Programming Flashcards

1
Q

How have I advised on the principals of executive programme control of projects

A

I developed a tool on my studies and investigations projects where the consultants would update their programmes in the tool. This had version history and live change logs to see what and who had changed.

This was an area that programme leadership also had access to, and were able to view the progress of the projects at any time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How have I applied planning techniques

A

On my Fareham Consolidation scheme, I noticed that the programme that I took over did not have any logic. I advised the client that in order to accurately determine critical path, there needs to be links.

I amended the rpogramme and demonstrated how, by using critical path analysis, I could assess the health of the programme better.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Have I produced an executive programme

A

Many times. On my Ventnor Water Supply Works project, I produced a programme of the activities. My process was:
- Identify key milestones under the clients governance structure
- filled in the project-specific tasks
- filled in the relationships, float etc
- conducted a workshop to verify durations and logic

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Have I provided advice on progress against programme

A

For my Large Scale mains Replacement project, I conducted weekly sessions with the contractor to be updated on programme. I compared this to the activity schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Establish project objectives

A

On all my projects that I come into at Stage 1, I conduct a workshop to identify a statement of need and project objectives. These objectives are then developed into key activities and milestones which are put on a programme with dates to achieve.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Have I provided advice on corrected measures to accelerate progress

A

Level 34 refurbishment - I led a session with multiple trade contractors to identify opportunities to improve the programme, as when I took over the programme was in delay.

The solution was to provide payment for additional resource. Other options would have been to reduce scope in certain areas (work that could be done once the space was operational) or do some work during the day.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Risks with overlapping IT/Furniture moves on L10

A

CDM: As the space would be a CDM site, the relevant teams had to fill in RAMS further in advance than usual.
Incomplete activities: if the construction programme was lagging behind, then there would be issues.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Risks associated with continuing with design activities for Brede

A

Not really any risks for my client - all this did was accelerate the starting point for detailed design (and start on site). There was no additional cost to the client.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Structure workshop for Contractor’s programme

A

I made the right parties were in the room. I did this by reaching out to various department leads.

I then pulled the contractor’s programme onto a screen and went through each activitiy. I let the wider team discuss durations and activity sequence. I noted down any observations/actions to go into my response to the Contractor.

Additionally, looking through the programme I typically try to identify risks alongside the team.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How do I control the programme on my projects

A

Under the NEC, contractor has to submit a programme each month for acceptance. I also run weekly meetings to review progress and a lookahead.

I have a baselined copy of the programme that I compare against as well.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

types of float

A

Free float: the amount of time an activity can be delayed by before it impacts any following activities
Terminal float: time in between planned completion and contract completion
Total Float: the amount of time an activity can be delayed by before it impacts the planned completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Tell me about a time you’ve used Critical Path on a project

A

On every project I do, I ensure the critical path (longest sequence of activities) is highlighted on a programme. This allows me to identify which activities, should they be delayed, would impact completion.

On my Fareham Consolodation project, when developing the programme I identified the critical path. This was used in decisions making and resource prioritisation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How do you decide what to include in high level programmes

A

Start and end dates, key milestones (SoS, stage gate sign off), expected activities for a RIBA stage (stage 2 = concept design), governance requirements.

On my Ventnor project, I identified the regulatory end date and used the day i was creating as the start date. I then plotted the relevant governance milestones and activities as a HL programme

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Risks associated with agreeing acceleration

A

On the UPM project, the main residual risk following instructing acceleration is that the work may still have not been completed in time. Other risks are:
- increased costs of additional labour
- drop in quality if you need to reduce scope

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q
A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly