Programming & Planning Flashcards

1
Q

How do you get the client to buy into the milestones within the programme?

A

Regular reviews of the contract with the Client and explaining the cause and effects of decisions to the Contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Who owns programme float?

A

No clear rule – generally it belongs to the contractor

The contractor normally includes float in his programme to accommodate his risk items and also provide time for correcting mistakes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

When there is a delay at the middle of the project, would you consider the actual delay or the delay for the whole period?

A

The actual delay caused by the item in question.

It is not fair to offset against any float time the contractor may have built up through good progress.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is a programme?

A

A programme describes the sequence in which tasks must be carried out so that a project (or part of a project) can be completed on time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What do programmes identify?

A
  • Dates and durations allocated to tasks.
  • A critical path (the sequence of critical tasks upon which the overall duration of the programme is dependent).
  • Tasks which can only be carried out after other tasks have been completed.
  • Tasks which can be carried out simultaneously.
  • ‘Float’ within tasks that are not on the critical path (that is, delays that can be incurred without affecting the critical path).
  • The need for specific resources such as plant, services or materials and their lead time.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Can you name some types of Programming Techniques

A
  • The Critical Path Method (CPM).

- The Program Evaluation and Review Technique (PERT).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Who’s responsibility is it to monitor the contractors working schedule?

A

The PM’s so they can check?

  • check it complies with the client’s time requirements
  • check it acknowledges any restraints imposed on the construction of the works
  • ensure that the level of detail is appropriate for the illustrating the progress of the works
  • ensure it suitable for monitoring the progress of the works
  • confirm the sequencing and logic of the schedule
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the critical path?

A
  • The shortest sequence in which a project can be completed in.
  • It is also considered to be the projects bottleneck..
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is PERT?

A

Programme, Evaluation, and Review Technique

You create three estimates for the duration of a project,

  • The most Optimistic (Shortest)
  • The most pessimistic (Longest)
  • The most likely (an average of the two)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What can be identified from the project programme?

A
  • The overall Start Date.
  • The overall Completion Date.
  • The start date for each activity.
  • The completion date of each activity.
  • The amount of ‘Float’ each activity has.
  • The Critical Path.
  • Tasks which can only be carried out sequentially.
  • Tasks which can be carried out simultaneously.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What should a programme help you do?

A
  • Plan Activities.
  • Monitor progress.
  • Manage Resources.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What types of Programme are there?

A
  • Contractors Master Programme.
  • Clients Overall Programme.
  • Design Programme.
  • Information Release Schedule
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What goes into the Clients Overall Programme?

A
  • Everything, from the appointment of the consultant, through to the completion of the project.
  • This will include work outside the scope of the main-contractor.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What goes into the design Programme?

A

• It describes the sequence of design tasks, i.e. from the process of design from inception through the Technical Design.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What goes into an information release schedule?

A
  • The dates by which information needs to be released by the design team, to avoid any delays.
  • This works both ways, for example when the contractor has a Contactors Design Portion.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What goes into the Contractors Master Programme?

A

• The schedule and sequence of construction activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Can you employ a consultant to produce a programme?

A

Yes, on large projects they can prepare the outline programme.

18
Q

What should you consider when preparing a programme?

A
• Items with a long lead-in.
• Pre-contract works.
• Pre-fabrication elements.
• Works outside of the main contract.
• Relationships with other projects.
• Phasing and Sectional Completion.
BD Department
19
Q

What should a PM do when receiving a contractors programme?

A

• Check that it is not front loaded.

- Check the activity timescales are reasonable and realistic

20
Q

What is a Gantt chart?

A

• A way of displaying a programme, through a combination of bars, each relating to an activity and having a specified duration.

21
Q

What does a Gantt chart programme show?

A
The:
o Start Date.
o Duration.
o Completion date.
o Of both activities and the project as a whole.
22
Q

What are the advantages of a Gantt chart?

A
  • Suitable for smaller projects.
  • It is suitable for construction as it offers a high level of detail.
  • To detailed for cost planning and estimates.
  • It shows the times to scale.
23
Q

What is Critical Path Analysis?

A

• A way of analysing the programme, to see if the critical path duration can be shortened or activities on it altered.

24
Q

What do you aim to identify when undertaking a Critical Path Analysis?

A
  • Any items with slack float which can be used to improve the programmes critical path.
  • Identify the risky items within the programme, i.e. items on the critical path that also have significantly long lead-in-times on materials etc.
25
Q

What is a Key Milestone?

A

• Specific points along the programme used to measure progress.

26
Q

What is the benefit of having Key Milestones?

A

Helps the project keep site of:
o The key dates.
o The Key Deadlines.

27
Q

What is Float?

A

• The amount of time an activity can be delayed, before it impacts on the completion of the works.

28
Q

Can tasks on the Critical Path have float?

A

• No, if they did you would identify them through Critical Path Analysis and amend the programme.

29
Q

What are the types of Float?

A
  • Total Float.

* Free Float.

30
Q

What is Total Float?

A

• The amount of time an activity can be delayed, before it impacts on the overall completion date.

31
Q

What is Free Float?

A

• The amount of time an activity can be delayed, before it impacts on the start date of another activity.

32
Q

How can you monitor progress on site?

A
  • Compare progress to programme.
  • Compare Valuations against cash flow forecast.
  • Use the ‘S’ curve principles.
  • Milestone Chart.
33
Q

What does PEP stand for?

A

• Project Execution Plan.

34
Q

What does a Project Execution Plan Do?

A

• Sets out the strategy for managing a project, by defining who does what, and how.

35
Q

What might be included within an Project Execution Plan?

A
  • The Project brief.
  • The drawings.
  • The Procurement Strategy.
  • The Programme.
  • The Risk Assessments and Methods Statements.
  • The Health and Safety Strategy.
  • The Quality Assurance Policy.
36
Q

What does ISO Stand for?

A

• Internal Standards Organisation.

37
Q

What is the benefit of having ISO?

A

• It will imply that the product/organisations services are safe, reliable and good quality.

38
Q

What is ISO 9001?

A

• A Quality Management system, used by organisations who want to prove that they consistently meet the needs of their clients.

39
Q

What are the Three types of delay?

A
  • Contract Led.
  • Client Led.
  • Neutral.
40
Q

What is Concurrent delay?

A

• Where multiple delays for numerous causes overlap. The difficulty is in determining the root cause.

41
Q

What types of concurrent delay are there?

A
  • Parallel Fault.
  • Overlapping Events.
  • Truly Concurrent Events.
42
Q

How do you assess Concurrent Delay?

A

• You must determine the root cause, true concurrent delay is actually very rare.
• Once you determine the root cause, you should really discard any other delays.
• Use the Malmaison approach.
o This is where if it is considered that one of the delays is the clients risks, then the contractor should be entitled to a Extension of Time without loss and expense.
o It will have to claim for loss and expense separately.