Programming & Planning Flashcards

1
Q

What are the benefits of the critical path method?

A

Idenifitcation of the critical items in a project
Reduction in delays
Improve organisation
Optimise efficiency
Visualise dependencies
Float calculation (how much a task can be delayed without impacting the project)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the critical path on a construction programme?

A
  • The critical path is the longest sequence of activities from project start to finish that must be completed to ensure the project is finished by a certain time.
  • Activities on the critical path are known as critical activities because if they are delayed the whole project will be delayed.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is concurrent delay?

A
  • Where one or more events occur at the same time that is caused by different parties involved in a project.
  • These events will typically occur independently of each other
    Both events have an effect on the completion date of the project.
    -City Inn v Shepherd
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How would you compile a programme for a new project?

A
  • I would first understand the purpose of the programme and the level of detail.
  • I would refer to the RIBA plan of works in relation to each stage
  • All activities would be identified using previous experience including project deliverable, key mileston and contractual requirements.
  • I would request assistance from the design consultants to feed in their various elements.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

If a project is running behind programme what methods would you consider adopting?

A

I would review if Acceleration is an option if it was agreed on pre-contract and look at ways to improve the programme such as weekend working hours or increase labourers.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How would you assess a concurrent delay?

A
You must determine the root
cause, true concurrent delay is
actually very rare.
Once you determine the root
cause, you should really discard
any other delays.
Use the Malmaison approach.
This is where if it is considered
that one of the delays is the clients
risks, then the contractor should
be entitled to a Extension of Time
without loss and expense.
o It will have to claim for loss and
expense separately.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is Free Float?

A

The amount of time an activity
can be delayed, before it impacts
on the start date of another
activity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is Total Float?

A

The amount of time an activity
can be delayed, before it impacts
on the overall completion date.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is Float?

A

The amount of time an activity
can be delayed, before it impacts
on the completion of the works.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is Critical Path Analysis?

A

A way of analysing the
programme, to see if the critical
path duration can be shortened or
activities on it altered.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the advantages of a

Gantt chart?

A
  • Suitable for smaller projects.
  • It is suitable for construction as it offers a high level of detail.
  • To detailed for cost planning and estimates.
  • It shows the times to scale.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is a Gantt chart?

A
A way of displaying a
programme, through a
combination of bars, each relating
to an activity and having a
specified duration.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is acceleration?

A

Whereby the completion dated
is brought forward, requiring the
works to be completed quicker.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What’s required undertaking a delay analysis?

A
  • Contract programme
  • An As-built Programme
  • The Use if Critical Path Analysis
  • Records of site visit or photograph of progress
How well did you know this?
1
Not at all
2
3
4
5
Perfectly