Programming & Planning Flashcards
How do you get the client to buy into the milestones within the programme?
Regular reviews of the contract with the Client and explaining the cause and effects of decisions to the Contract.
Who owns programme float?
No clear rule – generally it belongs to the contractor
The contractor normally includes float in his programme to accommodate his risk items and also provide time for correcting mistakes
When there is a delay at the middle of the project, would you consider the actual delay or the delay for the whole period?
The actual delay caused by the item in question.
It is not fair to offset against any float time the contractor may have built up through good progress.
What is a programme?
A programme describes the sequence in which tasks must be carried out so that a project (or part of a project) can be completed on time.
What do programmes identify?
- Dates and durations allocated to tasks.
- A critical path (the sequence of critical tasks upon which the overall duration of the programme is dependent).
- Tasks which can only be carried out after other tasks have been completed.
- Tasks which can be carried out simultaneously.
- ‘Float’ within tasks that are not on the critical path (that is, delays that can be incurred without affecting the critical path).
- The need for specific resources such as plant, services or materials and their lead time.
Can you name some types of Programming Techniques
- The Critical Path Method (CPM).
- The Program Evaluation and Review Technique (PERT).
Who’s responsibility is it to monitor the contractors working schedule?
The PM’s so they can check?
- check it complies with the client’s time requirements
- check it acknowledges any restraints imposed on the construction of the works
- ensure that the level of detail is appropriate for the illustrating the progress of the works
- ensure it suitable for monitoring the progress of the works
- confirm the sequencing and logic of the schedule
What is the critical path?
- The shortest sequence in which a project can be completed in.
- It is also considered to be the projects bottleneck..
What is PERT?
Programme, Evaluation, and Review Technique
You create three estimates for the duration of a project,
- The most Optimistic (Shortest)
- The most pessimistic (Longest)
- The most likely (an average of the two)
What can be identified from the project programme?
- The overall Start Date.
- The overall Completion Date.
- The start date for each activity.
- The completion date of each activity.
- The amount of ‘Float’ each activity has.
- The Critical Path.
- Tasks which can only be carried out sequentially.
- Tasks which can be carried out simultaneously.
What should a programme help you do?
- Plan Activities.
- Monitor progress.
- Manage Resources.
What types of Programme are there?
- Contractors Master Programme.
- Clients Overall Programme.
- Design Programme.
- Information Release Schedule
What goes into the Clients Overall Programme?
- Everything, from the appointment of the consultant, through to the completion of the project.
- This will include work outside the scope of the main-contractor.
What goes into the design Programme?
• It describes the sequence of design tasks, i.e. from the process of design from inception through the Technical Design.
What goes into an information release schedule?
- The dates by which information needs to be released by the design team, to avoid any delays.
- This works both ways, for example when the contractor has a Contactors Design Portion.
What goes into the Contractors Master Programme?
• The schedule and sequence of construction activities.