Construction Tech Flashcards

1
Q

Utilise knowledge of current regulations and design standards to ensure design compliance

A

Level 34 Refurbishment project: When installing surface mounted booking panels alongside meeting rooms, I ensured that we adhered to the requirements under building regs part M with regards to height.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
1
Q

How do I prepare annotated sketches/specs detailing how elements interact

A

I don’t really - I have prepared drawings where grommets need to go based on my knowledge, or highlighted areas where certain bits of work need to be done, but I try to stick my own area of competence and would consult with my design colleagues before issuing any drawings or specifications.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

MEP relevant to area of work

A

under floor power, HVAC, lighting, fresh air provisions, AV, IT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Construction materials

A

Water: worked with Polyethlene pipes, cast iron, ductile iron, galvanised iron
HSBC: mostly worked on CAT B fit outs, so built things like stud wall partitions, glazed partitions, carpeted flooring

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Various materials in relation to time/cost of the project

A

Certain material to form part of an eel screen. Mesh netting. Compared to alternatives, did not have a direct improvement on time/cost from a capex perspective, but it required significantly less cleaning than others and thus would have a lower opex over a 25 year period.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How delay and disruption to a construction activity impacted follow on activities and trades

A
  1. Trade availabilities - Level 10 refresh, a partition was not erected in time. Thus, the time that was booked the electrician to come in and do their works had to be pushed back and they were not available for another 2 weeks, resulting in a delay.
  2. Programme impacts: I assess the actual impacts by updating my master programme with expected times. I take great care to ensure that my programmes activities are as accurately linked as possible. I use this to compare against the contractor’s assessment.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Other items that need to be considered when working near a watercourse

A

Runoff into the river, flood risk, wildlife in the river, getting permission from the Environment Agency, impacting wildlife patters in the river, structural impacts of the river on your building

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What type of surveys would you use on a project

A

Environmental, asbestos, drainage, services, UXO, ground condition, archaeological,

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How do yo identify what surveys are required?

A

Context: in a pre-2000 building, 100% need an asbestos survey
History: if there has been sightings of endangered species on an area you’ll be working, you should get environmental surveys
General best practice: should always have certain ones done.
Specialists: wider members of the project team will have views on what is required
Client information: client provides certain information that will need to be validated.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Was there an alternative method other than trial holes

A

No. This was the best way to gather information about the ground condition and pipe location at the same time as this information was unclear.

I led a bit of an investigation into which areas NEEDED trial holes and which areas we knew would have corrosive ground based on what was in the surrounding areas (gas station within 100m for example)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Risks with trial holes

A

Disruptive (required road closures)
Took a while to get the results back due to lab backlog
Expensive to do

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Types of foundation

A

Piled foundation - piles put into ground to support load of building
Strip foundation - strip on outside of building put in place to spread load of building
Raft foundation - concrete slab put in place for entire footprint of building to spread the weight

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Name 5 building Regulations

A

Part A - Structure
Part B - Fire Safety
Part L - Heat loss/gain
Part M - Inclusive Environments
Part P - Electrical Safety

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Building Safety Act 2022

A

Introduced following tragic failures of building safety following Grenfell.

Applies to new or existing occupied builinds over 18 meters.
Creates new roles - building safety regulator and accountable person(s)

BSR: oversee safety/performance of buildings, set direction of industry-led competence, implement rew regulatory regime for higher risk buildings.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Surveys to be carried out for construction works

A

Drainage surveys
Ecological surveys
Environmental surveys
Arbocultural surveys
archaeological surveys
Unexploded ordnance surveys
utilities surveys
Asbestos surveys

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Different types of piles

A

Bored piles: create hole in ground, pour concrete in to cast in place

Driven piles: install piles by hammering or friction.

16
Q

Steel frames

A

Pros:
- faster
- predictable levels of quality
- Good under tension

Cons:
- no inherent fire safety
- volatility in market place
- requires skilled labor to erect

17
Q

Concrete frames

A

Pros:
- consistent price
- in-built fire safety
- good under compression

Cons:
- Has to be poured on site w/ curing period
- Requires larger foundations

18
Q

Building Information Modelling (BIM)

A

Process for creating and managing information on a construction project.

UK Govt has mandated BIM on public projects to Level 2. BIM has levels 1-3.

Benefits:
- Increased collaboration
- Increased information management
- clash detection to facilitate less mistakes once on site
- Design iterations

Negatives
- individual distrust
- Unfamiliartiy with system could cause issue

19
Q

Prefab - benefits/disadvantages

A

Benefits:
- Less risky
- items made in factory conditions
- faster

Disadvantages:
- design limitations
- issues take longer to resolve

20
Q
A