Case Study Questions Flashcards
What is the difference between D&B and Intermediate with Design Portion? Why wasn’t the latter used?
o Client wanted to fully allocate risk to the contractor
o It allows for a single point of responsibility for design and construction, resulting in earlier commencement on site as design can overlap with construction
What did you have to consider when utilising Sectional Completion?
o Difficulties with logistics on site when different sections are in possession of different parties
o The protection of completed sections from ongoing works
o The provision of appropriate insurance at all times for all sections
o The adoption of appropriate health and safety measures to deal with risks resulting from occupation of areas adjacent to, or only accessible through ongoing construction works.
o Provision of appropriate security measures
What are the consequences of Sectional Completion?
o Half of Retention is released for that section
o The Rectification period begins for that section
o The Contractor’s responsibility for insuring the works (if applicable) ends for that section.
o The Contractor’s liability for liquidated damages ends for that section.
o The employer is now responsible for any damages to the works for that section
Did you have damages associated with PC dates? How did you calculate these?
o As per the Contract, Liquidated Damages for Section 1 and 2 were £3000 per week.
o LADs are not penalties, they are pre-determined damages set at the time that a Contract is entered into, based on a calculation of the actual loss the client is likely to incur if the Contractor fails to meet the Sectional Completion dates.
o As LADs are not penalties, they must have been genuine calculation of damages when they were set. If they are not genuine, they may be seen as a penalty by the courts and therefore will be unenforceable.
We would not advise as to what level LADs should be set at however, as our PI would not cover.
Client would factor in, cost of borrowing if dates not met as well as LAD’s owed to the Employer through the AFL.
Did you have damages associated with PC dates? How did you calculate these?
o As per the Contract, Liquidated Damages for Section 1 and 2 were £3000 per week.
o LADs are not penalties, they are pre-determined damages set at the time that a Contract is entered into, based on a calculation of the actual loss the client is likely to incur if the Contractor fails to meet the Sectional Completion dates.
o As LADs are not penalties, they must have been genuine calculation of damages when they were set. If they are not genuine, they may be seen as a penalty by the courts and therefore will be unenforceable.
What other methods of procurement could you have used in this project?
o Traditional, Construction Management or Management Construction
What is the difference between a Greenfield and Brownfield site?
o Brownfield – any site that has been built on
o Greenfield – land that has not yet been developed
What surveys were missing from the tender pack? And why did this risk not transfer to the Contractor?
o EAI – Lowering of services & alternative off site drainage – contractor stated within their Qualifications list “excluded any costs associated with incoming statutory disconnections, diversions or new suppliers and metering, there were originally included as a provision but have been removed and administered and paid for by the client”. The Contractor stated they issued their drainage budget quickly as a budget to reflect the drawing within the tender pack. This showed maximum depths around the saddle connection location of less than 2m whereas the actual design received later showed depths between 3.5m-5m. Therefore the drainage budget was so much lower than the quoted cost.
o EAI – Removal of concrete slab – not picked up within tender pack.
o EAI – Additional gas membrane layer – the modular floor was not considered a suitable structural barrier, there decided to install an additional gas membrane layer, to achieve the desired 3 gas protection points
What mitigation measures did the Contractor impose to reduce delay?
o Employer may instruct contractor to accelerate the works
o JCT states a contractor is to “use his best endeavours” to prevent delay
o Contractor could re-programme the works
o Engage alternative suppliers
o Replace staff on site who are underperforming
o The duty to mitigate does not require the contractor to expend additional costs or carry out a change in scope any more efficiently than the original scope
Where would you find Acceleration in the Contract?
o Contract Particulars
o Supplemental Provision 4 – Acceleration Quotation
What is the time period for deciding on receipt of an EOT?
o 12 weeks
o However if completion date is less than 12 weeks away, the CA has to make best endeavours to make a decision before that date
What things would you do to communicate to the client on a regular basis
o Regular communication, whether verbal or in writing
o Weekly meetings
o Monthly reports
You mentioned you took over this project. How does your company manage date of transfer and how did you bring yourself up to speed on the project?
o Before my ex colleague left, we had regular meetings, to get myself up to speed with the project.
o He showed me where all files are located and what the current status was and any immediate actions that needed to be dealt with were
o He also left formal handover notes that I would be able to refer back to
o Whilst always complying with the ISO9001 Accreditation our firm has recently achieved. Whilst also complying with the General Data Protection Regulations and the Data Protection Act.
In terms of client care, how did you communicate the design change of the attenuation tank?
o Early warnings
o Risk register
o Frequent communications
More generally…
QA Procedures
Second set of eyes should never been the clients
Comp check
How come the engineer did not get approval for this?
o Anglian Water are not a statutory consultee therefore did not comment on the designs strategy during the planning stage
o The Essex County Council Lead Local Flood Authority (LLFA) who were a statutory consultee, deemed the proposed run off rate as acceptable and that there is no additional flood risk from the development to the receiving system.
- When you consider a relevant matter do you also consider a relevant event?
o Depends if there was a delay to the practical completion date
o A relevant event does not necessarily entitle the contractor to claim loss and expense.
o To claim loss and expense, a relevant matter must have occurred
o Relevant matter need not necessarily result in delay to the completion date
What were the Relevant Events for the EOT claim?
o Delay in giving the contractor possession of site
o Variations
o Clause 2.26 in the Contract
Could the contractor have mitigated this delay?
o No, as aborted works had to be dug up and re-installed.
For an EOT a contractor does however have to make all reasonable endeavours to mitigate delay
How would you value the new instruction of the attenuation tank. Once the instruction was issued, how would you assess this in your valuation?
o The contractor provided a quote for the increased tank
o The senior QS on the job reviewed
o In this particular example, the QS noticed an opportunity to achieve a saving through economies of scale, as the original quote was pro rata.
o This variation would then be included in an interim valuation
As a PM/EA, how did you assist in the valuations?
o Ensuring deadlines/timelines were met via the Contract.
You mention this could of gone to adjudication, is that true or would there be other steps before entering a formal dispute?
o Mediation, Conciliation and Negotiation could have been considered as less formal methods of Alternative Dispute Resolution (ADR).
What is the purpose of a performance bond?
o Typically provided by banks or insurance companies
o A tripartite contract between the Employer, the Contractor and the surety.
o Given the employer a guarantee of payment up to a stated amount of money (usually 10% of the contract value, premium for taking out the bond is added to the contract sum) should they suffer as a loss as a result of the contractor’s breach of their contractual obligations
o Employer have to prove that the contractor has defaulted in their obligations under the main contract and that loss has been suffered
What are examples of other types of bonds in the construction industry?
o Tender bond – covers the party inviting the tender if the lowest tenderer refuses to enter into a contract with them. Encourages to put in a serious price.
o Usually 1-5% of the tender sum
o Retention Bond – instead of deducting retention from each interim payment
o Should be same as if retention were deducted e.g 3% of the contract sum
o Advance payment bond – to guarantee the reimbursement of the advance to the employer should the contractor default
o Materials off site bond – covers the employer against loss or damage to materials already paid for (via interim valuations) before the materials are delivered to site