Procurement and Tendering Flashcards

1
Q

What is the benefit of partnering?

A
  • The potential for conflict is reduced
  • Communication is improved
  • Improved client satisfaction
  • A team environment is formed that encourages innovation
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is a framework agreement?

A
  • It is a type of contract that is commonly used as a multi-supplier agreement, establishing a long term relationship
  • It is an efficient way to work, without having to go through the tender process each time
  • Framework tenders are usually a mix of quality and price factors
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is partnering?

A
  • It is a long term approach of structuring business relationships
  • It involves two or more organisations working together to achieve specific mutual objectives
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are alliances?

A
  • An agreement providing that the parties will act in a certain way to achieve a common goal
  • In doing so the parties will share the success or failure of the project
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

When is traditional procurement appropriate?

A
  • When the Employer has had the design prepared
  • The Employer wishes to retain control over the design
  • If cost certainty is important at the start of the project
  • If the shortest overall programme is not a priority
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

When is design & build procurement appropriate?

A
  • When there is a need to make an early start on site, as there can be an overlap between design and construction
  • Where the client wishes to minimise risk
  • For technically complex projects requiring the Contractors experience
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the different procurement routes?

A
  • Traditional contracting: Design is completed by the clients design team before competitive tenders are invited and a main contractor appointed
  • Design & build: Where the Contractor is responsible for design and construction of the works in line with the employers requirements
  • Management Contracting: A management contractor is employed to contribute their expertise to the design and manage construction
  • Construction management: The Employer places a direct contract with each of the trade contractors and utilises the expertise of a construction manager who acts as a consultant to coordinate the contractors
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is two-stage tendering?

A
  • Where the client seeks to appoint the Contractor based on an outline scope of work that is not fully defined
  • It’s used when it is useful to obtain the Contractors buildability experience
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is single stage tendering?

A

It is a structured process of receiving competitive tenders from a number of pre-selected capable contractors
Contractors are pre-selected based on:
- Financial standing
- Qualifications
- Previous track record
- Capacity and resources
- size of work previously undertaken

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is negotiated tendering?

A
  • Where the client has an existing preference for appointing a particular firm and only negotiates with one contractor
  • Used when the contractor has carried out work successfully for the client and has an existing relationship
  • Schedule of rates from previous projects may be used as a basis of agreeing a price
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are some pro’s and con’s of two stage tendering?

A

Advantages:
- Early involvement of the contractor
- Encouragement of collaborative working
- Potential for an earlier start of site
Disadvantages:
- Cost certainty may not be achieved before construction starts
- Contractor could take advantage of the second stage of negotiation
- Potential for parties to not agree with a risk of retendering

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

When is Management Contracting appropriate?

A
  • Where the client does not prioritise cost certainty before commencement
  • The client wants early commencement
  • For large complex projects
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

When is Construction Management procurement appropriate?

A
  • On large complex jobs where the Construction Managers upfront buildability knowledge can be utilised
  • Where an early start on site is key
  • Where price certainty is not considered key
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

In your report you detailed different procurement methods. What are the different types of tendering methods available in construction?

A
  • Single-stage tendering
  • Two-stage tendering
  • Negotiated tendering
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

On the Old Oak Common project, take me through how you prepared a tender recommendation report for the appointment of the concrete subcontractor

A
  • I imported the price stack ups I had completed as part of the tender evaluation into the TRR
  • I added a written analysis which explained the differences in price and how one of them was clearly the most competitive
  • I added a section which explained how the proposed Subcontractor had a good understanding of the works
  • I liaised with the Project Manager who added his experience using the proposed Subcontractor on a similar project
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What checks are undertaken when subletting packages?

A

As part of the procurement process I undertake:
- Financial checks
- Health and safety checks
- Quality checks
- Commercial checks