Programming and Planning Flashcards
What is the Critical Path?
The longest route of linked activities within a programme.
What is a programme?
A tool used to identify activities, their phasing and sequencing towards an end date.
What can a programme be used for?
- Schedule of activities;
- Sequence of works;
- Key dates / milestones;
- Resource planner;
- Risk management aid;
- Cost management too
- Interdependencies
What is critical path analysis?
Critical path analysis is a technique that defines the sequence of activities that determine the programme duration. In doing so it reveals the total float and free float.
What is Float?
Float is the time that a task can be delayed without causing a delay to the subsequent tasks.
Explain to me what a drop line is?
Jagged or straight line moment in time to track progress on the programme.
Can you explain what acceleration is in a programme?
Bringing forward the completion date, encouraging an earlier completion, mechanisms under the contract to allow for acceleration can include out of hours works, additional labour, resequencing of works
Who does float belong to in a programme?
• JCT – No one owns it, it is taken by the first party who uses it
• NEC – Terminal float is owned by the contractor
• Free float is owned by the project, the first party to it gets it.
What should be considered when developing a programme?
- Determine project objectives
- Understand project constraints
- Identify tasks and estimate their durations
- Decide sequence of activities
- Identify and external constraints
- Identify resources required
What is a Gantt Chart?
This is a type of bar chart adapted to illustrate a project schedule. It should show the dependencies within the flow chart and highlights the critical path of activities in the project.
Gantt charts have two main components:
A horizontal axis – it is constructed to represent the total amount of time span in a period. This line is broken into increments to depict days, weeks or months.
A vertical axis – this represents all the tasks related to the project. For example foundations, superstructure etc.
What is float?
Float is the time that a task can be delayed without causing a delay to the subsequent tasks.
How do you determine if there are delays?
- Review the programme – use droplines (both jagged and straight)
- Physically review the works on site
- Speaking to sub-contractors on site to gain a deeper understanding of progress
- Close communication with contractor / clerk of works
- Issuing early warning notices by the contractor
- Review s-curve of the cashflow
- Risk management – identifies areas which could delay the project
Explain terminal float and who owns it?
Terminal float refers to a situation where a contractors planned date for completion is showing as earlier than the date to which they are obliged to deliver the works. Terminal float is specifically identified in the NEC (as opposed to other contract forms) as being “owned” by the Contractor.
What is the programmes role under NEC?
The Accepted Programme is a key project management tool in the NEC form and is crucial for achieving the NEC’s objectives. Broadly, it has two roles:
To ensure that all parties know what they have to do, and when; and
To provide a tool to enable the prompt and (hopefully) prospective assessment of compensation events and, specifically, the extensions of time claimed pursuant to them.
What is Time Risk Allowance?
TRA is a specific identified risk added into the programme. It needs to be identified and explained and can be shown as separate activities in the programme or integrated within the planned activity duration.
What are the reasons for rejecting a contractors programme under NEC?
- The Contractor’s plans are not practicable;
- It does not show the information required by the Contract;
- It does not represent the Contractor’s plans realistically; or
- It does not comply with the Scope.
What should be shown in the contractors programme updates?
Pursuant to clause 32.1, each revised programme must show:
- The actual progress it achieved on each operation and its effect upon the time of the remaining work;
- How the Contractor plans to deal with any delays to correct and notify Defects; and
- Any other changes which the Contractor proposes to make to the Accepted Programme.
Total float
The time by which an activity can be delayed or prolonged without affecting the project completion date.
Free float
The time by which an activity can be delayed or prolonged without affecting the timing of any of the succeeding activities.
Who does float belong to in a programme?
Who does float belong to in a programme?
* JCT – No one owns it, it is taken by the first party who uses it
* NEC – Terminal float is owned by the contractor
* Free float is owned by the project, the first party to it gets it.
Why would you allow for float in a programme?
It acts as a risk contingency for delay
Explain concurrent delay?
Concurrent delay is when two independent tasks are delayed at the same time with the potential to impact the critical path.
Under the NEC contract you should assess the effects of the two events in the order they occur. However, if your programme is managed well, the chances of concurrent delay occurring is very slim as the delays have to occur at the same time.
How would you go about putting together a programme?
In the first instance you consider things such as: project objectives, constraints, tasks and estimate their durations, sequencing of activities, resources required.
Once identified you establish your summaries, such as breaking the programme down into RIBA stages and or the methodology being followed for a RIBA stage and then input the tasks into a programming software and create your logic links.
What is a work breakdown structure?
A deliverable-oriented hierarchical breakdown of the work to be executed by the project team to accomplish the project objectives and create the required deliverables. It organises and defines the total scope of the project. Each descending level represents an increasingly detailed definition of the project work. The WBS is decomposed into work packages.