CONTRACT PRACTICE Flashcards

1
Q

What is a contract?

A

A legally binding agreement between two or more parties.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is needed to create contractual relationships?

A

Offer, Acceptance, Consideration and Intention to enter into legal relationship

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the different forms of standard building contract available in the UK?

A

JCT
NEC
FIDIC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are some advantages and disadvantages of each? Where are they used?

A
  • JCT – most commonly used
  • NEC – more suited to engineering contracts
  • FIDIC – more suited to large international project e.g. Channel Tunnel
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the JCT and what are their suite of contracts?

A
Joint Contracts Tribunal, formed in 1931
Suit of Contracts includes:
•	Standard (with quants, without, with approx.)
•	Intermediate
•	Minor works
•	Design and Build
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the advantages with a standard form of contract? How is it formed?

A

The advantages of a Standard Building Contract include:
• Developed over a long period
• Has input from legal, contractor, local authority
• Has more case law
• Less costly and time consuming to produce

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is an intermediate Contract?

A
  • Contract for simple works without any major complex service adjustments
  • It is a form of traditional procurement
  • Design must be in place
  • Can have sectional completion
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is included in a payment notice?

A
  • Date
  • Issue number
  • Contract sum
  • Valuation sum
  • Valuation sum minus retention
  • Valuation sum minus amount previously certified
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the timelines for payment? Where can this information be found?

A

Interim valuation/applications date is stipulated in the contract, and is same day each month (or nearest business day).
- This is outlined in section 4 of the contract particulars

  • Contractor can submit their application, is 7 days to review.
  • CA/EA has 5 days from the due date to issue payment notice/cert.
    Employer has 14 days from the due date to issue payment.
  • Payless notice has to be issued 5 days before due date.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is Practical Completion? What does it Trigger?

A

When all works in the contract have been deemed to be completed and the client can take occupation.

Deminimus in nature.

  • It releases half of the retention
  • Ends the contractor’s liability for LD’s
  • Starts the defects liability period
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What documentation is required at PC?

A
  • Testing and commission certs
  • Health and safety files
  • Building control sign off
  • O&M’s
  • Clients insurance in place
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is sectional completion and what is partial possession?

A
  • Sectional completion is defined in the contract
  • Partial possession is not determined in the contract, and is up to the contractors discretion to grant.
  • Both will mean that section is ‘practically complete’
  • LD’s will cease for that period.
  • Contractors decide whether to grant partial possession.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are staged payments?

A

OPTION A in the contract
Pre-agreed stages defined in the contract particulars – milestones in the project
On completion of a stage, payment is awarded.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What were the risks to the client by using staged payments?

A

The risk was this could leave the client exposed if they had not completed an amount of work in line with the payment amount.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the interim payment process? Where is this specified in the contract?

A

OPTION B

In comparison, a 2-weekly valuation and interim payment solution would be the optimum, as this would check.

This is outlined in the contract particulars and timings in section 4 of the contract conditions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What guidance documents are available?

A
  • RICS – Appropriate Contract Selection

* JCT – Guide to selecting the appropriate JCT

17
Q

What is the difference between an Employers Agent and a Contract Administrator?

A

CA = Standard form/ traditional of contract. Role only takes place when in contract. Administer the contract impartially.

EA = D&B role takes place before contract.

18
Q

What is the Housing, Grants and Regeneration Act 1996?

A

Ensure payments are made promptly

Any project over 45days must have interim payments

19
Q

What is a collateral warranty?

A

A side agreement which established a contractual link between two parties which would not otherwise exist.

  • Subcontractor warranties to client.
20
Q

What impacts the clients choice of contract?

A
  • Size, value & type of project
  • Appetite for design risk
  • Need for cost certainty
  • Employers experience
  • Scope for design change
21
Q

What would you include when pricing an EOT?

A
  • Prolongation of prelims
  • Subcontractor mobilisation costs
  • Management staff, security, cleaners etc
22
Q

Why use a JCT minor works contract?

A
  • Adopted on smaller more basic construction projects where the work is of a straightforward nature.
  • Limited provision for sectional completion.
  • Suitable for traditional forms of procurement
23
Q

When use a JCT D&B contract?

A
  • Used for projects where the main contractor retains risk for the design and construction.
  • When client has less appetite for risk.
  • Contain detailed provisions for SC and insurances.
24
Q

What is force majeure?

A

Certain events beyond the control of the parties.

War, Hostility etc

25
Q

What are relevant events? and example?

A

An event on or off site that delays completion of the works.

E.g. variations, late possession of site, adverse weather.

Contractor is entitled to claim an extension of time.

26
Q

What is a relevant matter? and example?

A

A relevant matter is a matter for which the client is responsible for affecting the progress of works.

  • Delays in receiving instructions
  • Discrepancies in the contract docs
  • Disruption by the client
  • Issued relating to CDM.

Contractor is entitled to claim direct loss and / or expense.