Project Cost Management Flashcards
Cost Processes
Planning: Plan Cost Management
Estimate Costs
Determine Budget
Monitoring/Controlling: Control Costs
Plan Cost Management
I: Project charter, PM plan, EEFs, OPAs
TT: Expert judgment, data analysis, meetings
O: Cost management plan
Estimate Costs
I: PM plan, project documents, EEFs, OPAs
TT: Expert judgment, analogous estimating, parametric estimating, bottom-up estimating, three-point estimating, data analysis, PM information system, decision making
O: Cost estimates, basis of estimates, project documents updates
Determine Budget
I: PM plan, project documents, business documents, agreements, EEFs, OPAs
TT: Expert judgment, cost aggregation, data analysis, historical information review, funding limit reconciliation, financing
O: Cost baseline, project funding requirements, project documents updates
Control Costs
I: PM plan, project documents, project funding requirements, work performance data, OPAs
TT: Expert judgment, data analysis, to-complete performance index, PM information system
O: Work performance information, cost forecasts, change requests, PM plan updates, project documents updates
Estimating
Bottom-up: start from activities, add up
Analogous: compare to past project
Parametric: use formula/model
Top-down: start with total then break it down
Three-point: most likely, optimistic, pessimistic = simple or weighted average
Basis of Estimates
eg, What was I thinking? original thoughts, calculations, assumptions behind estimates
Project Budget
Budget includes management reserve + cost baseline
Management reserve: time/money set aside tied to overall budget, can cover things not covered by contingency
Cost baseline / Control accounts includes cost estimates + contingencies
Contingency: for each work package, extra time/money reserved for risk reduction, released if unused
Earned Value Analysis
PV / EV / AC / BAC: Definitions
Formulas: cost variation, schedule variation, schedule performance index, cost performance index
Integrates scope/cost/schedule baselines
Cumulative actual costs compared to planned costs (Eg, did you spend less because under budget or did less work)
Planned Value (according to budget, defines physical work that should have been completed)
Earned Value (measure of work performed: planned costs of only the work performed to date)
Actual Cost: realized cost incurred
BAC / Budget at Completion (cost baseline)
Cost Variation = EV - AC
Schedule Variation = EV - PV
Schedule Performance Index = EV/PV
<1: behind schedule; >1: ahead of schedule
Cost Performance Index = EV/AC
<1: over budget; >1: under budget