction of the works to the ERs. 

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

How does Design and Build work?

A

The employer gives the tenderers the Ers and the contractor responds with the contractor’s proposals which include the price for the works.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

When might D&B be appropriate?

A

Where there is a need to make an early start on site (overlaps between design and construction.

Where the client wishes to minimise their risk as they transfer design responsibility to the main contractor.

For technically complex projects requiring the contractor’s expertise.

Where the employer does not want to retain control over design development.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What are the advantages of D&B?

A

There is a single point of responsibility for the design and construction.

There is earlier commencement on site

Early price certainty is increased

The client can benefit from the contractor’s experience harness during the design – improve buildability.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What are the Disadvantages of D&B?

A

Clients may find it hard to prepare a sufficiently comprehensive brief.

The client has to commit to a concept design early.

Variations from the original brief are difficult to arrange and are often expensive.

It is harder to compare tenders and harder to determine whether value for month is being achieved.

Variations may come up or reworks if the ERs are not clear, concise or missing vital information.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

How much design input will the contractor have on D&B?

A

Depends on the amount of design work the employer has already completed at time of tender.

This can range from full design to production information and coordination only.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Who carries out the design for the contractor (on D&B)

A

It may be outsourced to a separate design company (contractor retains responsibility).

They may have in house design capabilities or the client’s team may be novated.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

What is Management Contracting ?

A

Contractors are managed by and contracted to a management contractor. Similar to traditional but
rather than a fixed price the MC is reimbursed a % of the amount paid to the contractors

A management contractor is employed to contribute their expertise to the design and to manage construction with a management fee being paid to them for doing so.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

How does Management Contracting Work?

A

The management contractor has direct contractual links with all of the works contractors.

They have the responsibility for the construction works without actually carrying them out.

Not all of the design need to be completed before their first works contractors start work.

The MC selects the works contractors thought competitive open book tender.

The client reimburses the cost of these packages to the MC plus their management fee.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

What is competitive open book tender?

A

Competitive Open Book Tendering is a procurement method where the buyer approaches multiple suppliers and negotiates the terms of the contract with each of them. The suppliers provide a detailed breakdown of costs in their tenders, including labour, materials, overheads, profit, and contingency provision. This transparency allows the buyer to understand the real costs of a service and ensures they are not being overcharged.

Why it would be used:
* It ensures a competitive price is obtained.
* It’s useful when services are difficult to specify precisely up front.
* It allows the buyer to see into the supplier’s business and understand their pricing and margins.
* It can include incentives (and penalties) calculated as a percentage of the difference between the real cost of the project and an estimate provided up front.
Why it wouldn’t be used:
* It requires a high level of monitoring and involvement on the buyer’s side.
* It can be challenging to isolate the cost variables for which the contractor will accept sole responsibility.
* It can be counterproductive if it results in less effective contract management.
* A saving in the management fee can quickly be lost if the result is less effective operational management or failure to respond to the changing needs of the customer.
* It may not guarantee value for money. Simply knowing how supply chain costs are made up does not necessarily mean that they will be minimised.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

When might management contracting be appropriate?

A

Where the client does not want cost certainty before commencement. Where an early start on site it a priority.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

What are the advantages to Management Contracting?

A

Overall project duration is short due to overlapping design and construction

There is contractor contribution to the design and planning process.

Changes can be accommodated in package not yet let if they have no further impact.

The works are let competitively at current prices on a firm price basis.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

What are the disadvantages to Management Contracting?

A
  • The price for the works is not received until the last package has been let.
  • Changes to the design of later packages may affect packages already let.
  • There is little inventive for the Management Contractor to reduce costs.
  • In practice, the MC has little legal responsibility for the defaults of the work contract.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

What is Construction Management?

A

Contractors are contracted to the client, but managed by a construction manager. They administer and coordinate the works

The employer places a direct contract with each of the trade contractors and utilises the expertise of a construction manager who acts as aa consultant to coordinate the contracts.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

How does Construction Management work?

A
  • The trade contractors carry out the works.
  • The construction managers supervises the construction process and coordinates the design team.
  • The construction manager has no contractual links with the trade contractors or members of the design team.
  • The role includes preparation of the programme, determining requirements for site facilities, breaking down the project into suitable works packages, obtaining and evaluating tenders, co-ordinating and supervising the works.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

When might Construction Management be appropriate?

A
  • On large, complex projects where the advantages of CM can be utilised, e.g. using upfront buildability knowledge of the construction manager and their programme advise including specialist input from trade contractors.
  • Where an early start on site date is key.
  • Where price certainty before commencement is not considered a key driver
  • Where the client is experienced in construction.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

What are the advantages of Construction Management?

A
  • Overall project duration is reduced by overlapping design and construction.
  • The construction manager can contribute to the design and project planning processes.
  • Roles, risks and relationships for all parties are clear.
  • Prices may be lower due to direct contracts with trade contractors.
  • The Client has a means of redress to trade contractors through direct contractual links.
34
Q

What are the disadvantages of Construction Management?

A
  • Price certainty is not achieved until the last trade package is let.
  • Changes to packages may adversely affect packages that are already let.
  • The Client must be proactive and hands on.
  • The Client has a lost of consultants and contractors to deal with.
35
Q

What is the difference between Management Contracting and Construction Management?

A
  • Under Construction Management the client is in direct contractual relationship with each of the trade contractors and the construction manager isn’t.
  • Under Management Contracting, the Main Contractor is in direct contractual relationship with the trade contractors and the client is in contract with the Main Contractor only.
36
Q

How do you identify the client requirements before recommending a procurement route?

A

Through detailed discussions with the client and design team to identify their priorities in terms of cost, time, quality, risk, control requirements and experience.  

37
Q

If the client wishes to start on site asap, what route would you recommend? 

A

My recommendation would need to take into account their other requirements such as cost and quality.

If time was their overriding priority, then Construction Management or Management Contracting may offer the best solution as they can offer the fastest start on site with overlap of the design and construction.

This is because start on site is not dependent upon a long tender period however the key trade-off is a reduction in cost certainty.

38
Q

What would you recommend if the client wanted an early start but also cost certainty?

A
  • Design and build procurement may offer the best solution.
  • This is because it allows the design and construction to be overlapped rather than being sequential.
  • Design and construction risk is transferred to the Main Contractor with their tender being based on a lump sum price to offer high levels of cost certainty.
39
Q

What is GMP?

A

Guaranteed maximum price.

40
Q

What does GMP mean to you?

A

Guranteed maximun price

A lump sum contract under which there is no adjustment of tender price unless design changes are requested by the client.

The Contractor includes the additional risks involved in the design development process in his tender price.

41
Q

What is PFI?

A
  • Private Finance Initiative
  • A government programme launched in 1992 to bring private sector project management and expertise into the public sector.
  • The private sector is granted a concession to finance, design and Build and operate major public projects such as schools and hospitals.
42
Q

What are the three types of PFI projects?

A
  1. Financially free-standing – Projects costs are recovered by charging users (for example to roads and bridges).
  2. Joint Venture – Public and private sector stakeholders both invest however the private sector has overall control. Contributions and allocation of risk are clearly defined.
  3. Services Sold – The capital expenditure for the project is financed by the private sector then sold back to the public sector. The public sector requires clear demonstrations that this provides better value for money than option 1&2.
43
Q

What sort of projects might PFI be used on?

A
  • Its use is recommended where is offers clear value for money when compared against traditional public sector procurement.
  • It is generally considered more appropriate for larger projects of value greater than £20m and where there are significant ongoing maintenance requirements.
44
Q

What might be some of the problems associated with PFI?

A
  • High bidding costs are associate with PFI projects can take longer to procure than traditional projects.
  • Value for money is hard to achieve as the cost of private borrowing is more expensive than public sector borrowing.
  • Long term and inflexible contracts are formed which cannot response to demographic changes. For example, a reduction in school cohort numbers can lead to empty classrooms paid by local authorities.
45
Q

What is Build Lease Transfer (BLT)?

A
  • A Facility is designed, financed and constructed by the private sector and then leased back to the government for a predetermined period of time at a pre-agreed rental cost.
  • The facility is owned by the private sector partner during the lease period, at the end the government can renew the lease, buy out the private sector partner or walk away from the deal.
  • O&M of the facility during the lease period is usually the government’s responsibility.
  • This provides the public sector with a way of financing large-scale infrastructure projects based on ongoing revenue rather than using high levels of capital expenditure.
  • The primary disadvantage is that legal ownership remains with the private sector.
46
Q

What is Build Operate Transfer (BOT)?

A
  • The facility is designed, financed, operated and maintained by a concession company, for the period of the concession,
  • Ownership of the facility is vested in the host government from the time of construction completion.
  • At the end of the period, the concessionaire’s involvement in the project ends and all operating rights and maintenance responsibilities revert to the host government.
  • The concessionaire retains all toll income during the agreed period.
47
Q

What is Build Operate Transfer (BOOT)?

A

A variation on Build Operate Transfer (BOT) where ownership stays with the concessions until the end of the concession period at which time it is then transferred free of charge to the host government.

48
Q

What is partnering?

A
  • A long-term approach of structuring business relationships.
  • It involves two or more organisations working together to achieve specific mutual objectives and deliver continues measurable improvements.
49
Q

What is Project Partnering?

A
  • All members of the professional team becomes involved in the partnering process at the design stage including contractors.
  • Ownership of risk is spread between the parties and a collaborative approach encouraged to delivering the solution and overcoming the problems.
50
Q

What is Strategic Partnering?

A
  • A long-term relationship that is established with a view to undertaking a number of projects over a long period.
  • Framework agreements are used to set out the overriding contractual terms with fixed terms and conditions for future purchases.
  • Projects and services are then draw down on a project-by-project basis.
51
Q

What are the key characteristics of partnering?

A
  • More trust is achieved between the parties.
  • There is a reduced risk of adversarial relationship as pre-determined contract conditions are agreed by all parties in advance.
  • Increased cost certainty and speed of calling off contracts gained.
52
Q

What are the benefits of partnering?

A
  • The overall construction and design programme is shortened because there is a prior understanding of the Client and their requirements from potential projects
  • The potential for conflict is reduced.
  • Communication is improved.
  • Pooling of resources and ideas should result in innovative solutions.
  • Improved client satisfaction is gained.
  • Recognition of protection of profit margin for contractors and suppliers.
  • A team environment is formed that encourages innovation and technical developments.
53
Q

What is tendering?

A

A structured procedure for generating quotations from suppliers or contractors looking to obtain an award of business activity either under competition or via negotiations with a single contractor.

Tendering – a phase in the procurement strategy.

The bidding process, to obtain a price and how a contractor is actually appointed.

54
Q

What are the main methods of choosing a contractor?

A
  • Open tendering
  • Selective tendering:
    Single or Two stage
  • Negotiated tendering
  • Serial Tendering
55
Q

What is open tendering

A

Employer advertises his proposed project and permits as many contractors as are interested to apply for tender docs. Open to all that wishes to bid.

56
Q

What are the advantages of open tendering?

A

Promotes competition due to the potentially high volume of tender returns. Advocated by the European Commission when project requires technical expertise. Provides opportunities for capable firms which the clients may not have previously considered.

57
Q

What are the disadvantages of open tendering?

A

All tenderers who express an interest must be considered without any prior selection procedure. Risk of selecting a cheap contractor who is unknown. Danger of increased errors within the tender submission due to a risk of inexperienced contractors that have no prior understanding of the client’s requirements. There is no assurance that the lowest tenderer is capable of financially stable. The total cost and time needed to review the tenders is increased.

58
Q

What is selective tendering?

A

Shortlist drawn up by the project team or drawn from pre-agreed framework / approved-suppliers list. All tenderers evaluated against a set of criteria and the contract awarded to the highest scoring contractor.

There are two types of selective tendering – single and two stage.

59
Q

What is single stage tendering?

A

Single-stage tendering - The invitations to tender are issued out to contractors and the competing contractors compete against one another, a preferred contractor is selected and is awarded the contract.

60
Q

What are the advantages of a single stage tendering?  

A

Ensures only capable and approved firms submit tenders. It tends to reduce the aggregate cost of tendering. It reduces the risk of receiving tenders from unsuitable tendering.  

61
Q

What is two stage tendering?

A

Two-stage tendering involves in the first stage, a submission and evaluation of technical proposals from a number of potential contractors. A contractor is then chosen based on the quality of their bid and their team, the preliminaries price and overhead and profits the contractor has allowed for. The contractor then will help with the buildability of the project and assist the design team. The second stage includes amendments to the proposal and a submission of the tender price.

62
Q

What is the purpose of the first stage (of two stage tendering)?  

A

To select a suitable contractor by means of limited competition

Client provides an outline project design to each of the tenders. Tenderer will submit prices for helping the client develop and finalise the design using their buildability expertise. Submissions tend to consist of: schedule of rates, price for assisting the client with design development and build expertise during stage 2, confirmation of the contractors OH&P %. A preferred contractor is then appointed to assist with developing the design further.

63
Q

What is the purpose of the second stage (of two stage tendering)?

A

A negotiation process with the selected contractor on the basis of the first stage

Second Stage – following development of the design to a defined stage, a formal negotiation process is undertaken during stage 2 to agree: the final price, the contract conditions and programme.

64
Q

What do tenderers return as part of the first stage (of two stage tendering)?

A

Detailed build up of prices for the preliminaries items,
Profits and Overheads %,
a construction programme,
Proposed sub-letting of the works.

65
Q

What are the advantages of two stage tendering?

A

Early involvement of the contractor. Encouragement of collaborative working. Potential for an earlier start on site. Greater client involvement in selecting the supply chain. The contractor can help identify and manage risk.

66
Q

What are the disadvantages of two stage tendering?

A

Cost certainty may not be achieved before construction starts. Additional pre-construction fees are incurred for the main contractor. The contractor could take advantage of second stage negotiation and increase costs. Potential for parties to not agree the contract sum with a risk of retendering.

67
Q

Why should you use 2 stage tendering?

A

For complex buildings. Where the magnitude of work is unknown at time of contractor selection. If early completion is required. Where the design team would like to make use of contractors expertise on buildability issues.

68
Q

What is negotiated tendering?  

A

Single stage tender with a single tenderer who returns an initial price. This is then negotiated with the client’s team.

Contractor receives tender docs > Contractor returns with an initial price > PQS negotiates price with Contractor.

69
Q

When might negotiated tendering be used?

A

When the contractor has carried out work successfully for the client previously where they have an existing relationship.

70
Q

What could selecting the wrong contractor lead to?

A

A bad client & Contractor relationship
A dissatisfied client
An insolvent contractor
Effect in time, cost, quality of project.

71
Q

How would you put together a set of tender documents?  

A

ITT (invitation to tender letter)
Instruction to tenderers with:
Date and time for return, to whom, site visits, programme, errors procedures, scoring matric
Conditions of proposed contracts
Pricing documentation
Specifications
Drawings
ERs
Pre-Construction H&S Information
Form of tender.

72
Q

What is the form of tender?  

A

A pre-printed formal statement in which the tenderer fill sin the blank spaces

The tenderer provides their name, address and the sun of money for which they offer to carry out the works?

73
Q

How would you determine the duration of the tender period?

A

Depends on the procurement process and size of the project.

Traditional Procurement with a BoQ is being adopted allow for a month in order for the contractor to obtain pricing information for their S/C.

Large complex schemes – would need to be longer

If the tender is the 1 stage of a 2 stage tender then the tender period may be a shorter duration of 2-3 weeks

Better to ensure sufficient time so contractors can price the project correctly rather than rush and encourage contractors to price a high risk element into the tender.

74
Q

How does time, cost, quality and risk impact the deciding on a procurement route?

A

Time:
* Urgency: If time is of the essence, a fast-track procurement route may be chosen. This involves overlapping design and construction phases to expedite project delivery.
* Lead Time: Longer lead times may necessitate early contractor involvement (ECI) or design and build contracts to kickstart construction promptly.
Quality:
* Design Control: If maintaining design control is crucial, traditional procurement may be preferred. Here, the design is fully developed before tendering.
* Collaboration: Collaborative procurement models (e.g., BS 11000-1) emphasize quality through close collaboration between parties.
Cost:
* Budget Constraints: When cost efficiency is paramount, competitive tendering (e.g. single-stage or two-stage tendering) helps achieve value for money.
* Value Engineering: Procurement strategies should allow for value engineering and cost optimization during the tender process.
Risk:
* Risk Appetite: Different procurement routes carry varying levels of risk. For instance, design and build contracts transfer more risk to the contractor.
* Risk Allocation: Consider how risks related to design, construction, and unforeseen events are allocated among project participants.

75
Q

What should you include in your tender analysis report?

A
  • The background to the contract.
  • The scope of the contract.
  • Pre-qualification criteria.
  • The tender evaluation criteria.
  • Reasons for rejection of unsuccessful tenders.
  • Reasons for the recommendation.
  • A summary of any post-tender negotiations.
  • Comparison with the pre-tender estimate.
  • Any implications for the project.
76
Q

What is the difference between traditional (procurement route) with and without quantities?

A

With quantities is a BoQ. The traditional design is measured and the requirements are listed out for
a contractor to put his costs to (measures are employers risks). Without the contractor makes their
own assessment of the measures and costs (measures are contractors risks).

77
Q

What is the difference between management contracting and construction management?

A

Under construction management the client is in direct contractual relationships with each of the trade contractors and the construction manager isn’t.

Under management contracting, the MC is in direct contractual relationships with the trade contractors and the client is in contract with the MC only

78
Q

What is a framework agreement?

A

A list of contractors selected by the Client after a formal tendering procedure to work
over a long period of time

79
Q

What are the advantages and disadvantages of framework agreement?

A

Advantages include:
o Reduce tendering costs
o Quick start on site
o Buildability improved as contractor involved earlier
o Integration of supply chain
o Repeat work and continuity of projects
- Disadvantages include:
o Reduced competition resulting in higher tenders
 (Can carry out random audits & benchmarks with industry data to ensure
costs remain competitive during FA)
o Higher cost to set up at tender
o May act as barrier to some smaller firms

80
Q

What are the objectives for a framework agreement?

A
  1. Collaborative working – long term relationships
  2. Performance improvements – KPI’s
  3. Supply chain integration – specialist knowledge
  4. Savings – efficiency and innovation
  5. Maintain project team
81
Q

What is CITB?

A

CITB is the industry training board for the construction sector in England, Scotland, and Wales. They help the construction industry attract talent and to support skills development.

all opportunities over £10,000 are advertised and managed through our electronic tendering portal called Delta E-Sourcing (External link - Opens in a new tab or window) (which is provided by BIP Solutions Ltd). This portal provides a simple, secure and efficient method for managing the tender process reducing the time and effort required for both the Procurement, Commissioning and Contract Management (PCC) team and suppliers.