Project Finance Flashcards
- You mention an ROC, what would you expect to see in developing the ROC further?
At Feasibility you would have a cost per sqm, This develops to an elemental cost plan, to a PTE and sometimes post tender cost plan.
- Source of cost data?
Benchmarking from previous similar projects, BCIS, spons, manufacturing
- What is a provisional sum?
A provisional sum is an allowance included in a fixed price construction contract for an item of work that cannot be priced by the contractor at the time of entering the contract. You can have both defined and undefined provisional sums.
- What are defined provisional sums
Defined provisional sums are those which have been described in sufficient detail that the contractor is expected to have made allowance for them in their programming, planning and pricing preliminaries.
The work may not have been completely designed but the following information may be known:
* The nature and construction of the work.
* How the works may impact on the existing building or surroundings.
* The quantities that indicate the scope and extent of the work.
* Any specific limitations.
An example might be where a defined amount of brickwork is required, but the exact design has not be finalised and so the price cannot be accurately determined.
- Undefined provisional sums?
Undefined provisional sums are less well described and so the contractor cannot be expected to make allowance for them in their programming, planning and pricing preliminaries.
An example of an undefined provisional sum might be work required below an existing structure, where the ground conditions, and so the extent of work required, cannot be determined until the structure is demolished and the ground opened up.
With undefined provisional sums, the client typically bears the price and scheduling risks.
- NRM – What does it stand for and what is it?
New rules of measurement (NRM) is a suite of documents written to provide a standard set of measurement rules that can be understood by anyone involved in a construction project. They comprise rules for the measurement of the construction, repair, renewal, maintenance and demolition of built assets. The suite provides essential guidance to all those involved in the cost management of construction projects. The NRM suite comprises three volumes:
* NRM 1: Order of cost estimating and cost planning for capital building works
* NRM 2: Detailed measurement for building works
* NRM 3: Order of cost estimating and cost planning for building maintenance works
- How many NRM editions are there and what are they?
Three
* NRM 1: Order of cost estimating and cost planning for capital building works
* NRM 2: Detailed measurement for building works
* NRM 3: Order of cost estimating and cost planning for building maintenance works
- Tell me about the cost plan and how it develops with the project?
Becomes more detailed as the project develops
RIBA 1 – Order of cost estimate
RIBA 2 – Cost per sq M
RIBA 3 – Deviated price per m sq
RIBA ¾ - Pre and post tender estimates
- Give me an example of how you have used cash flow on one of your projects?
On the CAMUS project we used cash flow to assist with managing resource requirements for different stages of the methodology, we used it to manage risk, and manage milestone payments and invoicing to ensure we met the clients’ requirements to achieve a certain mount within each financial year.
- NEC 4 payment process and timescales?
- The Project Manager assesses the amount due at each assessment date
- The Contractor submits an application for payment to the Project Manager before each assessment date setting out the amount the Contractor considers is due at the assessment date. The Contractor’s application for payment includes details of how the amount has been assessed and is in the form stated in the Scope
- The Project Manager certifies a payment within one week of each assessment date
- Each certified payment is made within three weeks of the assessment date or, if a different period is stated in the Contract Data,
- What information would you find in a project cost report?
A project cost report captures historic and forecast costs across a construction project. Typical cost report headings are given below:
* construction costs
* professional fees
* statutory fees and charges
* third-party costs
* direct works costs
* land costs
* agency costs
* finance cost; and
* legal fees.
- What are the risk categories?
Employer change risk
Construction risk
Design development
Construction risk
Design development
Contract
H&S
Design
Financial
Procurement
Programme
Operational
Policy
- Give me some examples of some preliminaries
Site establishment
Temporary services
Security
Safety environmental protection
Cleaning
Maintaining site records
Insurance
Bonds
How were you involved in the project cost reporting?
- Forecasting
- Reporting into PMR
- Tracking cashflow against progress
Benefits of using cashflow forecasts
- Identify cashflow problems
- Helps ensure that the timing of the inflow and outflow is sufficient
- Potentially identify where customers are not paying on time
- Enables the business the check they are meeting a financial objective
- Allows a business to track reported revenue with cash receipts
How does a well managed change control process feed into good financial management?
A well controlled process will mean programme and cost are dealt with as stated within the contract at the time of the event, costs will then be agreed, incorporated, and recorded meaning by the time you get to the final account all costs are clear and accounted for.
How can cash flow be utilised as a PM tool?
Cash flow can be tracked and monitored, if overspending it could signal being ahead of programme, and if underspending it could be an indication of delay within the programme. Cashflow can therefore be assessed against programme to inform any resequencing or phasing of works.
- Are there allowances for provisional sums under NEC?
No
What is the impact of the PM not issuing the payment certificate?
Each certified payment is made within three weeks of the assessment date or, if a different period is stated in the Contract Data, within the period stated. If a certified payment is late, or if a payment is late because the Project Manager has not issued a certificate which should be issued, interest is paid on the late payment. Interest is assessed from the date by which the late payment should have been made until the date when the late payment is made, and is included in the first assessment after the late payment is made.
Additionally the contractor’s original application for payment will stand as a “default payment notice