Programming and Planning Flashcards

1
Q

What is the Critical Path?

A

The longest route of linked activities within a programme.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is a programme?

A

A tool used to identify activities, their phasing and sequencing towards an end date.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What can a programme be used for?

A
  • Schedule of activities;
  • Sequence of works;
  • Key dates / milestones;
  • Resource planner;
  • Risk management aid;
  • Cost management too
  • Interdependencies
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is critical path analysis?

A

Critical path analysis is a technique that defines the sequence of activities that determine the programme duration. In doing so it reveals the total float and free float.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is Float?

A

Float is the time that a task can be delayed without causing a delay to the subsequent tasks.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Explain to me what a drop line is?

A

Jagged or straight line moment in time to track progress on the programme.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Can you explain what acceleration is in a programme?

A

Bringing forward the completion date, encouraging an earlier completion, mechanisms under the contract to allow for acceleration can include out of hours works, additional labour, resequencing of works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Who does float belong to in a programme?

A

• JCT – No one owns it, it is taken by the first party who uses it
• NEC – Terminal float is owned by the contractor
• Free float is owned by the project, the first party to it gets it.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What should be considered when developing a programme?

A
  • Determine project objectives
  • Understand project constraints
  • Identify tasks and estimate their durations
  • Decide sequence of activities
  • Identify and external constraints
  • Identify resources required
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is a Gantt Chart?

A

This is a type of bar chart adapted to illustrate a project schedule. It should show the dependencies within the flow chart and highlights the critical path of activities in the project.
Gantt charts have two main components:
A horizontal axis – it is constructed to represent the total amount of time span in a period. This line is broken into increments to depict days, weeks or months.
A vertical axis – this represents all the tasks related to the project. For example foundations, superstructure etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is float?

A

Float is the time that a task can be delayed without causing a delay to the subsequent tasks.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How do you determine if there are delays?

A
  • Review the programme – use droplines (both jagged and straight)
  • Physically review the works on site
  • Speaking to sub-contractors on site to gain a deeper understanding of progress
  • Close communication with contractor / clerk of works
  • Issuing early warning notices by the contractor
  • Review s-curve of the cashflow
  • Risk management – identifies areas which could delay the project
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Explain terminal float and who owns it?

A

Terminal float refers to a situation where a contractors planned date for completion is showing as earlier than the date to which they are obliged to deliver the works. Terminal float is specifically identified in the NEC (as opposed to other contract forms) as being “owned” by the Contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the programmes role under NEC?

A

The Accepted Programme is a key project management tool in the NEC form and is crucial for achieving the NEC’s objectives. Broadly, it has two roles:
To ensure that all parties know what they have to do, and when; and
To provide a tool to enable the prompt and (hopefully) prospective assessment of compensation events and, specifically, the extensions of time claimed pursuant to them.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is Time Risk Allowance?

A

TRA is a specific identified risk added into the programme. It needs to be identified and explained and can be shown as separate activities in the programme or integrated within the planned activity duration.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are the reasons for rejecting a contractors programme under NEC?

A
  1. The Contractor’s plans are not practicable;
  2. It does not show the information required by the Contract;
  3. It does not represent the Contractor’s plans realistically; or
  4. It does not comply with the Scope.
17
Q

What should be shown in the contractors programme updates?

A

Pursuant to clause 32.1, each revised programme must show:

  • The actual progress it achieved on each operation and its effect upon the time of the remaining work;
  • How the Contractor plans to deal with any delays to correct and notify Defects; and
  • Any other changes which the Contractor proposes to make to the Accepted Programme.
18
Q

Total float

A

The time by which an activity can be delayed or prolonged without affecting the project completion date.

19
Q

Free float

A

The time by which an activity can be delayed or prolonged without affecting the timing of any of the succeeding activities.

20
Q

Who does float belong to in a programme?

A

Who does float belong to in a programme?
* JCT – No one owns it, it is taken by the first party who uses it
* NEC – Terminal float is owned by the contractor
* Free float is owned by the project, the first party to it gets it.

21
Q

Why would you allow for float in a programme?

A

It acts as a risk contingency for delay

22
Q

Explain concurrent delay?

A

Concurrent delay is when two independent tasks are delayed at the same time with the potential to impact the critical path.

Under the NEC contract you should assess the effects of the two events in the order they occur. However, if your programme is managed well, the chances of concurrent delay occurring is very slim as the delays have to occur at the same time.

23
Q

How would you go about putting together a programme?

A

In the first instance you consider things such as: project objectives, constraints, tasks and estimate their durations, sequencing of activities, resources required.
Once identified you establish your summaries, such as breaking the programme down into RIBA stages and or the methodology being followed for a RIBA stage and then input the tasks into a programming software and create your logic links.

24
Q

What is a work breakdown structure?

A

A deliverable-oriented hierarchical breakdown of the work to be executed by the project team to accomplish the project objectives and create the required deliverables. It organises and defines the total scope of the project. Each descending level represents an increasingly detailed definition of the project work. The WBS is decomposed into work packages.

25
Q

Can you list some programming software and their benefits to using them?

A

Microsoft project, Asta, Prima Vera 6
The software’s are all very similar, however MSP is very user friendly and in a format which is easily understood and user friendly, Prima Vera allows you to have an unlimited baseline.

26
Q

Can you list some activity relationships in a programme?

A

Finish to finish (FF),
Finish to start (FS),
Start to start (SS), and
Start to finish (SF).

The first part of these terms indicates the status the predecessor activity must obtain before the successor activity can have the status referred to in the second part. In a finish to start dependency, for instance, the predecessor must have finished for the successor to start.

27
Q

What is crashing in terms of a programme?

A

Also known as project time compression and crashing the project schedule—is a project management technique that involves adding more resources to accelerate the project timeline.

28
Q

Explain the difference between programming and planning?

A

Programming is the display on a programme of activities to be undertaken and when.

Planning is understanding how, when and what will be done. An analytical activity carried out to achieve objectives and then to examine courses of action that could be taken.

29
Q

How would you develop the tender programme?

A
  • Consider client requirements and key dates
  • Benchmark from similar projects and or experience
  • Pressure test the market
30
Q

Straight dropline

A

Comparing how far the activities have moved against the original plan, known as the baseline
The straight-line method allows the project to make data-driven decisions to get back on track as it can determine how behind / ahead the project is.

can determine that the project is 3 weeks behind. Or, specifically, that the project is likely to finish 3 weeks late if the project runs without any further delays. You can see this by comparing how far the activities have moved against the original plan, known as the baseline

31
Q

Jagged drop line

A

shows if tasks are behind, on time or ahead of the baseline programme.

It is easy to see which activities are on programme or behind.

Doesn’t quantify the delay.

Does not forecast when future activities will start based on where the project is now.
It does not forecast when the project will finish.
Cannot determine the critical path, making prioritising difficult or impossible.

32
Q
  1. What is Earned value management?
A

Earned value management is a project management technique for measuring project performance and progress. It has the ability to combine measurements of the project management triangle: scope, time, and costs.
earned value helps us manage a project by:
* providing data to enable objective measurement of project status;
* providing a basis for estimating final cost;
* predicting when the project will be complete;
* supporting the effective management of resources;
* providing a means of managing and controlling change.
Earned value provides information which enables effective decision making by knowing:
* what has been achieved of the plan;
* what it has cost to achieve the planned work;
* if the work achieved is costing more or less than was planned;
* if the project is ahead of or behind the planned schedule.

33
Q
  1. Programme lead & lag
A

Lead - successor activity is started before the predecessor activity has finished.
Lag – To schedule a delayed start on a logic link successor activity

34
Q

Explain how you would establish the critical path on a programme?

A

I would identify the tasks and durations, inputting them into a programming software most likely MSP and link the activities successors and predecessors. Through linking the tasks, float and the critical path will be identified and highlighted in a different colour on the Gant chart provided by the programming software.

35
Q

Describe how you established a list of activities on a project programme on one of your projects?

A

On the Wellington project I identified tasks through benchmarking against similar projects on the commission, as well as harnessing my knowledge from previous projects of the tasks required for the delivery of the certain RIBA stages, as well as my own knowledge of client specific task’s and durations, for example governance procedures. Finally if further input is required I would utilise my colleague’s knowledge.

36
Q

If an activity is delayed, but not on the critical path would this impact the completion date?

A

No the item would have a level of free float to use before becoming a critical path item, at which point it would delay the completion date.

37
Q

If an activity is delayed, but if delayed doesn’t impact the end date of the programme what type of float would this be?

A

Free float.