PROCUREMENT AND TENDERING Flashcards

1
Q

What are the different types of procurement route?

A
  • Traditional
  • Design and Build
  • Management Contracting
  • Single Stage
  • Two – Stage
  • Negotiated
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is traditional procurement?

A

Traditional
• (JCT Standard, Intermediate, Minor works contracts)
• Design-bid-build
• Contractor doesn’t take responsibility for design
• Design team (consultants) design the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is Design and Build procurement?

A

Design and Build
• (JCT Design and Build contract)
• Main contractor appointed to design and construct
• Contractor takes responsibility for design

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is management contracting?

A

Management Contractor
• Number of works contractors, contracted to a management contractor
• Appointed by a client early in the process
• Management contractor = principle.
• One contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is single stage tendering?

A
  • When enough information is required for the tendering party to submit a price against a design.
  • The contractor is then appointed to carry out the project works.
  • Priced competitively
  • No buildability input from contractor
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is two stage tendering?

A
  • Allows for early appointment of a contractor
  • Based on overheads, profit, schedule of rates, proposed team, programme, contract conditions e.g. insurance
  • Uses a PCSA until stage two, where contract is negotiated.
  • Contractor tenders works packages whilst designing.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is negotiated tendering?

A
  • Contractor appointed via PQQ.
  • Early involvement to help develop design.
  • Terms of the contract are developed later.
  • Lacks competitive aspect.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is included in a tender pack?

A

The form of contract and any amendments (so can be negotiated early)
Outline programme
Employers requirements
Tender pricing doc (or contract sum analysis on D&B)
Outline design

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What if a tender is received late?

A
  • Public projects – not accepted.

* Private – get written advice from client.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is included in the ER’s?

A
  • Occupational requirements
  • Architectural performance criteria
  • Services performance specifications
  • Branding guidelines
  • Conceptual design package
  • Test fits
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

How do you score tenders?

A
  • Tenders are scored against a weighted criterion, signed off by the employer.
  • This could include cost, proposed team, design, gut feel
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How would you manage unconscious bias?

A

Could review tenders blindly.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What if you find mistakes in tenders?

A

Two options:

  • Contractor either stands by price or withdraws
  • Contractor is given opportunity to review costs.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is a PQQ process?

A

Process prior to the competitive tender (or negotiated)
Larger selection of contractors
Enables employer to create shortlist of contractors for tender
Details include insurance, financial information, health and safety policy, ISO accreditation, experience on similar jobs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What information do you provide when giving feedback to contractors?

A
  • Feedback on team, presentation, approach

* Cannot disclose financial information.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the difference between a negotiated and competitive tender?

A

Negotiated – client negotiates with a single contractor

Competitive tender – client issues tender to a set of contractors to competitively submit a response.

17
Q

What was the process when utilising a negotiated tender?

A

Ensure contractor is capable of carrying out the role through a PQQ

All costs benchmarked against competitive rates.

18
Q

What is included in a benchmarking report?

A
  • Comparison of schedules and rates

* Comparisons of OHP and Prelims

19
Q

What is a PCSA?

A

Pre-construction services agreement - used in two stage tendering to appoint a contractor to aid with the design and buildability aspects of a project.

Is a JCT contract.

20
Q

What is a LOI?

A

Letter of Intent - document stating intent to enter into a contract at a later date.

Does not have substantial legal meaning.

21
Q

What guidance is there on tendering?

A

RICS Tendering Strategies

22
Q

What is construction management procurement?

A
  • Several trades directly employed by client.
  • Managed by construction manger
  • Acting as agent for client.
23
Q

What is a pre-tender estimate?

A
  • An estimate of construction costs before going to tender to ensure the client has sufficient funds.
24
Q

If a contractor asks for an extension what do you do?

A

Ensure that it is possible within the programme.

Ensure all contractors receive the same extension.

25
Q

What is OJEU?

A

Regulations for public projects
Public contracts must be published online
Must be competitively tendered

26
Q

What does a tender report contain?

A
  • Background
  • Scope
  • PQQ criteria
  • Tender evaluation
  • Rejection reasons
  • Recommendation reasons
  • Summary