Contract Practice Flashcards
What is concurrent delay?
- Where one or more events occur at the same time that is caused by different parties involved in a project.
- These events will typically occur independently of each other
Both events have an effect on the completion date of the project.
-City Inn v Shepherd
Can you provide more information on the JCT design and build contract for 2011?
They are used by all types of client, create a single point of responsible for the design and construction with the contractor • Can be used on projects of all sizes • Client must produce the Employers Requirements • Has a sub-contract derivative broken into two parts: JCT DB11 Sub-contract Agreement, JCT DB11 Subcontract Conditions • All derivatives have a Yellow and pink cover
What are the main contract suites?
• JCT (Joint Contract Tribunal) • NEC (New Engineering Contract) • FIDIC (International Federation of Consulting Engineer) • ICE (Institution of Civil Engineers)
What is an extension of time claim?
• An adjustment to the completion date,
relieving the contractor’s liability to pay
LADS for the period of additional time
granted.
What are the other forms of contracts within the JCT suite?
• SBC 2011/2016 • Intermediate building contract 2011/2016 Minor works Building contract 2011/2016 • Major Projects building contract 2011/2016 • Design and build contract 2011/2016 • Management Building contract 2011/2016 • Construction management contract 2011/2016 • Prime cost building contract 2011/2016
What is the contract?
A legally binding agreement (between
two parties) to provide goods and
services within a specified timeframe.
What are the advantages of using a standard form of contract?
• They are cheaper than getting a bespoke contract is drawn up • Offer a level of familiarity between the parties • Tried and tested contracts in court, Therefore, you should be able to predict the outcome in the courts.
What is a compensation event?
Events that occur during the course of
the works that cause the completion
date to be changed or additional cost
to the contractor as a result of the client
How would draft an Novation agreement?
Any Novation agreement has to be contractually and legally drafted and that’s outside of my scope and professional
What are the key legislative documents involved in your project?
Town and country planning act 1990 Health & Safety Act 1974 NHBC standards CDM Regulations 2015 Lifetime Homes BREEAM Building regulations
What do you know about the Fire Safety Act?
The Bill has been designed to “ensure that people feel safe in their homes and a tragedy like the Grenfell Tower fire will never happen again.”
The changes that come with it mostly apply to multi-occupied, residential buildings – any premises that comprise anything other than a single dwelling. This means that a house converted into two flats needs a risk assessment and adequate fire safety measures as well as a high-rise building with hundreds of apartments.
the Fire Safety Bill was introduced by the Home Office and in April 2021 received a Royal Accent, setting it in on the path to becoming law.
Amending the existing Fire Safety Order 2005, the First Safety Act 2021 (as it is now known) clarifies several points, including the responsibilities of duty-holders and/or building owners, known as ‘Responsible Persons’.
Can you give me an example where you have to advise the Client on contract matters? (Level 3)
On Dollis Phase 2, a regen project at post-completion, a resident was due to sell their flat as a leasehold.
The lender wants ESW1,
The contractor completed a survey and identified ACM.
My client wanted to see if there were any contractual mechanisms in place to withhold or delay the reversion of the entire leasehold interest from the building being transferred.
I advised my client that there is a clause noted in the development agreement that states that once the final unit has been sold, my client or purchaser much transfer the leasehold transfer.
and stated they were in breach of the contract if they refuse or do not transfer the leasehold interest.
I explored alternate routes to recover remedial costs via the collateral warrant route, I sought legal advice and presented this to my client.
What is practical completion?
There is no set in stone definition of PC
But I would considered PC is when a building is watertight and ready to move in
What conditions needs to be met for a contract to be in place?
Offer by one party (Tender)
Acceptance by another party (Tender return)
Consideration ( Price of the promise)
Intention to form a contract (lending money to a friend)
Legality of contract
Capacity to make an agreement
Consent (must not be forced)
What is a performance bond?
Insures the client should a contractor fail to fulfil its obligations to perform according to the contractual terms.
Gives the Employer/client assurance the contractor completes the project.
If a contractor becomes insolvent, the bond provides compensation guaranteed by a third party up to the amount of the PB.
Bonds are typically set at 10% of the contract sum
Most employers will request one from the contractor, who will, in turn, obtain it from a bank/ insurance company.
Commonly used alternatives to PCG’s.
What is a Retention Bond?
Alternative to retention (cash), protecting the employer after the project is finished that the contractor will carry out the necessary work