HEALTH AND SAFETY Flashcards
What did you take away from the Surveying Safely guidance note 2018?
‘Safe person concept’ each individual must assume responsibility for their own, their colleagues and others health and safety whilst at work. Lots of invaluable information.
What is best practice when visiting site?
- Notifying team members when you are visiting site
- Signing in and out
- Wearing correct PPE.
What do you do when you visit site for the first time?
Site induction from constriction manager / principal designer.
You mention you saw a site operative undertaking hot works without the necessary PPE, can you please just elaborate on what you did when you saw that?
- Asked them to stop works immediately
- Requested construction manager to re-induct the worker
- Notified the PD.
What documentation needs to be clearly displayed on site?
Construction phase plan, emergency routes, first aid information.
What is the HSWA 1974?
- Overarching piece of health and safety legislation
- Section 2 - Outlines employers must “ensure so far as reasonably practicable the health, safety and welfare at work of all their employees”
- Section 3 - employer must as far as reasonably practicable that persons who are not employees e.g. public, contractors, visitors
What is the role of HSE?
The health and safety executive is the body responsible for promoting, regulating and enforcing health, safety and welfare and provide research for occupational risks.
What is RICS gudance?
Surveying Safely
What is COSHH?
Control of Substances Hazardous to Health
Hold a COSHH assessment form
What is RIDDOR?
Reporting of Injuries Diseases and Dangerous Occurrences Regulation 2013
What is CDM 2015?
- Construction Design Management 2015
- Main set of regulations for health, safety and welfare in construction
- Outlines roles of each duty holder
What were the most recent changes to CDM 2015?
More onus on the client.
Must appoint a PC and PD.
Construction phase plan needed for all projects, not just notifiable.
What is the clients responsibilty?
- Sign F10
- Issue site / project information
- Appoint a Principal Designer
- Appoint Principal Contractor
What is the PD’s responsibilty?
- Collate pre-construction information
- Co-ordinate health and safety in design pre-construction
- Collate H&S file on completion of works.
What PPE would you expect to see on a site?
5 point PPE
- Gloves
- Hard hat
- High vis
- Eye protection
- Safety boots