Health and Safety Flashcards

1
Q

RIDDOR

A

Reporting of Injuries, Diseases and Dangerous Occurences (2013).
Types of incidents:
- deaths
- injuries (fractures, amputations, loss of sight, crush, others)
- 7+ day incapacitation
- 3+ day incapacitation
- occupational diseases (carpal tunnel, vibration syndrome)
- dangerous occurrences (plant or equipment hitting power lines)
- Gas incidents

Who should report:
- responsible persons should submit reports under RIDDOR, such as the employer or the person in control of the premises.

Must keep a record of these incidents.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
1
Q

How do I ensure personal safety on site

A

I always adhere to the RICS Guidance Note Surveying Safely. This discusses topics such as risk assessments and the correct type of training. I ensure that I have completed any relevant training required.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How do I ensure security of personal possessions on site

A

I try to bring as little as possible. On my Level 34 Refurbishment project, I was based in the same office so I would only bring my PPE and a work phone to take pictures and/or contact anyone should there be an incident.
On my mains replacement programmes, I would store the items in the site office before going out into site.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

When have I used PPE on inspection

A

For a colleagues project (a cycle centre refurbishment in the basement), I was asked to have a look at something to ensure it was on track. I spoke with the Contractor to have a site induction and understand what PPE would be required. I wore a hard hat, high vis vest, boots, gloves and glasses.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What would I do if I believed there was asbestos

A

I would instruct work to stop until a survey could take place. If one had previously taken place, I would review that with a competent colleague who has a better knowledge of this topic, and discuss further.

I would ensure that a survey is undertaken if I was at all concerned about asbestos.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

what hazardous materials have I come across in my work

A

I am fortunate enough to have not come across any hazardous materials. What I would do is ensure that these are picked up in the PCI or CPP if we are aware of them. If they are found later in the project, I would ensure that a risk assessment is completed and the hazardous material is disposed of safely.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How did a pre-start meeting help to manage H&S

A

It formalised the discussions that we’ve had previously. On my Level 10 project, we discussed what was happening initially. Then, we discussed working hours, amenities, deliveries, and set out a set of rules regarding access to the site. On this project, it was identified that we needed furniture moves to happen whilst this was a CDM site, and during this pre-start meeting we were able to identify how this would work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

F10

A

Notification to the Health and Safety Executive that a project is occurring.

Must be notified when:
lionger than 30 working days and more than 20 workers at same time
exceed 500 person days

What must be included:
Summary of project
Effected areas
Timescales
Nominated parties (PD, PC, Employer) and contact information
Number of people on site
Number of Contractors on site

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Roles under CDM

A

Prinicipal Designer: prepares the Pre-Construction information. Responsible for identifying and managing pre-construction HS risks and information

Principal Contractor: Responsible for producing the Construction Phase Plan. Responsible for managing H&S risks during

Employer: owns the H&S file and the site.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

RICS Surveying Safely

A

Key points:
Safe person concept - each person assumes individual behavioural responsibility
Guidance on risk assessments
Workplace (office, on site) guidance for maintianing a safe working environment
occupation health

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the H&S file

A

Issued post-Construction
Has information about future constructin works including cleaning, maintenance, alteration.
Should include:
- Description of works carried out
- Residual hazards and how have been dealt with
- Structural principles
- Hazards associated with materials used
- Information about removal/dismantling of installed plant/equipment
-Services

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Asbestos

A

Types: crocidolite, amosite, chrysotile.
Commonly foud in: insulation, roofing, electrical/ventilations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Asbestos surveys

A

Management - standard survey. Locate asbestos. Minorly intrustive.

Refurb/Demo - before any refurb/demo work carried out. Locate and describe. Intrustive.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Asbestos Regulations

A

Control of Asbestos Regulations 2012
- Asbestos contained in a safe manner can be let in-situ.
- Training is required to engage in asbestos removal
Need to notify 14 days in advance for removal of Asbestos

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Fire Strategy on retail banking projects

A

Work with fire officer to ensure that project requirements are compliant with building fire and escape strategy. For example, my Level 34 Refurbishment project, I liaised with the fire safety team to ensure that the locks on the new doors were compliant with fire strategy.

Legislation: Fire Safety Order (2005) - risk assessment for offices and shops

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How did I review a method statement

A

I reviewed a method statement against the known parameters - working hours, durations, etc. as well as against my understanding of best practice. For example, I reviewed the method statements on my Ningwood mains replacement project to ensure that I was comfortable with how the Contractor would be managing access to the site, traffic management, how they would manage pedestrian interfaces, as well as their construction methodology. I reviewed my findings with the Principal Designer to align.