Programming and Planning Flashcards
1
Q
What is critical path analysis?
A
- It is the identification of the sequence of curtail activities within the programme from start to finish
- Identifies other tasks that are required to complete the project but will not delay the programme if those activities are delayed
2
Q
What is the critical path?
A
- It is the longest bath from start to finish within the programme
- It indicates the minimum time necessary to complete a programme
3
Q
What is total folat?
A
- It is the amount that an activity can move without affecting the critical path
- Shared contractually by both parties
4
Q
What is free float?
A
- It is the amount that an activity can move by without affecting a non critical path item
- Must be less than or equal to total float
- Shared contractually by both parties
5
Q
What is time risk allowance?
A
- A proportion of an activity duration that has been assessed by the contractor as risk
- For example poor ground for excavations
- Requirement for it to be shown on NEC programmes
- Owned by the Contractor
6
Q
What is terminal float?
A
- It is the duration of time between the planned completion date and the contract completion date
- Owned by the Contractor
7
Q
What are the reasons for rejection of programme under NEC?
A
- Contractors plans shown are not practicable.
- It does not show the information which the contract required.
- It does not represent the Contractors plans realistically.
- It does not comply with the Works Information.
8
Q
How would you advise a client on assessing a EOT if there is no accepted programme?
A
- The only practical solution would be to agree the CL31 programme before assessing the EoT
- Without an accepted programme, there is no way to impact the last accepted programme
- Therefore my advise to the Client would be to focus on agreeing the CL31 programme and then using that as the baseline to impact any CE’s
9
Q
What has changed with programme management under NEC4?
A
Notifications can now be issued for the non acceptance of programmes, leading to their acceptance if there is non reply to the notification.