Project Finance Flashcards
What is a Cost Plan?
Cost planning is producing an estimate based of historic data, such as internal benchmark data.
Who prepares a cost plan?
The Quantity Surveyor
What types of cost plan are there?
Elemental Cost Plan.
• Initial Cost appraisal.
• Approximate quantities cost plan.
• Pre-tender estimate.
What is an initial cost plan?
A pre-estimate of the various cost options available at feasibility stage.
What is a feasibility study?
Preliminary studies undertaken in the early stages of a project, analysing whether a project is viable, and what options there are relating to construction methods etc.
What is an Elemental Cost plan?
A cost estimate prepared at the project brief, which is developed throughout the detailed design.
How does an Elemental Cost Plan evolve?
Initially each item is a percentage of the overall figure, or budget. This gets more detailed as the design develops, through measuring drawings, using sub-contactor prices etc.
What is an approximate quantities cost plan?
A cost estimate carried out at detailed design stage, based of approximate quantities.
What is a pre-tender estimate?
Prepared alongside the tender documents, they are an estimate of the total build cost at tender stage.
What is the Contract Sum?
The agreed value for carrying out the works in accordance with the contract
What is an Estimate?
The likely cost of something based of the limited information provided at the time.
What can you use to value a estimate?
- Use Build Construction Information Service, value a building on a price per square foot.
- Can use historical data, i.e. for care homes we work on, we can provide budget prices based on a price per bed etc.
What information would you require to potentially establish a budget?
- Size or number of beds etc.
* Location
What is a Cash Flow Forecast?
A prediction of the incomings and outgoings of cash with in a business/project.
What are the two types of Cash Flow Forecast?
- Organisational Cash Flow.
* Project Cash Flow.
What is Organisational Cash Flow?
- Used for planning and analysing company health.
* It is used to predict the incomings and outgoings of cash within a business over a specific period.
What is Project Cash Flow?
- Used for determining he amounts of cash that will be paid to a contractor, and the time they will be paid.
- Can be used to monitor performance by comparing value of interim valuations against cash flow forecasts.
What other methods of Cash Flow Forecast do you know?
The ‘S’ Curve Method.
What is the ‘S’ Curve method?
• A general principle, that a typical construction will follow:
o Low initial start costs.
o High costs in the middle as the majority of the works is undertaken.
o Low finish costs from demobilisation etc.
What would you do if you received a valuation from a Contractor that was massively over the Cash Flow Forecast value?
- Check contractors progress on site, to see if they are ahead of programme.
- See if they have re-sequenced the works.
- It may mean that the contractor is in distress.
- It might mean that the Cash Flow Forecast is incorrect.
What would you do if you received a valuation from a Contractor that was massively less than the Cash Flow Forecast Value?
- Check progress on site, they might have re-sequenced the works.
- Might mean that the contractor is behind programme.
- It might mean that the Cash Flow Forecast is incorrect.
What is a Works Breakdown Structure?
- It organises the project into manageable sections, comparing budget against the actual value of the works in a hierarchy structure.
- From this you are able to analyse each aspect of a project for its profitability.
What are the Four Stages of a risk assessment?
- Identify the risk.
- Evaluate the risk in terms of severity and impact.
- Produce a response to the risk, i.e. take measures to mitigate it.
- Report back how successful the mitigation method was for future application.
What is Value Engineering?
• An approach undertaken to try and deliver the employers requirements at minimum cost, without compromising the quality or function required.
What is Value Management?
• A method of identifying the most important aspects of a project from the client’s perspective, and ensuring that they are achieved to the required standard. Any left over budget can be used on the less important aspects.
What is included within preliminaries?
- Supervisions.
- Welfare.
- Mobilisation/demobilisations.
- Temporary Service
- Site Offices.