Project finance SoE Flashcards

1
Q

L1 - What if an element of scope was missing from the CSA but was in the contract documents?

A

Should be deemed included

it is still in the contract, should be clauses within the contract to use the most onerous element.

this is post contract. if D&B contract would say it is the contractors risk unless was in clarifications.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

L1 - How do you manage provisional sums under the contract?

A

Provisional sums are for items that cannot be fully defined at time of tender

I am aware of the risk that the actual cost and time exceeds that allowed for in the provisional sum because the nature of the item changes between tender and instruction

I would have a separate provisional sum tracker to monitor throughout the project

Then in the final account, the provisional sums included in the contract are deducted and the actual amount substituted

How well did you know this?
1
Not at all
2
3
4
5
Perfectly