Case study Flashcards

1
Q

What level of cost detail have GT provided to establish whether their proposal is based on robust supply chain selection and tendering?

A

They must qualify with the QDC requirement and provide a minimum of three quotations per works package.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Mclaughlin and Harvey stated their reason for withdrawing was resourcing another bid, was the ITT issued late?

A

It was issued slightly later in the year than stated in the initial engagement due to a delay obtaining Cabinet office approval.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How was the Market engagement undertaken?

A

RFI’s were issued questioning the interest issued with a few lines overview of the project.
Questions were asked around the contract and if there was a preference to split or not, there were also questions surrounding what would make the contract more appealing.
Following the RFI’s, engagement sessions were had to give more detail on the project around design, sites, outcomes, brief, cost, risk.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

The ITT docs were only issued to 2 nr contractors? Was there a selection process to identify these contractors and why only 2 nr?

A

Contractors available were dictated by the LOT under the CCS framework in which 18 were available, only two received the ITT as they were the only ones who responded to the EOI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How much over budget was the GT ROC?

A

45% over the approved budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

QDC – What is this and what were the implications?

A

Qualifying Defence contract – applicable when there is only one supplier / negotiated tender meaning there is a requirement for additional information in the tender return including three quotations for each works package that forms the overall price to ensure a fair tender return and VFM.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

If you did the process again, would your advice to the client remain the same?

A

I would have pushed harder to have a commercial strategy earlier, and possibly advised going out to tender earlier at end of RIBA 2 into a 2 stage D&B route.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

In the instance of having 3 contractors involved, and one requested an EOT to the tender return date, what would you do?

A

Have a discussion with the client to discus programme impact, and weigh up the risk of delay vs the contractor dropping out and any impact this would have on the competitive advantage of the procurement exercise. If agreed this would be communicated through the e-tendering portal, all contractors would be notified of the EOT.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What does working in MOD impose on how you manage a project?

A
  • Hierarchy
  • Security
  • Process driven
  • Clear brief and desired outcomes
  • Frameworks adopted
  • Set templates
  • Set processes, procedures and timescales
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Why was the CCS was the chosen framework for this project, and were other frameworks considered?

A

A procurement workshop was held in January 2022 where the following frameworks were considered:
* Crown Commercial Services Modular Building Solutions – this framework was not viewed as suitable due to the design and nature of the works required.
* SCAPE - this route was not deemed appropriate due to the complexity of schemes and potential risk by engaging within only one supplier.
* Crown Commercial Services - Construction Works and Associated Services – deemed most suitable due to the number of suppliers available including capability and competitiveness. The workshop concluded that the CWAS is a known framework to DIO, offering several lots and access to suitable suppliers.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What was the cost & technical split in the ITT?

A
  • Technical 60%
  • Social Value 10%
  • Cost 30%
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Option C was adopted, were other contract options considered?

A

Yes option A & Option C were considered.
Option A was discounted on the basis of current market conditions and hyperinflation which has resulted in an industry reluctance to sign up to an Option A contract. This was confirmed in feedback sought during the RFI stage.
Other DIO projects have recently encountered supplier inability to sign up to the tender validity period, in some instances of no greater than 30 days due uncertainties within the supply chain. This is not achievable within the tender process where a standard period of 90-120 days is required to seek necessary approvals.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are the disadvantages to use of option C on this project?

A

Option C may have drawbacks in a competitively tendered environment, where Contractors are more likely to offer unsustainable prices to win the contract with a view to increasing the target price during delivery. This risk will need to be fully considered at the evaluation stage, however noting that this is a ‘call off’ competition such risk will lesson in selecting this option. The rates held at FW can be carefully reviewed and analysed prior to award with the support of a DIO Quantity Surveyor (QS) to mitigate further

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What were the reasons for opting for an NEC option C contract?

A

o Cost certainty achieved at the offset
o Current DIO preference
o A cost-plus contract which permits a pain/gain share mechanism in relation to an agreed target-built cost from an activity schedule.
o Likely to be more attractive to industry than the original intention of a fixed price firm contract as it permits payment of defined costs plus or minus savings or over-spend.
o This Option provides a more collaborative approach in working with industry to lessen the perceived risk in entering a contract of this nature and value.
o In utilising Option C, the financial risk is reduced for the Contractor operating through a cost reimbursable approach. This is likely to attract greater competition for the project whilst also incentivising the contractor to drive savings and deliver

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Disadvantages to one contract for all three sites?

A
  • Risk of delivery placed on one contractor. The process will place even more emphasis on selecting the most appropriate contractor.
  • The combined cost (capital and revenue) including VAT may necessitate additional scrutiny if works to all three sites are procured under one contract.
  • The Construction Works and Associated Services (Framework Agreement) – as procured under the Crown Commercial Service) stipulates that the works are allocated by LOT values (namely £0 - £3m, £3m - £10m, £10m - £30m, and £30m - £80m). The total value of all works if procured under one contract is likely to fall within the £30m - £80m category. This may present an issue with regards to direct appointment of one contractor undertaking all the works.
  • A main contractor may perceive a greater commercial risk in being appointed to design and construct on three separate site locations (including the associated disruption with obtaining labour, materials, and other site-specific location considerations) rather than being appointed under a single source location.
  • Regional constraints with the geographical spread of each project location.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Benefits of one contract for all three sites?

A
  • Contractor economies of scale transfer of knowledge and learning between projects.
  • Delivers value for money in cost saving through economies of scale
  • May attract a top tier contractor which will bring benefits in manging quality and delivery.
  • Procurement of all works can be co ordinated as one project and is likely to secure benefit with regard to contract administration and project protocol.
  • The potential for reduced contractor overheads and design fees as the works are procured more seamlessly.
  • Better communication between design team and construction team personnel.
  • Consistency through development of the project at each site and their commonalities and differences.
  • Likely to attract greater market interest and competition due to the value and capabilities of the suppliers on the Framework.
17
Q

What would you do in working with a different client, based on having experience with MOD / DIO?

A

I would apply the same methods of SH management and engagement based on how well it had been received, however am aware this may need to be adapted as the MOD have a hierarchical set up and often have a very clear brief which other clients wouldn’t so a different approach in the support and advice to the client would need to be different

18
Q

What is the Noise at work Act?

A

The Control of Noise at Work Regulations 2005 is a law in Great Britain that requires employers to reduce the risk to their employees’ health by controlling the noise they are exposed to whilst at work1. The regulations were established under the Health and Safety at Work etc. Act 1974 and implement European Council directive

19
Q

What is the H&S Act?

A

The Health and Safety at Work Act 1974 (HASAWA) is a UK law that defines the structure and authority for the regulation and enforcement of workplace health, safety and welfare. It applies to employers and employees, as well as casual workers, self-employed workers, clients, visitors, and the general public. It outlines the responsibilities of both the employer and employee in ensuring there is a safe working environment.

20
Q

On what of your three options presented would you use a PCSA?

A

Option 2 – 2 stage
Option 3 – possibly during the VE exercise

21
Q

Would a JCT D&B be suitable to use on this project?

A

Yes, although NEC looks towards a more collaborative approach and collaboration was key here and further supported following the Latham report calling on better collaboration, NEC has become the preferred option for govt projects.

22
Q

Would a JCT D&B be suitable to use on this project?

A

Yes, although NEC looks towards a more collaborative approach and collaboration was key here and further supported following the Latham report calling on better collaboration, NEC has become the preferred option for govt projects.

23
Q

Reasons for only receiving two EOI’s?

A

Resourcing other significant bids in the market
Covid & Brexit factors meaning other significant defence bids live as well as it being a contractors market

24
Q

Key activities you undertook in RIBA 3 as the lead PM making sure they were undertaken?

A

RIBA 2 - Architectural Concept approved by the client and aligned to the Project Brief
Prepare Architectural Concept incorporating Strategic Engineering requirements and aligned to Cost Plan, Project Strategies and Outline Specification Agree Project Brief Derogations Undertake Design Reviews with client and Project Stakeholders Prepare stage Design Programme

RIBA 3 - Architectural and engineering information Spatially Coordinated
Undertake Design Studies, Engineering Analysis and Cost Exercises to test Architectural Concept resulting in Spatially Coordinated design aligned to updated Cost Plan, Project Strategies and Outline Specification Initiate Change Control Procedures Prepare stage Design Programme

Spatial co-ordination
Building up technical design in line with the agreed programme
Planning (noting the difficulties with the planning consultant hence the late start, and long duration for pre-app response, but I am aware that on major new build projects planning activities would usually commence in RIBA 2.

25
Q

Did you advise on the X-clauses to be added into the NEC contract?

A

No, however I am aware from reading the commercial strategy the following would apply, and had we got to a point of contract it would have been advised to also include Option X5: Sectional Completion
 X1 Price adjustment for inflation – Hyperinflation was an external factor considered, and X1 allows for allow for price adjustment for inflation which would be more attractive for suppliers.
 X7 Delay damages - should completion of the works be subject to delay and the contractor failing to meet their contractual obligations
 X13 Performance Bond
 X20 Key Performance Indicators

26
Q

What were the drivers of the cost increase in the ROC?

A
  • Risk associated especially with the lack of structural information in the SLA block above the basement
  • Lack of intrusive surveys
  • Inflation driven by external market factors
  • They were aware they were a single bidder
27
Q

Dates within case study

A
  • RIBA 2 budget – October 2021
  • PTE refresh – March 2022
  • Market engagement March 2022 – end of May 2022
  • Initial ITT release date June, but a month late mid July
  • ROC September 2022
  • Original Tender Return 02nd September 2022, delayed by 2 months to 03rd November 2022
28
Q

Cost increases & dates

A
  • Approved budget – October 2021
  • PTE - March 2022
  • ROC – September 2022
  • Tender return – November 2022
29
Q

How would you include multiple sites within one contract?

A
  • X5 sectional completion
  • Payment would be based on works complete across all three sites each month
  • Programme specified data is detailed within the programme, and we had requested in the ITT information for one programme but he information repeated three times over for the multiple sites
  • Contract data part 2 – To give consideration to the geographical split and possible variation in labour costs for example, you would expect a cost variance between rates and thus an elongated contract data part 2
30
Q

How did you keep the team motivated in the situation of high costs and having outcomes which weren’t inline with the project objectives?

A

Refer back to the project brief and highlight that we still had a very keen and interested party, which despite cost would deliver a the technical and quality aspect of the project, maintain regular contact, maintain motivation by acting as a role model, listen to the team.

31
Q

Cost increases between GT’s ROC and final tender return?

A
  • Each work package cost inflated – not inline with market testing
  • Only one tender return – of which they would have known about
  • 3 projects had a lot of risk – contractor have priced this in their submission
  • Due to the combined size only had tier 1 contractors interested – they would sub out the works, so in essences you’re paying prelims + ohp ontop of prelims + OHp
  • Would have got more interest splitting the works into 3