Construction Technology Flashcards
Name some advantages and disadvantages of precast concrete
- It offers high strength as it is cast in a controlled environment with ideal conditions
- Less time to install as it is ready upon delivery
- Requires transportation and has to be craned into position which may be difficult on some sites
Name some advantages and disadvantages of insitu concrete
- It can be cast in any form so provides more flexibility to designers
- Longer to install, as it requires the installation of formwork and rebar prior to pouring
- It can be used for areas where transportation is difficult
What are the RIBA stages of work?
0 - Strategic Detention
1- Preparation and briefing
2 - Concept design
3 - Spatial coordination
4 - Technical design
5 - Manufacturing and construction
6 - Handover
7 - Use
What are the GRIP stages?
1 - Output definition
2 - Feasibility
3 - Option Selection
4 - Single Option Development
5 - Detailed Design
6 - Construction test and commission
7 - Scheme handback
8 - Project Close out
What takes place in RIBA stage 0?
- Defines the the business case and client requirements
- Project risks, project budget and site surveys
What takes place in RIBA stage 1?
- Guidance on project outcomes
- Clients requirements are considered in more detail
- Feasibility studies are undertaken and project budget agreed
What takes place in RIBA stage 2?
- Sets the architectural concept for the project
- Preparation of site information, project brief, spatial requirements
What takes place in RIBA stage 3?
- Architectural and engineering info are spatially coordinated
- Design studies and engineering analysis are undertaken and project cost plan updated
What takes place in RIBA stage 4?
- All design information required to manufacture and construct is completed
- Stage 4 will often overlap with stage 5
What takes place in RIBA stage 5?
- Manufacturing, construction and commissioning are completed
- There is no design work other than responding to queries
What takes place in RIBA stage 6?
- Building handed over, after care initiated and building contract concluded
- Rectifying defects
What takes place in RIBA stage 7?
- Building used operated and maintained effectively
- Stage 7 starts concurrently with stage 6 and lasts the life of the building
What are the benefits of BIM?
- Increased collaboration and coordination: collaboration is done in real time
- Reduced construction time and cost: Detailed estimating and clash detection can be achieved
- Improved quality and safety: Allows visualisations and simulations
- Enhanced sustainability: Allows evaluation of building components
Name some different types of piles
- Sheet piles: can be used to form basement walls or act as a retaining wall
- Secant piles: Interlocking piles poured into the ground can provide a waterproof structure
- Bored piles : An auger is used to excavate the soil and concrete is then poured in
- Pre-cast piles: Piles are hammered into the ground
- CFA Piles: Continuous flight auger, are drilled into the ground and concreted in one continuous operation
What is a CAT3 check?
- Highest level of check required for complex designs
- An independent organisation must be used to check the design