Development/project briefs SoE Flashcards

1
Q

What are the different types of brief?

A

Statement of need which is the first attempt at defining the possible requirements for a project.

the strategic brief develops on from the statement of need and describes the client’s requirements in sufficient detail to allow the appointment of consultants.

the project brief is the key document upon which the design will be based.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What would you do if the client’s brief changed midway through the project?

A

I would document the change and coordinate with the design team and report back to the client on the consequences.

statutory approvals

affect procurment

cost implications

programme implications

review contract

Review the cashflow

assess with the design team

Issue any variations/instructions into the Contract if needed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

L3 So what was your further advice to the client to resolve the bathroom finishes in Leeds 1?

A

I created an excel document, which had the spec of what was being proposed compared to the contract spec

The client from this was able to decide what he wanted to change or keep.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is a project brief?

A

o The project brief is crucial for defining the clients requirements for the project

o It needs to be in enough detail, to facilitate the design and specification of the project

o Live document – will evolve over time as the design development progresses

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the WELL rating you refer to in your brief?

A

o Created 7 years ago – American

The WELL Building Standard comprises of:
o Air – strategies to promote clean air and reduce indoor air pollution
o Water – well promotes high quality water – proper filtration and regular testing
o Nourishment – limits presence of unhealthy foods
o Light – provides illumination guidelines that minimise disruption to the body’s circadian system, enhance productivity and good sleep.
o Fitness – encourages exercise
o Comfort – considers, thermal, acoustic, ergonomic comfort
o Mind – optimises cognitive & emotional health
o Innovation – allows for innovation by allowing projects to submit ideas for new ideas under WELL concepts.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How is WELL scored?

A

o Independent assessor assessing each category independently

o Numerical scale

o Pre-conditions – all must be met to achieve WELL certification

o Optimisations – not required to achieve silver level but work as a flexible way to achieve Gold/Platnium

Lower scores (0 – 4) comprise the compulsory Precondition features; a score less than 5 would denote failure to meet the Preconditions in that concept and thus failure for overall certification or compliance. Silver scores (5 – 6) mean that all compulsory Precondition features have been met in the concept. Gold scores (7 – 8) and Platinum scores (9 – 10) comprise the non-compulsory Optimizations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

L3 - What were the RIBA stage 1 deliverables you refer to in the PBSA in Manchester 3?

A

o New Build
- Existing context plan
- Site constraints
- Proposed bulking & massing studies
- Outline planning narrative and draft pre-app proposal
- Outline landscaping proposals
- Measured survey
- Outline response to sustainable transport measures

o Refurbishment
- Existing condition survey (Digital mapp plotted to scale of all existing features on the property and their spatial relationship to the right of way or boundary of the property)
- Ensuring the aesthetics fitted within the client’s design guide

o Decarbonisation
- Utilities survey
- Sample part L calculations (heat loss calculation)
- Target EPC rating of B
- Avoid demolition if possible and re-use existing buildings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What generally are the key project deliverables at RIBA stage 1?

A

o Securing approval of project brief by the client and confirming that the accommodation being proposed can be achieved on the development site

o Preparing the project brief

o Site appraisals

o Feasability study

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What would be included within a project brief?

A

o Client and project background – stakeholders, planning history, client culture, organisational structure

o Projects requirements – key milestones, criteria for success

o Financials – budget, funding proposals

o Site information – existing site surveys, existing drawings & site access

o Spatial and technical requirements – schedules of accommodation, areas and spatial requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How did you ensure the requirements of the project brief were met through the design and construction phase?

A

o Reviewing the design at completion of each of the RIBA stages and checked this against the clients brief. Getting client sign off on the updated brief at the end of each design stage.

o Maintaining engagement with end user & third party stakeholders

o Capturing changes via the change control process

o Reviewed and updated the PEP when necessary

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Who would be examples of third party stake holders?

A

o Landlord whose approval is required for the works

o A local pressure group who might object to the works

o An adjoining owner who might have compensation rights through rights of light

o An existing tenant or occupier who still has a need to access the building

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How would you manage the stakeholders?

A

o Firstly identifying all stakeholders (Retail Park Managing Agent – CBRE)

o Clarify whether they support or object to the project

o Project team can form a strategy on whether each stakeholder group needs to be engaged or not

o If applicable the team can undertake this through the appropriate action at each relevant stage of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What legal and regulatory issues would you typically consider within the project brief?

A

o S106 obligations
o Planning permission status
o Building regulation approvals
o Highway approvals (S.278)
o 3rd party wall considerations
o Oversailing or scaffolding licences
o Agreements for lease
o Rights of light
o Wayleaves/easements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What specific licences were required for access in ‘Portfolio 1’?

A

o Party walls notice – neighbouring buildings

A Party Wall Notice must be given to your neighbours to provide them with notice of the works you intend to carry out to the party wall in question, between two months and a year in advance of the work starting.

o Temporary Traffic Regulation Order (TTRO) – cherry pickers etc.

A Temporary Traffic Regulation Order (TTRO) is the legal process used to temporarily stop or limit vehicles or pedestrians on the highway. TTROs can last up to 18 months and can be applied to roads, footways or Public Rights of Way (PRoWs).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Why were the bathroom finishes in Leeds 1 not correct?

A
  • Contractor had struggles with procurement/supply
  • Those samples recieved, did not match the client’s requirements
  • Client wanted more luxury looking items
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What were the L2 Examples?

A

Manchester 2 - Achieving WELL Rating

Portfolio 1 - initial research and feasibility to develop scope of services and brief

17
Q

What were the L3 examples?

A

Leeds 1 - Bathroom finishes

Manchester 3 - Victoria Point - communicating brief to Architect team

18
Q

What is a Feasibility Study

A
  • A feasibility study is used to analyse and assess the sustainability and viability of a construction project.
  • The end output of undertaking the feasibility study is to understand
    whether the project is viable by assessing the practical aspects of
    the project and by identifying its potential strengths and
    weaknesses.
  • By undertaking the exercise objectively, an accurate view on the
    viability of the project can be determined.
  • This allows the project stakeholders to make informed decisions on
    any changes that may be required on the project and whether to
    proceed to the next stage.
  • The feasibility study should be structured in a way so the client can
    make an informed decision on whether to proceed to the next
    stage.
19
Q

What are the components of a feasibility study?

A

The main components of a feasibility comprise of:

  • Planning Permission status
  • Legal & Statutory Issues
  • Analysis of the budget relative to client requirements
  • Assessment of site information provided by the client
  • Site appraisal information include geotechnical studies, ground contamination, availability of services, land easement and environmental considerations
  • Operational & Maintenance Issues
  • Programme Considerations
  • Procurement Strategy
20
Q

Who prepares the project brief?

A
  • Typically it is the client team who will gather information and compile the project brief.
  • The consultant team will then typically review the brief to assist with its development, this is usually achieved by raising queries, engaging project stakeholders and identifying any areas of missing information and working out the next steps
  • For example if little to no information is known about the existing site, then initial site investigations may be commissioned and their findings fed back into the project brief
21
Q

What procedures did you adopt to ensure the requirements of the
project brief were met throughout the design and construction
phase?

A
  • I reviewed the design at completion of each RIBA work stage and
    checked this against the client brief’s to ensure the clients
    aspirations were being achieved
  • I ensured that engagement with end user stakeholders was
    maintained throughout the project to ensure the design being
    proposed was suitable for their operational requirements
  • I captured design changes within the scope of works through the
    change control process and reviewed the project execution plan to
    ensure suitable processes were in place
22
Q

When the project brief is agreed, how are subsequent changes
incorporated?

A

The change control procedure set out within the project execution
plan is implemented to capture the change subject to the required
levels of authorisation being obtained