Contract administration Flashcards

1
Q

What are the key differences between NEC and JCT?

A
  • JCT is traditionally used only for building projects, whereas the NEC is used for both building and civil engineering projects
  • Th NEC has a variety of bespoke contract options where the JCT has a standard set of clauses
  • JCT deals with time and cost separately, under variations and loss and expense claims
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the role of the Project Manager under the NEC?

A

They are the names person in Contract Data Pt1 who will administer the contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the role of the Supervisor under the NEC?

A

They are solely responsible for the checking of compliance in line with the works information

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the role of the Subcontractor under the NEC?

A

They are the person or organisation that has a contract with the Main Contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the role of the Consultant under the NEC?

A

They are the person or organisation that delivers work under a Professional Services Contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the defined response times under the NEC?

A
  • 1 week for a response to a CE under a ECC, 2 weeks under a ESC
  • On OOC the Contractors period of reply is 3 weeks to a CE and 5 weeks to a quotation
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Explain your knowledge of the Housing Grants, Construction and Regeneration Act 1996?

A
  • Suppliers have the right to be paid in interim, periodic or stage payments
  • Suppliers have the right to be informed of the amount due or withheld
  • Suppliers have the right to suspend performance for non-payment
  • Suppliers have the right to adjudication
  • Disallows pay when paid clauses
  • A payment must be issued within 5 days of the payment due date
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What does the Construction Act state if there are no payments provisions in the contract?

A
  • If the contract doesn’t specify a period then the payment due date will be every 28 days
  • The payment notice must be issued no later than 5 days after the payment due date
  • The Final Date for Payment is then 17 days after the payment due date
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

When might a notional final account statement be issued on a project?

A
  • The contractor or employer going into liquidation or
    administration
  • The contract being terminated due to performance or
    other reasons in accordance with the contract by the
    employer
  • The contract being terminated by the contractor.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is a reason for the Contractor to terminate contract?

A
  • If it has not received payment within 13 weeks
  • If work is suspended for more than 13 weeks following a project manager’s instruction, either party may terminate
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is Prevention under NEC?

A
  • Prevention (Clause 19) is the ‘Force Majeure’ clause
  • It states if a Force Majeure event happens, the Employer is to give an instruction defining how it should be dealt with
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is Force Majeure?

A
  • An exceptional, unforeseen event or circumstance that are beyond the reasonable control of a party to a contract and which prevent or impede performance of their obligations under the contract