Project Quality Management Flashcards

1
Q

Quality Processes

A

Planning: Plan Quality Management
Executing: Manage Quality
Monitoring/Controlling: Control Quality

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Plan Quality Management

A

I: Project charter, PM plan, project documents, EEFs, OPAs
TT: Expert judgment, data gathering, data analysis, decision making, data representation, test and inspection planning, meetings
O: Quality management plan, quality metrics, PM plan updates, project documents updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Manage Quality

A

I: PM plan, project documents, OPAs
TT: data gathering, data analysis, decision making, data representation (cause/effect fishbone diagram), audits, design for X, problem solving, quality improvement methods
O: Quality reports, test and evaluation documents, change requests, PM plan updates, project documents updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Control Quality

A

I: PM plan, project documents, approved change requests, deliverables, work performance data, EEFs, OPAs
TT: Data gathering, data analysis, inspection, testing/product evaluations, data representation, meetings
O: Quality control measurements, verified deliverables, work performance information, change requests, PM plan updates, project documents updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Cost of Quality

A

Cost of Conformance (prevention costs, appraisal costs) = money spent to avoid failures
Cost of Nonconformance (internal failure costs found by project, external failure costs found by customer) = money spent during/after project because of failures

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Quality vs Grade

A
Quality = delivered performance
Grade = complexity of the product
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Product vs Project quality

A

Product quality = produce all deliverables in compliance with specs, accepted by customer
Project quality = objectives for cost/schedule/scope controlled/achieved; performed by PM plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Verified deliverables

A

Output of Control Quality

Comes before Validate Scope process / accepted deliverables