PROJECT RESOURCE MANAGEMENT Flashcards
In planning your project, you decide to create a matrix showing the intersection of the tasks that have been defined and the resources assigned to those tasks. The tool used to best show these assignments is which of the following?
a. A Responsibility Assignment Matrix
b. A resource histogram
c. A Resource Breakdown Structure
d. A resource graph
A
The Responsibility Assignment Matrix shows the intersection of the WBS and the resources assigned to
the tasks of the project.
During the planning of a project, the project manager has determined the necessary resources for a project.
Although determining the necessary resources is a planning process, Acquire Resources is what type of
process?
a. An initiating process
b. A planning process as well
c. An executing process
d. A monitoring and closing process
C
Although you determine what resources are necessary in planning, the actual acquisition of those
resources is considered an executing process whereby you obtain team members, facilities, equipment, materials, supplies, and other resources necessary to complete project work.
Estimate Activity Resources is the process of estimating team resources and the type and quantities of materials, equipment, and supplies necessary to perform project work. With what other process is the Estimate Activity Resources process most closely aligned?
a. Develop Project Charter
b. Define Scope
c. Estimate Costs
d. Plan scope management
C
Estimating activity resources is very closely linked to the Estimate Costs process. The cost of resources
can drive how you perform the project.
The processes used to identify, acquire, and manage the resources needed for the successful completion of the project can be found in which of the following knowledge areas?
a. Project Integration Management
b. Project Communications Management
c. Project Scope Management
d. Project Resource Management
D
Project Resource Management includes the processes that identify, acquire, and manage the resources needed for the project.
Which of the following documents would the project manager use to determine training needs, safety
concerns, and procedures for releasing team members at the end of the project?
a. Resource requirements
b. Resource calendars
c. Staffing management plan
d. Resource breakdown schedule
C
The best answer choice is C because it contains the information the project manager needs as
described in the question.
The RACI chart is a common type of responsibility assignment matrix that defines the involvement of
stakeholders in project activities. What does RACI stand for?
a. Responsible, Approval, Concerned, Inform
b. Responsible, Accountable, Consult, Input
c. Responsible, Approval, Consult, Inform
d. Responsible, Accountable, Consult, Inform
D
An RACI chart is a type of responsibility assignment matrix where RACI stands for Responsible,
Accountable, Consult, and Inform.
To calculate the cost of a resource usage variance multiply the _________ times the difference between the actual quantity less the estimated quantity.
a. Estimated price
b. Expected usage
c. Price variance
d. Cost variance
A
The calculation for usage variance is (Actual quantity − Estimated quantity) × Estimated price.
Which of the following is not a component of the human resource management plan?
a. Roles and responsibilities
b. Project organization charts
c. Resource requirements
d. Staffing management plan
C
The best answer is C because that is not a component of the human resource management plan.
The process of improving competencies, team member interaction, and the overall team environment to enhance project performance is the Develop Team process. Tools and techniques used for this process include all of the following EXCEPT:
a. Project chartering
b. Influencing
c. Training
d. Individual and team assessments
A
Develop Project Charter is an initiating process, not a planning process. It is developed well in advance
of developing project team members.
A new project team is meeting to plan out their approach to an assigned project. Immediately, however, there are significant disagreements on how best to proceed. Which stage of team development are they likely in?
a. Forming
b. Storming
c. Norming
d. Performing
B
Since they are experiencing conflict as they figure out how to work together, the team is in the storming stage.
You wish to show a hierarchical representation of resources by category and type. Which of the following would be the best tool for you to use?
a. A Resource Breakdown Structure
b. A resource calendar
c. A project resource diagram
d. A Resource Traceability Matrix
A
The Resource Breakdown Structure identifies categories of resources and then decomposes them into types, skill levels, or other subcategories as appropriate.
You are a team member on a new project team consisting of highly qualified security experts and have been tasked with assigning the various work packages on the WBS. However, your project manager has changed some of your assignments, and you have distributed the new assignments to the team. Several team members have come to you to complain that the more difficult tasks have been assigned to the women on the team, and the men have received the easier work packages. At the same time, some of the male team members are complaining that they would like some of the more daunting tasks that could provide a learning experience and enhance their resumes. When you bring this up with your project manager, he simply tells you that he is managing the team and you will leave the assignments the way he determined. Which of the following describes the conflict resolution method the project manager is using?
a. Forcing
b. Compromising
c. Accommodating
d. Collaborating
A
The best answer choice is A because the project manager is pushing his personal viewpoint on others
by using the power of his position.
Which process is described as “ensuring that the physical resources assigned and allocated to the project are available as planned, as well as monitoring the planned versus actual utilization of resources and performing corrective action as necessary”?
a. Manage team process
b. Control resources
c. Estimate activity resources
d. Plan resource management
B
Control resources is defined as “ensuring that the physical resources assigned and allocated to the
project are available as planned, as well as monitoring the planned versus actual utilization of resources and
performing corrective action as necessary”.
Chuck is managing a virtual project team. He is trying to determine the most important factors for success.
Which of the following should Chuck put at the top of his list?
a. Team building
b. Resource breakdown structure
c. Communication
d. Risk register
C
The best answer choice is C. Communication is one of the most important factors for success in managing a virtual team.
When managing a virtual project team, which of the following choices is more likely to lead to success?
a. More frequent communication with team members
b. Using e-mail rather than phone calls
c. Utilizing contractors more often
d. Assigning bilingual assistants
A
The best answer choice is A because frequent communication is critical with virtual teams.