Victoria is a team member on a project involving new video game software. There are a large number of
stakeholders on this project, and she has been named the team member responsible for distributing project
communications. In order to do this in the most effective and efficient manner, Victoria needs a clear
comprehension of which of the following?
a. Stakeholder register
b. Monte Carlo simulation
c. Sender/receiver models
d. Fast-tracking
C
The best answer choice is C. Because communications typically involve senders and receivers, each with individual responsibilities, in order to be an effective communicator, one must have a clear understanding of sender/receiver models.
Betty is managing a project for a new digital sensor for their full frame camera. There are a lot of highly technical issues with this product, and Betty realizes that good communication is key to project success. In order to ensure effective communication among the team members assigned to this project, which of the
following should Betty do?
a. Get the sponsor’s approval on all communication
b. Make sure all stakeholders receive copies of the information
c. Provide the right information in the right format at the right time
d. Rewrite the communications plan
C
The best answer choice is C. Betty needs to make certain that the right information is distributed in the right format at the right time.
In a traditional communications model, the sender encodes the message and sends it to the receiver. Which of the following is the receiver responsible for?
a. Decoding the message
b. The message content
c. Determining the communication channel
d. Timely delivery
A
The best answer choice is A because from the choices listed, only decoding the message is the responsibility of the receiver.
The project steering committee wishes to see an ad hoc report that shows the portfolio of projects displayed with variance reports, which provides an easy snap shot of project schedules. This is part of which process?
a. Monitor Stakeholder Engagement
b. Monitor Communications
c. Manage Stakeholder Engagement
d. Control Resources
B
Making sure communications meet the needs of the stakeholders is part of Monitor Communications.
Juanita is developing her communications management plan. Which of the following inputs would be necessary to determine the correct communication recipients?
a. Communication methods
b. Communication models
c. Stakeholder register
d. Meetings
C
The best answer choice is C because it is the only choice that is an input to the Plan Communications Management process.
Including the project manager, there are nine members making up your project team. How many communication channels are there in this project team?
a. 9
b. 18
c. 36
d. 81
C
The best answer choice is C. The equation used to determine communication channels is [n × (n – 1)] /
2. In this case, 9 × 8 / 2.
There are pros and cons to using email communications. What is the primary disadvantage of email when compared to a face-to-face conversation?
a. Poor grammar
b. Not being able to see body language
c. Informality
d. None of the above
B
Visual communication is a strong component of human dialog. The primary communication disadvantage of email conversations, as compared to in-person conversations, is not being able to see body language.
Elmer is a project manager for a large communications firm involved in creating a state-of-the-art
communications system for spacecraft that will employ a gimbal-supported video system to capture not only the audio portion of the communication but a video record as well as RAW digital images. As the manager of the project, Elmer must make relevant information on the project’s progress available to all stakeholders during the project’s life cycle. Effective distribution of this information is dependent on a number of techniques including sender-receiver models, distribution channel, message frequency, and writing style. In this context, which of the following would contain a feedback loop?
a. Writing style
b. Sender-receiver model
c. Distribution channel
d. Message frequency
B
The best answer choice is B. Of the choices given, only the sender-receiver model contains a feedback loop.
The stakeholder register is an input to which process in the Project Communications Management Knowledge Area?
a. Manage communications
b. Control stakeholder engagement
c. Plan communications management
d. Control communications
C
The best answer choice is C because it is the only process listed that has the stakeholder register as an
input.
An email reminder about an upcoming project status meeting is considered:
a. Formal and written
b. Formal and verbal
c. Informal and verbal
d. Informal and written
D
Written communication may also be informal, such as a brief note to a team member, an inquiry via email, or a follow-up reminder that a deliverable is due soon.
You’ve been asked to give a short presentation to update the client on the status of a project. What type of communication is required?
a. Formal, written
b. Informal, written
c. Formal, verbal
d. Informal, verbal
C
The briefing is verbal, and the client, along with the rest of the project steering committee, necessitates formal communication.
Valerie has just completed her project schedule. Which of the following choices provides the proper way to distribute it?
a. She should distribute it only to the project team members
b. She should have the project sponsor distribute it as he wishes
c. She should have the project manager distribute it as desired
d. She should distribute it according to the communications management plan
D
The best answer choice is D because the communications management plan will specify to whom the schedule needs to be distributed.
Posting a written project progress report onto a project website for people to access as needed is an example of ________ communication.
a. Pull
b. Push
c. Interactive
d. Written
A
Pull communication requires recipients to access the communication content at their own discretion.
In the Control Communications process, which of the following is not considered an input?
a. Work performance information
b. Project management plan
c. Work performance data
d. Issue log
A
The best answer choice is A because work performance information is an output of this process.
Stuart is an aspiring project manager. He has been tasked with determining the communication methods that will be used to convey project information. Which of the following would provide this information?
a. Sender/receiver model
b. E-mail directory
c. Stakeholder register
d. Communications Management plan
D
The best answer choice is D. Stuart will need to refer to the Communications Management plan to find the methods used to convey project information.